BRIDGE REPAIR
- Let date
- Thursday, March 3, 2022
- CCSJ
- 6393-23-001
- District
- Dallas
- County
- Dallas
- Highway
- SH 352
- Limits
- VARIOUS LOCATIONS ALONG SH 352 IN to SOUTHEAST DALLAS COUNTY MAINTENANCE
- Classification
- Maintenance
- Project number
- BPM - 639323001
- Working days
- 79
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $377,370 | ||
| 1 | PATHFIELD INVESTMENTS LLC Low bidder | $389,185 | +3.1% | |
| 2 | IBCTX, LLC | $511,710 | +35.6% | +31.5% |
| 3 | HIGHWAY 19 CONSTRUCTION LLC | $569,580 | +50.9% | +46.4% |
| 4 | RAGLE CONSTRUCTION, INC. | $591,530 | +56.8% | +52.0% |
| 5 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $676,223 | +79.2% | +73.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 PATHFIELD INVES… | #2 IBCTX, LLC | #3 HIGHWAY 19 CONS… | #4 RAGLE CONSTRUCT… | #5 SCOTT TUCKER CO… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 100-6002 | PREPARING ROW | 2 | STA | $2,000.00 | $5,000.00 | $12,500.00 | $10,000.00 | $29,000.00 | $6,440.29 |
| 2 | 420-6158 | CL C CONC(PILE ENCASEMENT) | 899 | LF | $350.00 | $375.00 | $450.00 | $500.00 | $420.00 | $616.46 |
| 3 | 500-6001 | MOBILIZATION | 1 | LS | $35,000.00 | $10,000.00 | $51,100.00 | $50,000.00 | $59,000.00 | $67,580.00 |
| 4 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 | MO | $2,500.00 | $2,500.00 | $2,500.00 | $5,000.00 | $14,000.00 | $2,534.33 |
| 5 | 506-6020 | CONSTRUCTION EXITS (INSTALL) (TY 1) | 224 | SY | $20.00 | $50.00 | $50.00 | $35.00 | $35.00 | $65.17 |
| 6 | 506-6024 | CONSTRUCTION EXITS (REMOVE) | 224 | SY | $10.00 | $15.00 | $15.00 | $10.00 | $15.00 | $41.17 |
| 7 | 6185-6002 | TMA (STATIONARY) | 10 | DAY | $200.00 | $250.00 | $150.00 | $1,000.00 | $175.00 | $253.92 |