14-00433-00-BR
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Alliance Contractors, Inc. Low bidder | $491,679 | ||
| 2 | Lorig Construction Company | $561,355 | +14.2% | |
| 3 | Areatha Construction Co., Inc. | $569,311 | +15.8% | |
| 4 | Civil Constructors, Inc. | $603,945 | +22.8% | |
| 5 | Sjostrom & Sons, Inc. | $634,276 | +29.0% | |
| 6 | Norvilla, LLC | $676,999 | +37.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Alliance Contra… | #2 Lorig Construct… | #3 Areatha Constru… | #4 Civil Construct… | #5 Sjostrom & Sons… | #6 Norvilla, LLC |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0322128 | MEMBR WTRPR B STRUCT | 130 | SQ YD | $56.73 | $55.00 | $55.00 | $55.00 | $51.13 | $68.40 | |
| 2 | X2130010 | EXPLOR TRENCH SPL | 100 | FOOT | $1.00 | $35.00 | $23.80 | $12.00 | $39.93 | $43.10 | |
| 3 | X2511630 | EROS CONT BLANKET SPL | 404 | SQ YD | $2.25 | $1.80 | $2.25 | $1.55 | $4.11 | $2.70 | |
| 4 | X4024000 | TEMP ACCESS- FLD ENT | 1 | EACH | $1.00 | $350.00 | $2,330.00 | $2,000.00 | $3,408.33 | $2,658.35 | |
| 5 | X6310088 | TRAF BAR TERM T6A SPL | 4 | EACH | $3,683.00 | $3,600.00 | $3,683.00 | $3,683.00 | $3,128.22 | $4,235.45 | |
| 6 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $7,000.00 | $12,000.00 | $12,500.00 | $10,900.00 | $16,534.89 | $12,535.00 | |
| 7 | X7015005 | CHANGEABLE MESSAGE SN | 30 | CAL DA | $25.00 | $25.00 | $40.00 | $50.00 | $67.03 | $57.50 | |
| 8 | X7810300 | REC REF PVT MARKER | 12 | EACH | $145.00 | $145.00 | $145.00 | $145.00 | $27.93 | $174.00 | |
| 9 | Z0007124 | STEEL RAILING SPL | 66 | FOOT | $259.47 | $460.00 | $273.45 | $259.47 | $435.72 | $298.40 | |
| 10 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $4,823.54 | $10,000.00 | $7,490.00 | $13,000.00 | $5,418.53 | $7,665.65 | |
| 11 | Z0022800 | FENCE REMOVAL | 250 | FOOT | $4.00 | $7.00 | $4.00 | $4.00 | $5.89 | $3.45 | |
| 12 | Z0030850 | TEMP INFO SIGNING | 55 | SQ FT | $15.00 | $15.00 | $20.00 | $15.00 | $21.83 | $17.25 | |
| 13 | Z0066400 | STAB DRIVEWAYS 6 | 17 | SQ YD | $176.50 | $75.00 | $152.50 | $131.50 | $84.46 | $151.25 | |
| 14 | 20100110 | TREE REMOV 6-15 | 84 | UNIT | $27.00 | $30.00 | $27.00 | $30.00 | $33.51 | $29.70 | |
| 15 | 20100210 | TREE REMOV OVER 15 | 27 | UNIT | $36.00 | $30.00 | $36.00 | $30.00 | $55.86 | $39.60 | |
| 16 | 20200100 | EARTH EXCAVATION | 435 | CU YD | $5.00 | $25.00 | $47.30 | $51.00 | $40.29 | $57.80 | |
| 17 | 20201200 | REM & DISP UNS MATL | 125 | CU YD | $5.00 | $45.00 | $64.85 | $33.00 | $35.26 | $61.00 | |
| 18 | 20300100 | CHANNEL EXCAVATION | 70 | CU YD | $5.00 | $65.00 | $80.45 | $33.00 | $51.68 | $87.60 | |
| 19 | 20400800 | FURNISHED EXCAVATION | 140 | CU YD | $5.00 | $15.00 | $15.25 | $20.00 | $31.17 | $71.60 | |
| 20 | 20800150 | TRENCH BACKFILL | 7 | CU YD | $100.00 | $42.00 | $60.00 | $35.00 | $142.69 | $245.00 | |
| 21 | 21001000 | GEOTECH FAB F/GR STAB | 396 | SQ YD | $1.00 | $2.50 | $4.95 | $2.00 | $6.18 | $6.90 | |
| 22 | 21101505 | TOPSOIL EXC & PLAC | 395 | CU YD | $10.00 | $45.00 | $34.65 | $36.00 | $26.25 | $50.95 | |
| 23 | 25000210 | SEEDING CL 2A | 0.5 | ACRE | $2,500.00 | $2,000.00 | $2,500.00 | $2,800.00 | $3,463.39 | $3,894.00 | |
| 24 | 25000314 | SEEDING CL 4B | 0.25 | ACRE | $3,600.00 | $2,500.00 | $3,600.00 | $3,000.00 | $7,261.94 | $6,490.00 | |
| 25 | 25000400 | NITROGEN FERT NUTR | 47 | POUND | $2.50 | $3.00 | $2.50 | $1.50 | $2.23 | $3.55 | |
| 26 | 25000600 | POTASSIUM FERT NUTR | 47 | POUND | $2.50 | $3.00 | $2.50 | $1.50 | $2.23 | $3.55 | |
| 27 | 25100630 | EROSION CONTR BLANKET | 1,993 | SQ YD | $1.10 | $1.20 | $1.10 | $1.25 | $1.68 | $1.40 | |
| 28 | 28000250 | TEMP EROS CONTR SEED | 50 | POUND | $8.00 | $6.00 | $8.00 | $5.00 | $3.91 | $7.80 | |
| 29 | 28000305 | TEMP DITCH CHECKS | 130 | FOOT | $13.00 | $15.00 | $13.00 | $12.50 | $8.62 | $13.45 | |
| 30 | 28000400 | PERIMETER EROS BAR | 1,054 | FOOT | $2.85 | $2.50 | $2.85 | $2.87 | $3.35 | $1.80 | |
| 31 | 28000500 | INLET & PIPE PROTECT | 1 | EACH | $300.00 | $150.00 | $300.00 | $165.00 | $505.69 | $188.80 | |
| 32 | 28001100 | TEMP EROS CONTR BLANK | 2,396 | SQ YD | $1.00 | $1.20 | $1.00 | $1.25 | $1.68 | $1.20 | |
| 33 | 28100107 | STONE RIPRAP CL A4 | 136 | SQ YD | $136.00 | $82.00 | $100.00 | $94.03 | $77.56 | $74.25 | |
| 34 | 28200200 | FILTER FABRIC | 136 | SQ YD | $1.00 | $2.25 | $3.35 | $3.57 | $7.54 | $12.30 | |
| 35 | 30300001 | AGG SUBGRADE IMPROVE | 95 | CU YD | $35.00 | $75.00 | $48.55 | $84.00 | $80.51 | $68.80 | |
| 36 | 30300112 | AGG SUBGRADE IMPR 12 | 780 | SQ YD | $12.50 | $20.00 | $26.80 | $15.00 | $32.27 | $18.10 | |
| 37 | 35101800 | AGG BASE CSE B 6 | 76 | SQ YD | $6.25 | $16.00 | $26.80 | $15.00 | $18.45 | $17.70 | |
| 38 | 40600290 | BIT MATLS TACK CT | 992 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0500 | |
| 39 | 40600625 | LEV BIND MM N50 | 37 | TON | $107.00 | $86.00 | $130.00 | $107.00 | $145.24 | $123.05 | |
| 40 | 40600982 | HMA SURF REM BUTT JT | 22 | SQ YD | $30.00 | $52.00 | $1.00 | $30.00 | $1.12 | $34.50 | |
| 41 | 40603335 | HMA SC "D" N50 | 74 | TON | $107.00 | $103.00 | $64.55 | $107.00 | $72.12 | $123.05 | |
| 42 | 40701801 | HMA PAVT FD 6 | 324 | SQ YD | $30.00 | $34.00 | $33.25 | $30.00 | $37.14 | $31.50 | |
| 43 | 44000100 | PAVEMENT REM | 321 | SQ YD | $20.00 | $15.00 | $17.00 | $12.00 | $15.43 | $26.20 | |
| 44 | 44000158 | HMA SURF REM 2 1/4 | 865 | SQ YD | $5.80 | $5.75 | $5.65 | $5.80 | $6.31 | $6.70 | |
| 45 | 48203021 | HMA SHOULDERS 6 | 583 | SQ YD | $30.00 | $31.00 | $33.00 | $30.00 | $36.86 | $34.50 | |
| 46 | 50100100 | REM EXIST STRUCT | 1 | EACH | $55,850.00 | $60,000.00 | $39,078.00 | $37,967.00 | $48,067.36 | $28,000.00 | |
| 47 | 50105220 | PIPE CULVERT REMOV | 25 | FOOT | $10.00 | $23.00 | $30.00 | $28.00 | $42.31 | $43.80 | |
| 48 | 50200100 | STRUCTURE EXCAVATION | 354 | CU YD | $5.00 | $45.00 | $41.00 | $39.20 | $38.55 | $124.60 | |
| 49 | 50300300 | PROTECTIVE COAT | 19 | SQ YD | $5.00 | $12.00 | $5.90 | $25.40 | $30.96 | $58.00 | |
| 50 | 50800205 | REINF BARS, EPOXY CTD | 25,930 | POUND | $1.40 | $1.52 | $1.50 | $1.77 | $1.80 | $1.70 | |
| 51 | 51500100 | NAME PLATES | 1 | EACH | $500.00 | $550.00 | $518.00 | $820.00 | $660.53 | $1,359.30 | |
| 52 | 54003000 | CONC BOX CUL | 176.7 | CU YD | $857.00 | $800.00 | $925.00 | $1,132.00 | $1,029.40 | $1,120.00 | |
| 53 | 542A0220 | P CUL CL A 1 15 | 30 | FOOT | $250.00 | $48.00 | $80.00 | $100.00 | $81.67 | $154.15 | |
| 54 | 54213660 | PRC FLAR END SEC 15 | 2 | EACH | $1,000.00 | $1,900.00 | $1,500.00 | $1,400.00 | $809.32 | $2,040.00 | |
| 55 | 60100945 | PIPE DRAINS 12 | 100 | FOOT | $20.00 | $51.00 | $70.00 | $38.00 | $36.35 | $26.85 | |
| 56 | 60235300 | INLETS TA T1F CL | 3 | EACH | $100.00 | $1,700.00 | $850.00 | $1,150.00 | $1,253.49 | $2,095.00 | |
| 57 | 63000001 | SPBGR TY A 6FT POSTS | 250 | FOOT | $24.80 | $22.50 | $24.80 | $24.80 | $25.13 | $28.50 | |
| 58 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $2,738.50 | $2,800.00 | $2,738.50 | $2,738.50 | $4,022.00 | $3,149.30 | |
| 59 | 63200310 | GUARDRAIL REMOV | 288 | FOOT | $4.85 | $7.00 | $4.85 | $4.85 | $5.38 | $5.80 | |
| 60 | 66600105 | FUR ERECT ROW MARKERS | 7 | EACH | $793.00 | $450.00 | $225.00 | $185.06 | $279.31 | $296.50 | |
| 61 | 67000500 | ENGR FIELD OFFICE B | 4 | CAL MO | $500.00 | $2,400.00 | $2,000.00 | $3,200.00 | $3,106.60 | $2,360.00 | |
| 62 | 67100100 | MOBILIZATION | 1 | L SUM | $37,805.00 | $25,000.00 | $33,200.00 | $36,236.00 | $38,057.73 | $40,000.00 | |
| 63 | 72400100 | REMOV SIN PAN ASSY TA | 2 | EACH | $35.00 | $35.00 | $200.00 | $100.00 | $150.00 | $120.00 | |
| 64 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $45.00 | $35.00 | $45.00 | $45.00 | $162.00 | $54.00 | |
| 65 | 78000200 | THPL PVT MK LINE 4 | 1,445 | FOOT | $1.50 | $1.50 | $1.50 | $1.50 | $1.68 | $1.80 | |
| 66 | 78200005 | GRDRAIL REF TYPE A | 8 | EACH | $12.00 | $10.00 | $12.00 | $12.00 | $11.17 | $13.80 |