Concrete Spall Repair 07 11.26
- Let date
- Thursday, November 12, 2026
- CCSJ
- 6509-36-001
- District
- Dallas
- County
- Collin
- Highway
- US0075
- Limits
- VARIOUS ROADWAYS IN THE COLLIN to COUNTY MAINTENANCE SECTION
- Classification
- Routine Maintenance Project - Sealed · Maintenance
- Project number
- RMC - A00223997
- Working days
- 365
- DBE goal
- 0%
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $925,400 | ||
| 1 | STRUCTURAL INTEGRITY GROUP LLC Low bidder | $615,350 | -33.5% | |
| 2 | XIT PAVING AND CONSTRUCTION INC. | $727,000 | -21.4% | +18.1% |
| 3 | GHB EQUIPMENT COMPANY, L.L.C. | $743,150 | -19.7% | +20.8% |
| 4 | O. TREVINO CONSTRUCTION, LLC | $765,100 | -17.3% | +24.3% |
| 5 | PREMIER CONTRACTORS LLC | $810,750 | -12.4% | +31.8% |
| 6 | DIGG COMMERCIAL, LLC | $980,750 | +6.0% | +59.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 STRUCTURAL INTE… | #2 XIT PAVING AND … | #3 GHB EQUIPMENT C… | #4 O. TREVINO CONS… | #5 PREMIER CONTRAC… | #6 DIGG COMMERCIAL… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-7002 | MOBILIZATION (CALLOUT) | 120 | EA | $1,500.00 | $1.00 | $100.00 | $1.00 | $50.00 | $1.00 | $1.00 |
| 2 | 500-7033 | MOBILIZATION (EMERGENCY) | 30 | EA | $2,000.00 | $1.00 | $200.00 | $1.00 | $50.00 | $1.00 | $1.00 |
| 3 | 505-7001 | TMA (STATIONARY) | 600 | DAY | $150.00 | $1.00 | $265.00 | $1.00 | $85.00 | $1.00 | $1.00 |
| 4 | 721-7001 | FIBER REINFORCED POLYMER PATCHING MATLS | 80,000 | LB | $6.98 | $6.40 | $6.75 | $8.98 | $8.70 | $9.50 | $11.00 |
| 5 | 721-7002 | BULKING AGGREGATE | 20,000 | LB | $1.85 | $5.13 | $0.5000 | $1.20 | $0.5300 | $2.50 | $5.00 |