Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $457,830 | ||
| 1 | SKYLINE CONSTRUCTION PAVING & STRIPING Low bidder | $286,825 | -37.4% | |
| 2 | P-VILLE, INCORPORATED | $290,689 | -36.5% | +1.3% |
| 3 | T&L CLEANING SERVICES LLC | $379,685 | -17.1% | +32.4% |
| 4 | TERRASOL, LLC | $435,920 | -4.8% | +52.0% |
| 5 | GROUNDCOVER HOLDINGS, LLC | $441,445 | -3.6% | +53.9% |
| 6 | USA DT SERVICES, INC. | $492,920 | +7.7% | +71.9% |
| 7 | CROSS PLUS CONSTRUCTION, LLC | $544,250 | +18.9% | +89.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 SKYLINE CONSTRU… | #2 P-VILLE, INCORP… | #3 T&L CLEANING SE… | #4 TERRASOL, LLC | #5 GROUNDCOVER HOL… | #6 USA DT SERVICES… | #7 CROSS PLUS CONS… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-7002 | MOBILIZATION (CALLOUT) | 5 | EA | $500.00 | $100.00 | $1.00 | $1.00 | $1,250.00 | $1.00 | $500.00 | $5,000.00 |
| 2 | 730-7021 | SPOT MOWING | 150 | AC | $35.00 | $33.50 | $1.00 | $48.00 | $45.00 | $20.00 | $62.00 | $99.00 |
| 3 | 730-7022 | FULL - WIDTH MOWING | 7,760 | AC | $58.00 | $36.25 | $37.44 | $48.00 | $54.50 | $56.50 | $62.00 | $65.00 |