BRIDGE REPAIR
- Let date
- Tuesday, December 14, 2021
- CCSJ
- 6390-34-001
- District
- Houston
- County
- Harris
- Highway
- IH 10
- Limits
- VARIOUS LOCATIONS to SMITH ST EXIT
- Classification
- Local Let
- Project number
- RMC - 639034001
- Working days
- 20
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $193,961 | ||
| 1 | FORDE CONSTRUCTION COMPANY, INC. Low bidder | $142,710 | -26.4% | |
| 2 | AAD CONTRACTING INC. | $144,234 | -25.6% | +1.1% |
| 3 | SCR CIVIL CONSTRUCTION, LLC | $145,670 | -24.9% | +2.1% |
| 4 | NBG CONSTRUCTORS, INC. | $154,140 | -20.5% | +8.0% |
| 5 | STRAIGHT LINE SAWING & SEALING, INC. | $167,458 | -13.7% | +17.3% |
| 6 | IDEA CONTRACTING LLC | $172,258 | -11.2% | +20.7% |
| 7 | MB WESTERN INDUSTRIAL CONTRACTING COMPANY | $178,854 | -7.8% | +25.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 FORDE CONSTRUCT… | #2 AAD CONTRACTING… | #3 SCR CIVIL CONST… | #4 NBG CONSTRUCTOR… | #5 STRAIGHT LINE S… | #6 IDEA CONTRACTIN… | #7 MB WESTERN INDU… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 104-6009 | REMOVING CONC (RIPRAP) | 4.6 | SY | $25.00 | $1,000.00 | $40.00 | $1,300.00 | $650.00 | $250.00 | $55.00 | |
| 2 | 420-6158 | CL C CONC(PILE ENCASEMENT) | 8.6 | LF | $293.39 | $2,600.00 | $500.00 | $2,800.00 | $2,600.00 | $1,400.00 | $900.00 | |
| 3 | 429-6005 | CONC STR REPAIR(DECK REP (FULL DEPTH)) | 37.7 | SF | $138.09 | $580.00 | $500.00 | $400.00 | $1,200.00 | $875.00 | $200.00 | |
| 4 | 446-6024 | CLEAN & PAINT EXIST PILING (SYSTEM II) | 2 | LS | $22,000.00 | $5,000.00 | $5,000.00 | $10,000.00 | $1,000.00 | $17,500.00 | $20,000.00 | |
| 5 | 446-6026 | CLEAN & PAINT EXIST PILING(SYS III-B) | 1 | LS | $99,000.00 | $15,000.00 | $10,000.00 | $11,700.00 | $1,400.00 | $16,000.00 | $95,000.00 | |
| 6 | 500-6001 | MOBILIZATION | 1 | LS | $18,159.11 | $13,000.00 | $60,000.00 | $14,500.00 | $13,500.00 | $16,000.00 | $8,000.00 | |
| 7 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 | MO | $16,508.28 | $24,000.00 | $20,000.00 | $14,500.00 | $15,000.00 | $8,000.00 | $5,000.00 | |
| 8 | 776-6053 | REPLACE (STEEL RAIL) | 25.8 | LF | $102.20 | $980.00 | $500.00 | $1,350.00 | $1,750.00 | $1,600.00 | $125.00 | |
| 9 | 6001-6001 | PORTABLE CHANGEABLE MESSAGE SIGN | 20 | DAY | $96.27 | $230.00 | $200.00 | $50.00 | $150.00 | $75.00 | $100.00 | |
| 10 | 6185-6002 | TMA (STATIONARY) | 20 | DAY | $194.37 | $100.00 | $200.00 | $200.00 | $175.00 | $175.00 | $175.00 |