RAISED PAVEMENT MARKINGS
- Let date
- Wednesday, May 5, 2021
- CCSJ
- 6377-16-001
- District
- Wichita Falls
- County
- Wichita
- Highway
- US 82
- Limits
- VARIOUS ROADWAYS to DISTRICTWIDE
- Classification
- Maintenance
- Project number
- RMC - 637716001
- Working days
- 38
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $315,153 | ||
| 1 | BRYDL CONTRACTING, INC. Low bidder | $273,843 | -13.1% | |
| 2 | PMI PAVEMENT MARKING, LLC | $282,724 | -10.3% | +3.2% |
| 3 | PAVEMENT MARKINGS INC. | $285,023 | -9.6% | +4.1% |
| 4 | FC TRAFFIC CONTROL, INC. | $287,000 | -8.9% | +4.8% |
| 5 | CENTERLINE TECHNOLOGIES, LLC | $290,722 | -7.8% | +6.2% |
| 6 | TRP CONSTRUCTION GROUP, LLC | $395,382 | +25.5% | +44.4% |
| 7 | CROSS PLUS CONSTRUCTION, LLC | $421,824 | +33.8% | +54.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 BRYDL CONTRACTI… | #2 PMI PAVEMENT MA… | #3 PAVEMENT MARKIN… | #4 FC TRAFFIC CONT… | #5 CENTERLINE TECH… | #6 TRP CONSTRUCTIO… | #7 CROSS PLUS CONS… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6001 | MOBILIZATION | 1 | LS | $28,650.29 | $12,000.00 | $1,000.00 | $3,500.00 | $8,012.00 | $1.00 | $15,000.00 | |
| 2 | 672-6007 | REFL PAV MRKR TY I-C | 6,148 | EA | $2.60 | $2.50 | $3.00 | $3.80 | $3.00 | $3.00 | $4.00 | |
| 3 | 672-6009 | REFL PAV MRKR TY II-A-A | 28,143 | EA | $2.73 | $2.50 | $3.00 | $3.40 | $3.00 | $3.00 | $4.00 | |
| 4 | 672-6010 | REFL PAV MRKR TY II-C-R | 58,667 | EA | $3.01 | $3.00 | $3.00 | $2.75 | $3.00 | $3.20 | $4.00 | |
| 5 | 6185-6005 | TMA (MOBILE OPERATION) | 114 | DAY | $150.00 | $1.00 | $25.00 | $10.00 | $1.00 | $1.00 | $75.00 |