17-00131-00-SW
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sumit Construction Co., Inc. Low bidder | $54,111 | ||
| 2 | Copenhaver Construction, Inc. | $69,151 | +27.8% | |
| 3 | Alliance Contractors, Inc. | $77,480 | +43.2% | |
| 4 | A Lamp Concrete Contractors, Inc. | $79,186 | +46.3% | |
| 5 | Scanlon Excavating & Concrete, Inc. | $91,717 | +69.5% | |
| 6 | Landmark Contractors, Inc. | $99,317 | +83.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sumit Construct… | #2 Copenhaver Cons… | #3 Alliance Contra… | #4 A Lamp Concrete… | #5 Scanlon Excavat… | #6 Landmark Contra… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0100002 | GRADING & SHAPING SPL | 183 | SQ YD | $10.00 | $15.00 | $5.00 | $20.00 | $10.00 | $20.00 | |
| 2 | X0323569 | STEEL POST REMOVAL | 1 | EACH | $150.00 | $400.00 | $100.00 | $250.00 | $150.00 | $400.00 | |
| 3 | X0326275 | RR ROW ENTRY PERMIT | 1 | EACH | $1,000.00 | $1,500.00 | $3,500.00 | $3,500.00 | $15,000.00 | $2,500.00 | |
| 4 | X2800500 | INLET PROTECTION SPL | 1 | EACH | $250.00 | $20.00 | $200.00 | $200.00 | $250.00 | $350.00 | |
| 5 | X4240800 | DETECTABLE WARN SPL | 20 | SQ FT | $15.00 | $50.00 | $1.00 | $50.00 | $40.00 | $20.00 | |
| 6 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,000.00 | $5,000.00 | $2,500.00 | $3,500.00 | $7,500.00 | $4,663.78 | |
| 7 | Z0018500 | DRAINAGE STR CLEANED | 1 | EACH | $500.00 | $50.00 | $400.00 | $200.00 | $500.00 | $700.00 | |
| 8 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $6,500.00 | $6,000.00 | $7,000.00 | $5,000.00 | $3,500.00 | $8,000.00 | |
| 9 | Z0064800 | SELECTIVE CLEARING | 1 | UNIT | $1,000.00 | $2,000.00 | $150.00 | $3,500.00 | $5,000.00 | $2,351.49 | |
| 10 | 20101100 | TREE TRUNK PROTECTION | 4 | EACH | $100.00 | $60.00 | $250.00 | $10.00 | $250.00 | $315.00 | |
| 11 | 20101200 | TREE ROOT PRUNING | 3 | EACH | $150.00 | $30.00 | $200.00 | $10.00 | $100.00 | $315.00 | |
| 12 | 20200100 | EARTH EXCAVATION | 100 | CU YD | $42.00 | $35.00 | $25.00 | $20.00 | $55.00 | $123.70 | |
| 13 | 21101615 | TOPSOIL F & P 4 | 300 | SQ YD | $5.00 | $7.00 | $10.00 | $2.00 | $11.00 | $15.65 | |
| 14 | 25200100 | SODDING | 300 | SQ YD | $12.00 | $7.00 | $13.00 | $5.00 | $20.00 | $20.38 | |
| 15 | 25200200 | SUPPLE WATERING | 4 | UNIT | $50.00 | $0.0100 | $75.00 | $1.00 | $100.00 | $117.58 | |
| 16 | 28000400 | PERIMETER EROS BAR | 270 | FOOT | $3.00 | $2.00 | $4.50 | $1.00 | $4.00 | $7.05 | |
| 17 | 31101180 | SUB GRAN MAT B 2 | 176 | SQ YD | $3.00 | $5.00 | $4.00 | $9.50 | $15.00 | $12.75 | |
| 18 | 31101200 | SUB GRAN MAT B 4 | 54 | SQ YD | $6.50 | $12.00 | $8.00 | $20.00 | $31.00 | $23.50 | |
| 19 | 42101300 | PROTECTIVE COAT | 230 | SQ YD | $3.00 | $1.00 | $0.0100 | $1.00 | $1.00 | $7.00 | |
| 20 | 42300200 | PCC DRIVEWAY PAVT 6 | 45 | SQ YD | $62.00 | $68.00 | $103.00 | $105.00 | $75.00 | $115.00 | |
| 21 | 42400200 | PC CONC SIDEWALK 5 | 1,580 | SQ FT | $8.00 | $9.00 | $9.50 | $8.85 | $7.00 | $12.50 | |
| 22 | 42400300 | PC CONC SIDEWALK 6 | 100 | SQ FT | $9.00 | $12.00 | $11.45 | $10.00 | $10.00 | $16.50 | |
| 23 | 44000200 | DRIVE PAVEMENT REM | 54 | SQ YD | $28.00 | $17.00 | $50.00 | $15.00 | $22.00 | $25.55 | |
| 24 | 44000600 | SIDEWALK REM | 130 | SQ FT | $3.00 | $5.00 | $10.00 | $4.00 | $10.00 | $6.00 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $3,000.00 | $3,900.00 | $5,000.00 | $4,500.00 | $5,500.00 | $7,700.00 | |
| 26 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $3,000.00 | $14,000.00 | $17,500.00 | $22,400.00 | $5,000.00 | $3,919.15 | |
| 27 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $2,000.00 | $100.00 | $1.00 | $1.00 | $1,500.00 | $156.76 | |
| 28 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $200.00 | $100.00 | $1.00 | $1.00 | $1,500.00 | $156.76 | |
| 29 | 78000650 | THPL PVT MK LINE 24 | 14 | FOOT | $30.00 | $140.00 | $125.00 | $215.00 | $260.00 | $195.96 |