FY26 - SH 19 SB Bridge Repair
- Let date
- Tuesday, February 10, 2026
- CCSJ
- 6494-76-001
- District
- Bryan
- County
- Walker
- Highway
- SH0019
- Limits
- @ SH 75 to @ SH 75
- Classification
- Routine Maintenance Project - Sealed · Maintenance
- Project number
- RMC - A00218646
- Working days
- 9
- DBE goal
- 0%
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $101,567 | ||
| 1 | GARRET SHIELDS INFRASTRUCTURE Low bidder | $57,501 | -43.4% | |
| 2 | BK FIELD OPERATIONS LLC | $74,378 | -26.8% | +29.4% |
| 3 | RESTEK, INC. | $79,671 | -21.6% | +38.6% |
| 4 | SCR CIVIL CONSTRUCTION, LLC | $85,355 | -16.0% | +48.4% |
| 5 | AAD CONTRACTING INC. | $100,000 | -1.5% | +73.9% |
| 6 | STRUCTURAL INTEGRITY GROUP LLC | $103,968 | +2.4% | +80.8% |
| 7 | BLACKSMITH VENTURES LLC | $106,396 | +4.8% | +85.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 GARRET SHIELDS … | #2 BK FIELD OPERAT… | #3 RESTEK, INC. | #4 SCR CIVIL CONST… | #5 AAD CONTRACTING… | #6 STRUCTURAL INTE… | #7 BLACKSMITH VENT… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-7001 | MOBILIZATION | 1 | LS | $16,714.43 | $5,000.00 | $8,000.00 | $21,305.00 | $8,400.00 | $20,000.00 | $10,000.00 | $1.00 |
| 2 | 502-7001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 | MO | $12,485.32 | $5,000.00 | $10,000.00 | $6,650.00 | $8,400.00 | $10,000.00 | $18,500.00 | $5,000.00 |
| 3 | 503-7002 | PORTABLE CHANGEABLE MESSAGE SIGN | 1 | EA | $10,532.21 | $1.00 | $1.00 | $1,400.00 | $1,000.00 | $350.00 | $1.00 | $5,000.00 |
| 4 | 505-7001 | TMA (STATIONARY) | 18 | DAY | $214.32 | $300.00 | $1.00 | $150.00 | $150.00 | $450.00 | $1.00 | $450.00 |
| 5 | 780-7002 | CNC CRACK REPAIR (DISCRETE)(INJECT) | 35 | LF | $78.31 | $120.00 | $90.00 | $40.00 | $65.00 | $100.00 | $120.00 | $100.00 |
| 6 | 786-7001 | CARBON FIBER REINF POLYMER PROTECTION | 430 | SF | $75.66 | $70.00 | $40.00 | $33.70 | $60.00 | $90.00 | $68.00 | $162.00 |
| 7 | 788-7004 | CONCRETE BEAM REP (STRAND SPLICE) | 3 | EA | $7,120.00 | $2,000.00 | $12,000.00 | $10,500.00 | $12,200.00 | $6,000.00 | $14,000.00 | $5,000.00 |
| 8 | 7010-7002 | MAINTENANCE SPEED LIMIT SIGNING | 9 | DAY | $149.18 | $200.00 | $1.00 | $25.00 | $20.00 | $150.00 | $1.00 | $15.00 |