$7.68Avg low bid / SQ YD
$6.55Avg of all bids
—Avg engineer's estimate
6Jobs · 16,471 SQ YD
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 4 | 9,932 | $8.66 | $7.24 |
| 2025 | 2 | 6,539 | $6.20 | $5.66 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2026 | 61M51 | CookDistrict 1 | 2,432 SQ YD | $7.55 | Martam Construction Incorporated |
| Apr 24, 2026 | 76V05 | RandolphDistrict 8 | 5,783 SQ YD | $10.00 | G. M. Sipes Construction, Inc. |
| Jan 16, 2026 | 61M07 | MchenryDistrict 1 | 102 SQ YD | $17.50 | Curran Contracting Company |
| Jan 16, 2026 | 61M01 | WillDistrict 1 | 1,615 SQ YD | $5.00 | Austin Tyler Construction, Inc. |
| Jun 13, 2025 | 87874 | KankakeeDistrict 3 | 3,037 SQ YD | $7.00 | M & J Underground Inc. |
| Apr 25, 2025 | 85774 | Rock IslandDistrict 2 | 3,502 SQ YD | $5.50 | Valley Construction Co. |