16-00016-00-SW
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Alliance Contractors, Inc. Low bidder | $443,926 | ||
| 2 | A Lamp Concrete Contractors, Inc. | $529,913 | +19.4% | |
| 3 | Phoenix Corporation of the Quad Cities | $565,746 | +27.4% | |
| 4 | Copenhaver Construction, Inc. | $634,854 | +43.0% | |
| 5 | Berger Excavating Contractors, Inc. | $740,202 | +66.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Alliance Contra… | #2 A Lamp Concrete… | #3 Phoenix Corpora… | #4 Copenhaver Cons… | #5 Berger Excavati… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | A2006516 | T-QUERCUS BICOL 2 | 3 | EACH | $475.00 | $570.00 | $500.00 | $900.00 | $475.00 | |
| 2 | B0001716 | T-AMEL X GF AP 2 | 6 | EACH | $520.00 | $624.00 | $550.00 | $900.00 | $520.00 | |
| 3 | B2006116 | T-SYRG PEK M TF 2 | 6 | EACH | $475.00 | $570.00 | $500.00 | $900.00 | $475.00 | |
| 4 | XX008550 | REM REPL STONE RIPRAP | 69 | SQ YD | $65.00 | $150.00 | $40.00 | $110.00 | $140.00 | |
| 5 | XX009325 | TEMPORARY FLOW BYPASS | 1 | L SUM | $37,725.00 | $1,000.00 | $13,500.00 | $45,000.00 | $75,000.00 | |
| 6 | X0326806 | WASHOUT BASIN | 1 | L SUM | $750.00 | $100.00 | $1,000.00 | $1,000.00 | $1,500.00 | |
| 7 | X0327487 | TRI GEOGRID REINF T1 | 62 | SQ YD | $12.00 | $10.00 | $5.00 | $15.00 | $16.00 | |
| 8 | X0327584 | GRAD& SHAP SHLDRS SPL | 420 | FOOT | $10.00 | $10.00 | $12.00 | $25.00 | $32.00 | |
| 9 | X0964700 | SHOULDERS SPL | 110 | SQ YD | $90.00 | $90.00 | $90.00 | $75.00 | $130.00 | |
| 10 | X2130010 | EXPLOR TRENCH SPL | 50 | FOOT | $10.00 | $10.00 | $10.00 | $20.00 | $51.00 | |
| 11 | X4021000 | TEMP ACCESS- PRIV ENT | 4 | EACH | $200.00 | $20.00 | $800.00 | $120.00 | $800.00 | |
| 12 | X4810200 | AGGREGATE SHLD REMOVL | 50 | CU YD | $10.00 | $35.00 | $40.00 | $10.00 | $95.00 | |
| 13 | X6026624 | VALVE BOX ADJ SPL | 3 | EACH | $250.00 | $350.00 | $400.00 | $600.00 | $650.00 | |
| 14 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $19,750.00 | $56,000.00 | $29,000.00 | $79,000.00 | $10,000.00 | |
| 15 | X8440116 | RELOC EX LT UNIT SPL | 1 | EACH | $8,538.00 | $7,500.00 | $5,500.00 | $10,000.00 | $9,100.00 | |
| 16 | X8780105 | CONC FDN SPL | 6 | EACH | $1.00 | $1,500.00 | $1,000.00 | $500.00 | $1,750.00 | |
| 17 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,920.00 | $6,500.00 | $7,000.00 | $19,000.00 | $9,500.00 | |
| 18 | Z0029604 | HEADWALL REMOVAL | 7 | EACH | $250.00 | $3,000.00 | $600.00 | $2,500.00 | $1,850.00 | |
| 19 | 20100110 | TREE REMOV 6-15 | 120 | UNIT | $18.00 | $22.50 | $45.00 | $25.00 | $18.00 | |
| 20 | 20100210 | TREE REMOV OVER 15 | 116 | UNIT | $39.00 | $48.75 | $50.00 | $39.00 | $39.00 | |
| 21 | 20101000 | TEMPORARY FENCE | 240 | FOOT | $5.00 | $1.00 | $14.00 | $3.00 | $7.00 | |
| 22 | 20101200 | TREE ROOT PRUNING | 5 | EACH | $180.00 | $220.00 | $200.00 | $20.00 | $180.00 | |
| 23 | 20101300 | TREE PRUN 1-10 | 5 | EACH | $40.00 | $100.00 | $125.00 | $20.00 | $40.00 | |
| 24 | 20101350 | TREE PRUN OVER 10 | 5 | EACH | $140.00 | $180.00 | $175.00 | $20.00 | $140.00 | |
| 25 | 20101600 | POTASSIUM FERT NUTR | 55 | POUND | $3.00 | $3.45 | $3.00 | $4.00 | $3.00 | |
| 26 | 20200100 | EARTH EXCAVATION | 135 | CU YD | $10.00 | $55.00 | $62.00 | $50.00 | $70.00 | |
| 27 | 20201200 | REM & DISP UNS MATL | 385 | CU YD | $15.00 | $55.00 | $41.00 | $40.00 | $70.00 | |
| 28 | 20400800 | FURNISHED EXCAVATION | 65 | CU YD | $15.00 | $20.00 | $75.00 | $10.00 | $35.00 | |
| 29 | 20700220 | POROUS GRAN EMBANK | 25 | CU YD | $50.00 | $20.00 | $155.00 | $49.00 | $95.00 | |
| 30 | 20800150 | TRENCH BACKFILL | 40 | CU YD | $50.00 | $50.00 | $95.00 | $35.00 | $60.00 | |
| 31 | 21101615 | TOPSOIL F & P 4 | 2,915 | SQ YD | $4.80 | $5.50 | $5.00 | $7.00 | $6.00 | |
| 32 | 25000110 | SEEDING CL 1A | 0.7 | ACRE | $2,400.00 | $2,760.00 | $2,500.00 | $4,000.00 | $2,500.00 | |
| 33 | 25000400 | NITROGEN FERT NUTR | 55 | POUND | $3.00 | $3.45 | $3.00 | $4.00 | $3.00 | |
| 34 | 25100630 | EROSION CONTR BLANKET | 2,915 | SQ YD | $1.40 | $1.65 | $1.60 | $3.00 | $1.65 | |
| 35 | 28000250 | TEMP EROS CONTR SEED | 30 | POUND | $5.00 | $5.75 | $5.00 | $5.00 | $5.00 | |
| 36 | 28000305 | TEMP DITCH CHECKS | 135 | FOOT | $9.00 | $10.35 | $10.00 | $15.00 | $10.00 | |
| 37 | 28000400 | PERIMETER EROS BAR | 565 | FOOT | $2.20 | $1.00 | $3.00 | $3.00 | $4.00 | |
| 38 | 28200200 | FILTER FABRIC | 65 | SQ YD | $1.00 | $10.00 | $5.50 | $5.00 | $15.00 | |
| 39 | 31101200 | SUB GRAN MAT B 4 | 1,070 | SQ YD | $5.00 | $6.50 | $21.00 | $8.00 | $16.00 | |
| 40 | 31101600 | SUB GRAN MAT B 8 | 110 | SQ YD | $10.00 | $10.00 | $38.00 | $15.00 | $21.00 | |
| 41 | 40600275 | BIT MATLS PR CT | 301 | POUND | $1.00 | $0.0100 | $0.0100 | $0.1000 | $1.00 | |
| 42 | 40600290 | BIT MATLS TACK CT | 242 | POUND | $1.00 | $0.0100 | $0.0100 | $0.1000 | $1.00 | |
| 43 | 40600982 | HMA SURF REM BUTT JT | 33 | SQ YD | $1.00 | $10.00 | $23.00 | $95.00 | $1.00 | |
| 44 | 40603335 | HMA SC "D" N50 | 80 | TON | $155.00 | $165.00 | $400.00 | $222.00 | $155.00 | |
| 45 | 42400200 | PC CONC SIDEWALK 5 | 9,627 | SQ FT | $6.75 | $8.65 | $7.80 | $7.00 | $8.00 | |
| 46 | 42400800 | DETECTABLE WARNINGS | 10 | SQ FT | $40.00 | $45.00 | $50.00 | $40.00 | $40.00 | |
| 47 | 44000157 | HMA SURF REM 2 | 409 | SQ YD | $21.00 | $10.00 | $7.25 | $35.00 | $21.00 | |
| 48 | 44000200 | DRIVE PAVEMENT REM | 96 | SQ YD | $25.00 | $12.00 | $16.00 | $15.00 | $13.00 | |
| 49 | 44201711 | CL D PATCH T4 5 | 35 | SQ YD | $85.00 | $60.00 | $110.00 | $130.00 | $190.00 | |
| 50 | 44300200 | STRIP REF CR CON TR | 214 | FOOT | $2.50 | $6.00 | $3.50 | $3.00 | $2.50 | |
| 51 | 48101200 | AGGREGATE SHLDS B | 72 | TON | $72.00 | $45.00 | $103.00 | $80.00 | $70.00 | |
| 52 | 50105220 | PIPE CULVERT REMOV | 162 | FOOT | $15.00 | $5.00 | $32.00 | $50.00 | $25.00 | |
| 53 | 50901720 | BICYCLE RAILING | 50 | FOOT | $341.45 | $355.00 | $215.00 | $340.00 | $330.00 | |
| 54 | 51100300 | SLOPE WALL 6 | 45 | SQ YD | $90.00 | $110.00 | $115.00 | $100.00 | $385.00 | |
| 55 | 54001001 | BOX CUL END SEC C1 | 2 | EACH | $10,680.00 | $13,500.00 | $22,000.00 | $7,600.00 | $8,500.00 | |
| 56 | 54010606 | PCBC 6X6 | 45 | FOOT | $1,335.00 | $925.00 | $1,050.00 | $850.00 | $3,350.00 | |
| 57 | 542A0217 | P CUL CL A 1 12 | 115 | FOOT | $60.00 | $105.00 | $86.00 | $85.00 | $75.00 | |
| 58 | 54213657 | PRC FLAR END SEC 12 | 7 | EACH | $775.00 | $1,500.00 | $1,150.00 | $900.00 | $1,550.00 | |
| 59 | 59300100 | CONTR LOW-STRENG MATL | 140 | CU YD | $104.00 | $130.00 | $200.00 | $250.00 | $190.00 | |
| 60 | 60207605 | CB TC T8G | 1 | EACH | $2,100.00 | $2,000.00 | $2,200.00 | $3,900.00 | $1,825.00 | |
| 61 | 60255500 | MAN ADJUST | 1 | EACH | $495.00 | $350.00 | $1,200.00 | $700.00 | $775.00 | |
| 62 | 60600605 | CONC CURB TB | 195 | FOOT | $40.50 | $40.00 | $40.00 | $30.00 | $75.00 | |
| 63 | 63000003 | SPBGR TY A 9FT POSTS | 104 | FOOT | $27.88 | $39.00 | $25.00 | $37.00 | $28.00 | |
| 64 | 63000350 | LSG OV CUL 12'6" SPAN | 75 | FOOT | $26.90 | $58.00 | $40.00 | $60.00 | $29.00 | |
| 65 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $2,610.00 | $4,000.00 | $3,300.00 | $3,800.00 | $2,610.00 | |
| 66 | 63200310 | GUARDRAIL REMOV | 129 | FOOT | $8.50 | $10.00 | $11.00 | $11.00 | $10.00 | |
| 67 | 67100100 | MOBILIZATION | 1 | L SUM | $26,575.00 | $30,000.00 | $39,500.47 | $38,000.00 | $43,530.25 | |
| 68 | 70107025 | CHANGEABLE MESSAGE SN | 180 | CAL DA | $30.00 | $10.00 | $20.00 | $33.00 | $30.00 | |
| 69 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $35.00 | $51.50 | $50.00 | $55.00 | $35.00 | |
| 70 | 78000200 | THPL PVT MK LINE 4 | 645 | FOOT | $4.50 | $6.25 | $5.55 | $9.00 | $6.00 | |
| 71 | 78200005 | GRDRAIL REF TYPE A | 8 | EACH | $12.00 | $10.25 | $10.00 | $11.00 | $15.00 |