DANA THOMAS 2019
- Let date
- Friday, July 30, 2021
- Contract
- 46911 · job page
- District
- District 6
- County
- Sangamon
- Highway
- Limits
- Removal and replacement of a portion of the existing parking lot, the sealing of the remainder of the existing parking lot and the construction of a bus lane and drop off connection at the Dana Thomas House State Historic Site in Springfield.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kinney Contractors, Inc. Low bidder | $439,805 | ||
| 2 | Otto Baum Company, Inc. | $467,385 | +6.3% | |
| 3 | Sangamo Construction Company | $475,954 | +8.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kinney Contract… | #2 Otto Baum Compa… | #3 Sangamo Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0300019 | REM REIN PARKING BLKS | 31 | EACH | $95.00 | $91.06 | $197.91 | |
| 2 | X0301339 | REM EX PARKING BLOCKS | 7 | EACH | $55.00 | $33.73 | $130.10 | |
| 3 | X0327308 | PARK LOT SEAL CT | 392 | GALLON | $12.50 | $7.71 | $7.71 | |
| 4 | X0487800 | SAN SEW REMOV 12 | 27 | FOOT | $29.00 | $73.89 | $133.01 | |
| 5 | X0800003 | COARSE AGR BACKFIL SP | 145 | CU YD | $130.00 | $133.27 | $218.56 | |
| 6 | X2010400 | STUMP REMOVAL ONLY | 27 | UNIT | $22.00 | $42.52 | $60.55 | |
| 7 | X2020410 | EARTH EXCAVATION SPL | 592 | CU YD | $39.75 | $48.37 | $35.94 | |
| 8 | X2110104 | TOPSOIL F & P 4 SPL | 494 | SQ YD | $23.00 | $21.00 | $19.94 | |
| 9 | X4402400 | CURB REMOVAL SPL | 177 | FOOT | $12.00 | $22.93 | $34.10 | |
| 10 | X6011805 | PIPE DRAINS 8 SPL | 87 | FOOT | $70.00 | $106.14 | $86.19 | |
| 11 | X6020710 | CB ADJ W/SPL F&G | 3 | EACH | $1,350.00 | $1,045.90 | $787.43 | |
| 12 | X6022230 | MAN TA 4 DIA SPL F&G | 1 | EACH | $5,100.00 | $6,985.30 | $9,487.41 | |
| 13 | X6024200 | MAN TA 6D T1F CL SPL | 2 | EACH | $10,000.00 | $11,893.48 | $12,543.47 | |
| 14 | X6062400 | CONC GUTTER SPL | 20 | FOOT | $90.00 | $79.61 | $71.31 | |
| 15 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $10,000.00 | $7,318.28 | $12,560.57 | |
| 16 | X7240300 | SIGN REMOVAL | 3 | EACH | $150.00 | $123.74 | $152.25 | |
| 17 | X7240600 | REM RE-ERECT EX SIGN | 3 | EACH | $275.00 | $465.11 | $524.79 | |
| 18 | X8300001 | LIGHT POLE SPECIAL | 7 | EACH | $2,750.00 | $1,974.98 | $2,095.74 | |
| 19 | Z0004002 | BOLLARDS | 1 | EACH | $875.00 | $938.71 | $1,140.77 | |
| 20 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $6,500.00 | $6,272.23 | $7,789.00 | |
| 21 | 20100110 | TREE REMOV 6-15 | 50 | UNIT | $25.00 | $71.23 | $60.46 | |
| 22 | 20100210 | TREE REMOV OVER 15 | 43 | UNIT | $105.00 | $94.62 | $59.49 | |
| 23 | 20800150 | TRENCH BACKFILL | 28 | CU YD | $75.00 | $84.29 | $74.49 | |
| 24 | 28000400 | PERIMETER EROS BAR | 166 | FOOT | $9.50 | $7.33 | $5.72 | |
| 25 | 28000510 | INLET FILTERS | 13 | EACH | $285.00 | $332.39 | $375.54 | |
| 26 | 28500100 | FAB FORM CONC REV MAT | 5.3 | SQ YD | $300.00 | $489.16 | $1,169.00 | |
| 27 | 31100300 | SUB GRAN MAT A 4 | 115 | SQ YD | $21.50 | $17.87 | $20.42 | |
| 28 | 35100700 | AGG BASE CSE A 8 | 285 | SQ YD | $25.50 | $28.18 | $22.92 | |
| 29 | 35101100 | AGG BASE CSE A 12 | 759 | SQ YD | $32.50 | $32.52 | $24.88 | |
| 30 | 40600275 | BIT MATLS PR CT | 1,684 | POUND | $1.00 | $3.30 | $3.19 | |
| 31 | 40600290 | BIT MATLS TACK CT | 168 | POUND | $1.00 | $3.30 | $3.19 | |
| 32 | 40602978 | HMA BC IL-9.5 N50 | 63 | TON | $375.00 | $225.38 | $223.46 | |
| 33 | 40604050 | HMA SC IL-9.5 C N50 | 63 | TON | $345.00 | $225.38 | $223.46 | |
| 34 | 42000200 | PCC PVT 7 | 279 | SQ YD | $69.00 | $89.77 | $85.00 | |
| 35 | 42400200 | PC CONC SIDEWALK 5 | 1,030 | SQ FT | $8.70 | $10.89 | $8.76 | |
| 36 | 44000100 | PAVEMENT REM | 559 | SQ YD | $15.00 | $14.78 | $12.15 | |
| 37 | 44000300 | CURB REM | 446 | FOOT | $9.00 | $13.87 | $25.37 | |
| 38 | 44000600 | SIDEWALK REM | 1,568 | SQ FT | $3.00 | $2.42 | $4.26 | |
| 39 | 45100200 | CRACK FILLING | 430 | POUND | $9.00 | $7.23 | $7.24 | |
| 40 | 550A0050 | STORM SEW CL A 1 12 | 50 | FOOT | $111.00 | $103.63 | $89.38 | |
| 41 | 60218300 | MAN TA 4 DIA T1F OL | 1 | EACH | $2,995.00 | $3,005.49 | $3,989.27 | |
| 42 | 60234200 | INLETS TA T1F OL | 1 | EACH | $1,620.00 | $1,670.91 | $2,210.11 | |
| 43 | 60235700 | INLETS TA T3F&G | 2 | EACH | $1,850.00 | $1,869.72 | $2,384.62 | |
| 44 | 60236200 | INLETS TA T8G | 3 | EACH | $1,525.00 | $1,578.42 | $2,134.56 | |
| 45 | 60500040 | REMOV MANHOLES | 1 | EACH | $450.00 | $915.05 | $1,183.27 | |
| 46 | 60500050 | REMOV CATCH BAS | 2 | EACH | $400.00 | $688.95 | $816.16 | |
| 47 | 60600605 | CONC CURB TB | 268 | FOOT | $62.50 | $85.78 | $43.58 | |
| 48 | 60604400 | COMB CC&G TB6.18 | 184 | FOOT | $60.00 | $76.36 | $63.53 | |
| 49 | 60605900 | COMB CC&G TB9.12 | 61 | FOOT | $62.00 | $80.95 | $62.60 | |
| 50 | 61140200 | STORM SEWER SPEC 12 | 146 | FOOT | $37.50 | $119.14 | $136.20 | |
| 51 | 61140400 | STORM SEWER SPEC 15 | 65 | FOOT | $43.00 | $131.36 | $144.72 | |
| 52 | 67100100 | MOBILIZATION | 1 | L SUM | $25,500.00 | $27,926.06 | $28,081.30 | |
| 53 | 72000100 | SIGN PANEL T1 | 28 | SQ FT | $21.00 | $41.46 | $18.09 | |
| 54 | 72900100 | METAL POST TY A | 180 | FOOT | $24.00 | $24.45 | $21.28 | |
| 55 | 78001100 | PT PVT MK LTRS & SYMB | 105 | SQ FT | $5.50 | $5.32 | $4.79 | |
| 56 | 78001110 | PAINT PVT MK LINE 4 | 2,844 | FOOT | $0.7500 | $1.58 | $0.6400 | |
| 57 | 78001130 | PAINT PVT MK LINE 6 | 860 | FOOT | $1.25 | $2.39 | $1.06 | |
| 58 | 78300201 | PAVMT MRKG REM GRIND | 246 | SQ FT | $3.50 | $5.95 | $2.99 | |
| 59 | 81028310 | UNDRGRD C PVC 3/4 | 536 | FOOT | $16.00 | $25.41 | $26.96 | |
| 60 | 81702450 | EC C XLP USE 3-1C 10 | 729 | FOOT | $2.00 | $3.18 | $3.37 | |
| 61 | 82110003 | LUM LED RDWY C | 11 | EACH | $1,275.00 | $523.55 | $555.56 | |
| 62 | 83600200 | LIGHT POLE FDN 24D | 98 | FOOT | $350.00 | $190.53 | $202.18 | |
| 63 | 84200600 | REM LT U NO SALV | 3 | EACH | $1.00 | $628.74 | $667.19 | |
| 64 | 84200804 | REM POLE FDN | 3 | EACH | $300.00 | $1,016.15 | $1,078.28 |