BURNING STAR 2022
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | DMS Contracting, Inc. Low bidder | $1,851,558 | ||
| 2 | Samron Midwest Contracting, Inc. | $1,947,633 | +5.2% | |
| 3 | E. T. Simonds Construction Company | $1,954,867 | +5.6% | |
| 4 | Sierra Bravo Contractors, LLC | $2,199,477 | +18.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 DMS Contracting… | #2 Samron Midwest … | #3 E. T. Simonds C… | #4 Sierra Bravo Co… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0300010 | BIT MATLS FS | 45,585 | POUND | $0.9000 | $0.7900 | $0.8300 | $0.8400 | |
| 2 | X0323013 | TUBULAR STEEL GATE | 7 | EACH | $9,200.00 | $7,500.00 | $10,069.20 | $10,165.09 | |
| 3 | X0324062 | ENTRANCE SIGN | 1 | L SUM | $18,600.00 | $30,000.00 | $26,162.23 | $26,411.39 | |
| 4 | X0327593 | SMALL ENTRANCE SIGN | 10 | EACH | $3,000.00 | $4,200.00 | $2,229.28 | $2,250.51 | |
| 5 | X1500006 | BIT SURF TREATMNT A3 | 84,415 | SQ YD | $6.50 | $5.34 | $5.61 | $5.66 | |
| 6 | X4200408 | PCC PVT 8 SPL | 534 | SQ YD | $120.00 | $115.00 | $123.16 | $196.55 | |
| 7 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $5,100.00 | $100,000.00 | $16,606.92 | $41,690.39 | |
| 8 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $20,000.00 | $14,000.00 | $6,720.00 | $26,500.00 | |
| 9 | Z0015500 | DEBRIS REMOVAL | 1 | L SUM | $780.00 | $1,500.00 | $4,193.07 | $5,355.62 | |
| 10 | 20100500 | TREE REMOV ACRES | 3 | ACRE | $0.0100 | $10,000.00 | $12,285.08 | $10,490.72 | |
| 11 | 20200100 | EARTH EXCAVATION | 4,595 | CU YD | $19.00 | $15.00 | $22.27 | $31.25 | |
| 12 | 20800150 | TRENCH BACKFILL | 226 | CU YD | $53.00 | $50.00 | $43.81 | $47.38 | |
| 13 | 25000210 | SEEDING CL 2A | 2 | ACRE | $3,200.00 | $5,500.00 | $3,648.75 | $3,683.50 | |
| 14 | 25000400 | NITROGEN FERT NUTR | 180 | POUND | $3.50 | $3.35 | $3.15 | $3.18 | |
| 15 | 25000500 | PHOSPHORUS FERT NUTR | 180 | POUND | $3.50 | $3.35 | $3.15 | $3.18 | |
| 16 | 25000600 | POTASSIUM FERT NUTR | 180 | POUND | $3.50 | $3.35 | $3.15 | $3.18 | |
| 17 | 25100115 | MULCH METHOD 2 | 2 | ACRE | $1,600.00 | $1,700.00 | $2,598.75 | $2,623.50 | |
| 18 | 28000305 | TEMP DITCH CHECKS | 200 | FOOT | $32.00 | $30.00 | $16.20 | $23.32 | |
| 19 | 28100707 | STONE DUMP RIP CL A4 | 156 | SQ YD | $65.00 | $45.00 | $69.39 | $84.83 | |
| 20 | 35101582 | AGG BASE CSE B 2 | 72,157 | SQ YD | $3.40 | $4.00 | $4.00 | $3.16 | |
| 21 | 35101600 | AGG BASE CSE B 4 | 7,994 | SQ YD | $8.75 | $12.50 | $9.20 | $6.68 | |
| 22 | 35102000 | AGG BASE CSE B 8 | 15,041 | SQ YD | $13.30 | $14.50 | $13.97 | $14.04 | |
| 23 | 35800100 | PREPARATION OF BASE | 84,415 | SQ YD | $1.20 | $0.6000 | $0.7500 | $2.67 | |
| 24 | 35800200 | AGG BASE REPAIR | 1,700 | TON | $27.25 | $45.00 | $56.12 | $38.65 | |
| 25 | 48101500 | AGGREGATE SHLDS B 6 | 582 | SQ YD | $17.50 | $13.00 | $24.40 | $42.83 | |
| 26 | 50105220 | PIPE CULVERT REMOV | 685 | FOOT | $5.00 | $5.00 | $67.28 | $37.86 | |
| 27 | 542D0223 | P CUL CL D 1 18 | 154 | FOOT | $119.00 | $65.00 | $113.04 | $129.06 | |
| 28 | 542D1081 | P CUL CL D 2 36 | 197 | FOOT | $205.00 | $115.00 | $169.42 | $123.88 | |
| 29 | 542D1909 | P CUL CL D 3 24 | 263 | FOOT | $145.00 | $80.00 | $188.56 | $124.29 | |
| 30 | 542D1921 | P CUL CL D 3 36 | 164 | FOOT | $187.00 | $115.00 | $166.61 | $144.83 | |
| 31 | 54262718 | METAL FL END SEC 18" | 8 | EACH | $852.00 | $550.00 | $896.21 | $744.97 | |
| 32 | 54262724 | METAL FL END SEC 24" | 4 | EACH | $1,130.00 | $750.00 | $1,061.85 | $904.60 | |
| 33 | 54262736 | METAL FL END SEC 36" | 5 | EACH | $1,725.00 | $1,500.00 | $1,517.11 | $1,474.42 | |
| 34 | 60801036 | FLAP GATE 36 | 1 | EACH | $3,280.00 | $2,500.00 | $3,065.81 | $3,146.59 | |
| 35 | 63400105 | GUARD POSTS | 332 | EACH | $128.00 | $125.00 | $134.18 | $135.46 | |
| 36 | 67100100 | MOBILIZATION | 1 | L SUM | $30,200.00 | $115,000.00 | $44,090.21 | $130,645.00 | |
| 37 | 72000100 | SIGN PANEL T1 | 126 | SQ FT | $65.50 | $18.00 | $24.15 | $24.38 | |
| 38 | 72000200 | SIGN PANEL T2 | 180 | SQ FT | $72.00 | $40.00 | $47.25 | $47.70 | |
| 39 | 72400100 | REMOV SIN PAN ASSY TA | 2 | EACH | $136.00 | $175.00 | $553.89 | $6,270.78 | |
| 40 | 73000100 | WOOD SIN SUPPORT | 610 | FOOT | $16.50 | $31.00 | $18.90 | $19.08 |