$3,288.10Avg low bid / EACH
$3,042.24Avg of all bids
—Avg engineer's estimate
13Jobs · 135 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 3 | 23 | $3,306.96 | $2,588.51 |
| 2025 | 9 | 96 | $3,389.93 | $3,226.17 |
| 2024 | 1 | 16 | $2,650.00 | $2,087.75 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2026 | 64V40 | Rock IslandDistrict 2 | 9 EACH | $5,000.00 | Valley Construction Co. |
| Jan 16, 2026 | 62F94 | WillDistrict 1 | 12 EACH | $2,090.00 | D. Construction, Inc. |
| Jan 16, 2026 | 76E84 | Madison, St.clairDistrict 8 | 2 EACH | $2,990.00 | The Kilian Corporation & Christ Brothers Asphalt & Keeley & Sons, Inc. tri-venture |
| Sep 19, 2025 | 62R22 | WillDistrict 1 | 8 EACH | $3,960.00 | D. Construction, Inc. |
| Aug 1, 2025 | 64C24 | WinnebagoDistrict 2 | 20 EACH | $2,914.57 | OHLA Central, Inc. |
| Jun 13, 2025 | 76K74 | St.clairDistrict 8 | 2 EACH | $1,861.50 | Keeley & Sons, Inc. Keller Construction Inc. |
| Apr 25, 2025 | 62W87 | CookDistrict 1 | 2 EACH | $2,800.00 | Lorig Construction Company |
| Apr 25, 2025 | 64N98 | OgleDistrict 2 | 6 EACH | $4,802.12 | William Charles Construction Company, LLC |
| Mar 7, 2025 | 62N91 | CookDistrict 1 | 16 EACH | $3,295.00 | Dunnet Bay Construction Company & K-Five Construction Corporation |
| Jan 17, 2025 | 70G85 | McleanDistrict 5 | 20 EACH | $2,955.68 | Bodine Electric of Decatur |
| Jan 17, 2025 | 78884 | Franklin, JeffersonDistrict 9 | 2 EACH | $7,746.09 | E. T. Simonds Construction Company |
| Jan 17, 2025 | 46656 | VariousDistrict 0 | 20 EACH | $3,500.00 | ROADSAFE TRAFFIC SYSTEMS, INC. |
| Dec 13, 2024 | 78798 | WilliamsonDistrict 9 | 16 EACH | $2,650.00 | Samron Midwest Contracting, Inc. |