FY26 Brenham AO Hydraulic Cement - 04
- Let date
- Tuesday, April 14, 2026
- CCSJ
- 6498-63-001
- District
- Bryan
- County
- Washington
- Highway
- SH0036
- Limits
- Various to Various
- Classification
- Material Maintenance Project · Maintenance
- Project number
- MMC - A00220033
- Working days
- 180
- DBE goal
- 0%
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $208,008 | ||
| 1 | TOUCHSTONE RESOURCES, LLC Low bidder | $197,551 | -5.0% | |
| 2 | AKA-MATERIALS | $207,895 | -0.1% | +5.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 TOUCHSTONE RESO… | #2 AKA-MATERIALS |
|---|---|---|---|---|---|---|---|
| 1 | 8009-7001 | HYDRAULIC CEMENT(TY I)(DEL)(ST 1) | 250 | TON | $220.00 | $210.00 | $215.00 |
| 2 | 8009-7003 | HYDRAULIC CEMENT(TY I)(DEL)(ST 3) | 250 | TON | $220.00 | $210.00 | $222.00 |
| 3 | 8009-7005 | HYDRAULIC CEMENT(TY I)(DEL)(ST 5) | 250 | TON | $220.00 | $210.00 | $229.00 |
| 4 | 8009-7038 | HYDRAULIC CEMENT(TY I)(DEL)(47LB)(ST 2) | 1,792 | BAG | $8.00 | $7.45 | $7.70 |
| 5 | 8009-7040 | HYDRAULIC CEMENT(TY I)(DEL)(47LB)(ST 4) | 1,792 | BAG | $8.00 | $7.45 | $7.65 |
| 6 | 8009-7042 | HYDRAULIC CEMENT(TY I)(DEL)(47LB)(ST 6) | 1,792 | BAG | $8.00 | $7.45 | $7.75 |