MISCELLANEOUS BRIDGE REPAIR
- Let date
- Wednesday, March 4, 2020
- CCSJ
- 6340-83-001
- District
- Houston
- County
- Waller
- Highway
- FM 1488
- Limits
- THREE MILE CREEK to THREE MILE CREEK
- Classification
- Maintenance
- Project number
- BPM - 634083001
- Working days
- 15
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $319,750 | ||
| 1 | SCR CIVIL CONSTRUCTION, LLC Low bidder | $149,525 | -53.2% | |
| 2 | JAMES CONSTRUCTION GROUP, L.L.C. | $177,608 | -44.5% | +18.8% |
| 3 | RAGLE CONSTRUCTION, INC. | $223,250 | -30.2% | +49.3% |
| 4 | FORDE CONSTRUCTION COMPANY, INC. | $225,475 | -29.5% | +50.8% |
| 5 | CHAMPION INFRASTRUCTURE, LLC | $302,100 | -5.5% | +102.0% |
| 6 | FNH CONSTRUCTION, LLC | $722,450 | +125.9% | +383.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 SCR CIVIL CONST… | #2 JAMES CONSTRUCT… | #3 RAGLE CONSTRUCT… | #4 FORDE CONSTRUCT… | #5 CHAMPION INFRAS… | #6 FNH CONSTRUCTIO… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6001 | MOBILIZATION | 1 | LS | $30,000.00 | $14,900.00 | $13,147.90 | $22,500.00 | $30,000.00 | $40,000.00 | $75,000.00 |
| 2 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 | MO | $4,000.00 | $12,000.00 | $3,800.00 | $50,000.00 | $40,000.00 | $6,500.00 | $12,500.00 |
| 3 | 4056-6002 | INWATER PILING ENCAPSULATION | 63 | LF | $4,500.00 | $1,900.00 | $2,512.59 | $2,200.00 | $2,325.00 | $4,000.00 | $10,000.00 |
| 4 | 6185-6002 | TMA (STATIONARY) | 9 | DAY | $250.00 | $325.00 | $262.96 | $1,350.00 | $1,000.00 | $400.00 | $550.00 |