$1,842.06Avg low bid / EACH
$1,922.62Avg of all bids
—Avg engineer's estimate
20Jobs · 262 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 10 | 121 | $1,963.12 | $1,989.17 |
| 2025 | 10 | 141 | $1,738.17 | $1,842.37 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2026 | 62W99 | CookDistrict 1 | 6 EACH | $3,751.06 | K-Five Construction Corporation |
| Jun 12, 2026 | 72509 | LoganDistrict 6 | 22 EACH | $2,629.66 | Bodine Electric of Decatur |
| Apr 24, 2026 | 61L84 | DupageDistrict 1 | 19 EACH | $1,518.52 | K-Five Construction Corporation |
| Feb 27, 2026 | 61M26 | CookDistrict 1 | 14 EACH | $1,615.43 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 61M27 | CookDistrict 1 | 2 EACH | $1,657.43 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 61M28 | CookDistrict 1 | 9 EACH | $1,600.00 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 62R19 | Grundy, Kendall, WillDistrict 1 | 2 EACH | $4,120.89 | Meade Inc. |
| Feb 27, 2026 | 62W78 | LakeDistrict 1 | 9 EACH | $1,670.00 | Hecker and Company, Inc. |
| Jan 16, 2026 | 91642 | ChampaignDistrict 5 | 31 EACH | $1,004.00 | William Charles Construction Company, LLC |
| Jan 16, 2026 | 99763 | JacksonDistrict 9 | 7 EACH | $4,800.00 | Samron Midwest Contracting, Inc. |
| Sep 19, 2025 | 72977 | LoganDistrict 6 | 21 EACH | $1,496.69 | Bodine Electric of Decatur |
| Aug 1, 2025 | 61L37 | CookDistrict 1 | 10 EACH | $1,740.00 | Plote Construction, Inc. |
| Aug 1, 2025 | 61L38 | CookDistrict 1 | 6 EACH | $2,238.00 | Plote Construction, Inc. |
| Jun 13, 2025 | 66K71 | BureauDistrict 3 | 51 EACH | $1,454.87 | D. Construction, Inc. |
| Jun 13, 2025 | 78B32 | AlexanderDistrict 9 | 1 EACH | $3,691.88 | E. T. Simonds Construction Company |
| Apr 25, 2025 | 62W87 | CookDistrict 1 | 24 EACH | $2,450.00 | Lorig Construction Company |
| Jan 17, 2025 | 70A55 | VermilionDistrict 5 | 2 EACH | $1,500.00 | Open Road Paving Company LLC |
| Jan 17, 2025 | 72G59 | AdamsDistrict 6 | 2 EACH | $4,130.00 | Diamond Construction Company |
| Jan 17, 2025 | 61K53 | CookDistrict 1 | 7 EACH | $1,250.00 | Utility Dynamics Corporation |
| Jan 17, 2025 | 61K68 | KaneDistrict 1 | 17 EACH | $1,536.69 | Martam Construction Incorporated |