Bid code AR752418

PRECAST REINFORCED CONC. FES 18" · per EACH

‹ All bid codes

$1,462.24Avg low bid / EACH
$1,338.17Avg of all bids
—Avg engineer's estimate
4Jobs · 8 EACH

Average low bid by year

YearJobsQuantityAvg lowAvg all
202212$2,049.97$2,049.97
202114$1,312.00$1,297.81
201911$1,400.00$1,205.00
201811$950.00$1,082.50

Recent low bids

ExcelCSV
Let dateContractCounty / DistrictQuantityUnit priceLow bidder
Jan 21, 2022MV066 JeffersonDistrict 92 EACH $2,049.97Southern Illinois Asphalt Co., Inc.
Jan 15, 2021LI039 MontgomeryDistrict 64 EACH $1,312.00Stutz Excavating, Inc.
Jan 18, 2019KA048 KankakeeDistrict 31 EACH $1,400.00Kankakee Valley Construction Company, Inc.
Jun 15, 2018SD059 St. ClairDistrict 81 EACH $950.00Hank's Excavating & Landscaping, Inc.