FLEXIBLE PAVEMENT STRUCTURE RPR 03 0125
- Let date
- Wednesday, January 8, 2025
- CCSJ
- 6467-45-001
- District
- Dallas
- County
- Dallas
- Highway
- IH0030
- Limits
- ON IH 30 IN to EAST DALLAS COUNTY MAINTENANCES
- Classification
- Routine Maintenance Project - Sealed · Maintenance
- Project number
- RMC - 646745001
- Working days
- 28
- DBE goal
- 0%
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,406,343 | ||
| 1 | PEACHTREE CONSTRUCTION, LTD. Low bidder | $1,020,538 | -27.4% | |
| 2 | FOUTSCO PAVING COMPANY, LLC | $1,231,171 | -12.5% | +20.6% |
| 3 | TEXAS MATERIALS GROUP, INC. | $1,237,360 | -12.0% | +21.2% |
| 4 | FNH CONSTRUCTION, LLC | $1,745,188 | +24.1% | +71.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 PEACHTREE CONST… | #2 FOUTSCO PAVING … | #3 TEXAS MATERIALS… | #4 FNH CONSTRUCTIO… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 344-7019 | SP MIXES SP-C PG70-22 | 5,850 | TON | $175.00 | $136.50 | $178.50 | $171.00 | $200.00 |
| 2 | 344-7077 | TACK COAT | 5,318 | GAL | $1.00 | $1.00 | $4.00 | $4.50 | $6.00 |
| 3 | 354-7003 | PLANE & TEXT ASPH CONC PAV(0" TO 3") | 53,180 | SY | $3.75 | $2.75 | $3.00 | $3.09 | $6.00 |
| 4 | 500-7001 | MOBILIZATION | 1 | LS | $100,000.00 | $50,000.00 | $5,000.00 | $5,952.00 | $160,000.00 |
| 5 | 502-7001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 | MO | $25,000.00 | $5,000.00 | $500.00 | $17,800.00 | $15,000.00 |
| 6 | 503-7001 | PORTABLE CHANGEABLE MESSAGE SIGN | 70 | DAY | $185.00 | $25.00 | $1.00 | $60.00 | $150.00 |
| 7 | 505-7001 | TMA (STATIONARY) | 42 | DAY | $250.00 | $50.00 | $1.00 | $1.25 | $250.00 |
| 8 | 662-7112 | WK ZN PAV MRK SHT TERM (TAB)TY W | 2,000 | EA | $2.00 | $3.00 | $0.0100 | $1.34 | $6.00 |
| 9 | 662-7113 | WK ZN PAV MRK SHT TERM (TAB)TY Y | 200 | EA | $2.00 | $3.00 | $0.0100 | $1.34 | $6.00 |