Hot Mix FY2027
- Let date
- Thursday, November 12, 2026
- CCSJ
- 6506-44-001
- District
- Dallas
- County
- Collin
- Highway
- SH0005
- Limits
- Collin County to Maintenance Section
- Classification
- Material Maintenance Project · Maintenance
- Project number
- MMC - A00223366
- Working days
- 180
- DBE goal
- 0%
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $566,650 | ||
| 1 | AUSTIN ASPHALT, INC. Low bidder | $530,400 | -6.4% | |
| 2 | ROADXCHANGE MELISSA LLC | $548,000 | -3.3% | +3.3% |
| 3 | SOUTHERN SOURCING SOLUTIONS, LLC | $582,770 | +2.8% | +9.9% |
| 4 | TOUCHSTONE RESOURCES, LLC | $684,300 | +20.8% | +29.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 AUSTIN ASPHALT,… | #2 ROADXCHANGE MEL… | #3 SOUTHERN SOURCI… | #4 TOUCHSTONE RESO… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 8011-7055 | D-GR HMA TY D PG 64-22 (PICKUP) | 500 | TON | $94.35 | $86.00 | $88.00 | $94.50 | $110.00 |
| 2 | 8011-7127 | D-GR HMA TY C PG 70-22 (PICKUP) | 100 | TON | $94.90 | $95.00 | $99.00 | $103.43 | $110.00 |
| 3 | 8017-7010 | SP MIXTURES SP-C PG70-22 (PICKUP) | 900 | TON | $94.90 | $96.00 | $99.00 | $104.48 | $112.00 |
| 4 | 8017-7019 | SP MIXTURES SP-D PG64-22 (PICKUP) | 4,500 | TON | $94.35 | $87.00 | $90.00 | $95.81 | $115.00 |