D5 ITS 2025-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Bodine Electric of Decatur Low bidder | $2,995,164 | ||
| 2 | John Burns Construction Company | $3,144,875 | +5.0% | |
| 3 | Champaign Signal and Lighting Co. A Division of Champaign Asphalt Company LLC | $3,407,913 | +13.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Bodine Electric… | #2 John Burns Cons… | #3 Champaign Signa… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0323920 | POLE MT EQUIP CAB TB | 5 | EACH | $9,434.05 | $17,500.00 | $10,000.00 | |
| 2 | X0323923 | SUPPORT EQUIP & MAINT | 1 | L SUM | $15,827.97 | $13,210.00 | $30,000.00 | |
| 3 | X0325485 | TR MTD LED DYN MSG SN | 5 | EACH | $112,919.04 | $178,425.00 | $150,000.00 | |
| 4 | X0326905 | CCTV DOME CAM IP BASE | 5 | EACH | $8,517.18 | $17,302.00 | $10,000.00 | |
| 5 | X1400459 | DMS REMOVAL - IDOT | 5 | EACH | $9,289.28 | $9,161.00 | $50,000.00 | |
| 6 | X6430120 | REM IMP ATTEN NO SALV | 6 | EACH | $6,997.12 | $8,502.00 | $5,000.00 | |
| 7 | X8100105 | CONDUIT SPLICE | 1 | EACH | $2,931.55 | $1,216.00 | $500.00 | |
| 8 | X8302135 | WOOD POLE 35 CL 4 | 5 | EACH | $2,774.72 | $7,204.00 | $5,000.00 | |
| 9 | X8710036 | FIB OPT CBL 12F SM | 4,120 | FOOT | $23.22 | $12.00 | $18.00 | |
| 10 | X8710071 | FIB OPT FUSION SPLICE | 10 | EACH | $2,171.52 | $1,478.00 | $2,000.00 | |
| 11 | X8710103 | ETHERNET SWITCH | 5 | EACH | $2,485.18 | $3,467.00 | $4,000.00 | |
| 12 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $12,064.00 | $15,000.00 | $30,000.00 | |
| 13 | 20400800 | FURNISHED EXCAVATION | 75 | CU YD | $603.20 | $625.00 | $400.00 | |
| 14 | 25000210 | SEEDING CL 2A | 0.5 | ACRE | $16,165.76 | $5,000.00 | $15,000.00 | |
| 15 | 25000400 | NITROGEN FERT NUTR | 47 | POUND | $84.45 | $5.00 | $250.00 | |
| 16 | 25000500 | PHOSPHORUS FERT NUTR | 47 | POUND | $84.45 | $5.00 | $250.00 | |
| 17 | 25000600 | POTASSIUM FERT NUTR | 47 | POUND | $84.45 | $5.00 | $250.00 | |
| 18 | 25100115 | MULCH METHOD 2 | 0.5 | ACRE | $18,578.56 | $5,000.00 | $15,000.00 | |
| 19 | 63000001 | SPBGR TY A 6FT POSTS | 2,325 | FOOT | $38.60 | $30.00 | $40.00 | |
| 20 | 63100045 | TRAF BAR TERM T2 | 13 | EACH | $2,050.88 | $1,600.00 | $2,500.00 | |
| 21 | 63100167 | TR BAR TRM T1 SPL TAN | 13 | EACH | $4,463.68 | $3,620.00 | $5,000.00 | |
| 22 | 63200310 | GUARDRAIL REMOV | 697 | FOOT | $9.65 | $6.00 | $10.00 | |
| 23 | 67100100 | MOBILIZATION | 1 | L SUM | $115,573.12 | $188,000.00 | $200,000.00 | |
| 24 | 70100420 | TRAF CONT-PROT 701411 | 2 | EACH | $9,687.39 | $1.00 | $50,000.00 | |
| 25 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $272,935.94 | $90,000.00 | $200,000.00 | |
| 26 | 70107025 | CHANGEABLE MESSAGE SN | 35 | CAL DA | $1,737.22 | $50.00 | $500.00 | |
| 27 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $12,305.28 | $11,000.00 | $5,000.00 | |
| 28 | 72501000 | TERMINAL MARKER - DA | 13 | EACH | $60.32 | $50.00 | $100.00 | |
| 29 | 73300300 | OVHD SIN STR-SPAN T3A | 313 | FOOT | $2,066.56 | $1,874.00 | $1,800.00 | |
| 30 | 73301810 | OSS WALKWAY TY A | 100 | FOOT | $784.16 | $504.00 | $1,000.00 | |
| 31 | 73400200 | DRILL SHAFT CONC FDN | 110.3 | CU YD | $2,433.31 | $2,615.00 | $2,250.00 | |
| 32 | 73600100 | REMOV OH SIN STR-SPAN | 5 | EACH | $18,096.00 | $6,921.00 | $18,000.00 | |
| 33 | 73700300 | REM CONC FDN-OVHD | 20 | EACH | $2,955.68 | $2,815.00 | $3,500.00 | |
| 34 | 78200005 | GRDRAIL REF TYPE A | 49 | EACH | $18.10 | $10.00 | $20.00 | |
| 35 | 80500100 | SERV INSTALL TY A | 5 | EACH | $8,034.62 | $14,544.00 | $12,500.00 | |
| 36 | 81028350 | UNDRGRD C PVC 2 | 1,734 | FOOT | $36.19 | $95.00 | $30.00 | |
| 37 | 81100600 | CON AT ST 2 GALVS | 90 | FOOT | $91.08 | $125.00 | $130.00 | |
| 38 | 81400100 | HANDHOLE | 2 | EACH | $5,018.62 | $11,857.00 | $6,000.00 | |
| 39 | 84500120 | REMOV ELECT SERV INST | 5 | EACH | $1,857.86 | $8,502.00 | $5,000.00 | |
| 40 | 87300901 | ELCBL C TRACER 12 1C | 394 | FOOT | $3.26 | $0.5000 | $5.00 | |
| 41 | 87301815 | ELCBL C SERV 6 3C | 1,451 | FOOT | $36.19 | $7.00 | $8.00 | |
| 42 | 87301900 | ELCBL C EGRDC 6 1C | 1,476 | FOOT | $5.55 | $1.50 | $5.00 | |
| 43 | 87900200 | DRILL EX HANDHOLE | 4 | EACH | $965.12 | $1,216.00 | $5,000.00 |