21-00119-00-RS
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Iroquois Paving Corporation Low bidder | $480,977 | ||
| 2 | D. Construction, Inc. | $496,123 | +3.1% | |
| 3 | Gallagher Asphalt Corporation | $521,368 | +8.4% | |
| 4 | K-Five Construction Corporation | $551,833 | +14.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Iroquois Paving… | #2 D. Construction… | #3 Gallagher Aspha… | #4 K-Five Construc… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X4421672 | CL D PATCH T2 11 SP | 5 | SQ YD | $300.00 | $1,000.00 | $600.00 | $500.00 | |
| 2 | Z0004522 | HMA DRIVEWAY PAVT 6 | 67 | SQ YD | $90.00 | $55.00 | $110.00 | $79.50 | |
| 3 | Z0017400 | DRAIN UTIL STR ADJ | 40 | EACH | $850.00 | $700.00 | $855.00 | $855.00 | |
| 4 | Z0017700 | DRAIN UTIL STR RECON | 1 | EACH | $1,700.00 | $1,500.00 | $1,700.00 | $1,700.00 | |
| 5 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $20.00 | $25.00 | $20.00 | $20.00 | |
| 6 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $3,500.00 | $15,000.00 | $4,200.00 | $1,100.00 | |
| 7 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 8 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 9 | 21101615 | TOPSOIL F & P 4 | 425 | SQ YD | $7.00 | $8.80 | $7.00 | $15.00 | |
| 10 | 25200110 | SODDING SALT TOLERANT | 425 | SQ YD | $10.00 | $13.75 | $10.00 | $18.60 | |
| 11 | 25200200 | SUPPLE WATERING | 13 | UNIT | $0.0100 | $110.00 | $0.0100 | $35.00 | |
| 12 | 28000250 | TEMP EROS CONTR SEED | 10 | POUND | $6.00 | $6.60 | $6.00 | $15.00 | |
| 13 | 28000510 | INLET FILTERS | 14 | EACH | $215.00 | $198.00 | $215.00 | $225.00 | |
| 14 | 35101600 | AGG BASE CSE B 4 | 566 | SQ YD | $3.60 | $3.96 | $3.60 | $16.00 | |
| 15 | 35800100 | PREPARATION OF BASE | 121 | SQ YD | $0.0100 | $5.00 | $15.00 | $0.0100 | |
| 16 | 35800200 | AGG BASE REPAIR | 46 | TON | $0.0100 | $40.00 | $50.00 | $5.00 | |
| 17 | 40201000 | AGGREGATE-TEMP ACCESS | 5 | TON | $30.00 | $33.00 | $30.00 | $30.00 | |
| 18 | 40600290 | BIT MATLS TACK CT | 2,508 | POUND | $0.0100 | $0.0100 | $2.00 | $0.0100 | |
| 19 | 40600370 | LONG JOINT SEALANT | 5,129 | FOOT | $3.00 | $4.94 | $3.00 | $3.35 | |
| 20 | 40600400 | MIX CR JTS FLANGEWYS | 5 | TON | $0.0100 | $0.0100 | $1,400.00 | $450.00 | |
| 21 | 40600982 | HMA SURF REM BUTT JT | 55 | SQ YD | $0.0100 | $15.00 | $20.00 | $45.00 | |
| 22 | 40603200 | P HMA BC IL-4.75 N50 | 483 | TON | $130.00 | $107.00 | $135.00 | $147.26 | |
| 23 | 40604060 | HMA SC IL-9.5 D N50 | 965 | TON | $110.00 | $77.00 | $94.00 | $121.38 | |
| 24 | 42300300 | PCC DRIVEWAY PAVT 7 | 86 | SQ YD | $99.00 | $108.90 | $99.00 | $99.00 | |
| 25 | 42400200 | PC CONC SIDEWALK 5 | 3,641 | SQ FT | $10.00 | $11.00 | $10.00 | $10.00 | |
| 26 | 42400400 | PC CONC SIDEWALK 7 | 1,442 | SQ FT | $12.00 | $13.20 | $12.00 | $12.00 | |
| 27 | 42400800 | DETECTABLE WARNINGS | 140 | SQ FT | $30.00 | $33.00 | $30.00 | $30.00 | |
| 28 | 44000157 | HMA SURF REM 2 | 11,145 | SQ YD | $3.50 | $2.40 | $3.05 | $3.38 | |
| 29 | 44000200 | DRIVE PAVEMENT REM | 273 | SQ YD | $29.00 | $29.70 | $32.00 | $27.00 | |
| 30 | 44000500 | COMB CURB GUTTER REM | 840 | FOOT | $10.00 | $11.00 | $10.00 | $10.00 | |
| 31 | 44000600 | SIDEWALK REM | 5,216 | SQ FT | $2.00 | $2.20 | $2.00 | $2.00 | |
| 32 | 44201761 | CL D PATCH T1 10 | 4 | SQ YD | $200.00 | $200.00 | $405.00 | $240.05 | |
| 33 | 44201765 | CL D PATCH T2 10 | 29 | SQ YD | $105.00 | $156.00 | $245.00 | $240.05 | |
| 34 | 44201769 | CL D PATCH T3 10 | 58 | SQ YD | $95.00 | $156.00 | $240.00 | $240.05 | |
| 35 | 44201771 | CL D PATCH T4 10 | 30 | SQ YD | $95.00 | $156.00 | $186.00 | $240.05 | |
| 36 | 48101498 | AGGREGATE SHLDS B 4 | 51 | SQ YD | $60.00 | $20.00 | $79.00 | $57.08 | |
| 37 | 60601805 | CONC CURB TRANS | 30 | FOOT | $40.00 | $44.00 | $54.00 | $40.00 | |
| 38 | 60603800 | COMB CC&G TB6.12 | 11 | FOOT | $40.00 | $44.00 | $59.00 | $40.00 | |
| 39 | 60608562 | COMB CC&G TM4.12 | 802 | FOOT | $45.00 | $38.50 | $45.00 | $35.00 | |
| 40 | 67100100 | MOBILIZATION | 1 | L SUM | $10,000.00 | $30,000.00 | $25,005.38 | $31,000.00 | |
| 41 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $23,950.00 | $4,900.00 | $6,000.00 | |
| 42 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | |
| 43 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $5,000.00 | $1.00 | $1,650.00 | $1,900.00 | |
| 44 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1,650.00 | $1,900.00 | |
| 45 | 70300100 | SHORT TERM PAVT MKING | 1,886 | FOOT | $1.25 | $0.0100 | $3.20 | $1.50 | |
| 46 | 70300150 | SHRT TRM PAVT MK REM | 686 | SQ FT | $1.75 | $0.0100 | $0.0100 | $1.00 | |
| 47 | 72000100 | SIGN PANEL T1 | 95 | SQ FT | $25.00 | $44.00 | $35.00 | $40.37 | |
| 48 | 72400200 | REMOV SIN PAN ASSY TB | 13 | EACH | $100.00 | $192.50 | $115.00 | $132.65 | |
| 49 | 72400310 | REMOV SIGN PANEL T1 | 28 | SQ FT | $25.00 | $27.50 | $15.00 | $17.30 | |
| 50 | 72900200 | METAL POST TY B | 137 | FOOT | $25.00 | $16.50 | $10.65 | $12.28 | |
| 51 | 78000100 | THPL PVT MK LTR & SYM | 224 | SQ FT | $7.00 | $5.50 | $5.00 | $5.00 | |
| 52 | 78000200 | THPL PVT MK LINE 4 | 7,544 | FOOT | $0.8500 | $0.9900 | $0.9000 | $0.9000 | |
| 53 | 78000400 | THPL PVT MK LINE 6 | 442 | FOOT | $1.75 | $1.49 | $1.35 | $1.35 | |
| 54 | 78000600 | THPL PVT MK LINE 12 | 170 | FOOT | $3.50 | $2.97 | $2.70 | $2.70 | |
| 55 | 78000650 | THPL PVT MK LINE 24 | 168 | FOOT | $7.00 | $5.50 | $5.00 | $5.00 | |
| 56 | 88600600 | DET LOOP REPL | 366 | FOOT | $17.50 | $19.09 | $18.00 | $18.00 |