CALL OUT TRAFFIC CONTROL
- Let date
- Tuesday, June 4, 2019
- CCSJ
- 6339-15-001
- District
- Abilene
- County
- Howard
- Highway
- IH 20
- Limits
- MITCHELL, HOWARD, to SCURRY AND BORDEN COUNTIES
- Classification
- Maintenance
- Project number
- RMC - 633915001
- Working days
- 365
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,578,570 | ||
| 1 | BARRICADES UNLIMITED Low bidder | $1,536,375 | -2.7% | |
| 2 | NIXON ENGINEERING | $1,657,750 | +5.0% | +7.9% |
| 3 | TOTAL HIGHWAY MAINTENANCE, LLC | $2,021,825 | +28.1% | +31.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 BARRICADES UNLI… | #2 NIXON ENGINEERI… | #3 TOTAL HIGHWAY M… |
|---|---|---|---|---|---|---|---|---|
| 1 | 500-6001 | MOBILIZATION | 1 | LS | $100,000.00 | $25,000.00 | $10,000.00 | $160,000.00 |
| 2 | 6185-6003 | TMA (MOBILE OPERATION) | 9,000 | HR | $90.00 | $95.00 | $90.00 | $125.00 |
| 3 | 7148-6001 | 1 LN CLOSURE 2 LN RD NO SHOULDERS | 2,200 | HR | $140.00 | $140.00 | $200.00 | $145.00 |
| 4 | 7148-6002 | 1 LN CLOSURE 2 LN RD PAVED SHOULDERS | 1,000 | HR | $140.00 | $140.00 | $200.00 | $150.00 |
| 5 | 7148-6003 | 1 LN CLOSURE 4 LN RD | 120 | HR | $110.00 | $50.00 | $200.00 | $165.00 |
| 6 | 7148-6004 | 2 LN CLOSURE 4 LN RD | 35 | HR | $115.00 | $50.00 | $200.00 | $185.00 |
| 7 | 7148-6005 | FREEWAY 1 LANE CLOSURE | 125 | HR | $165.00 | $75.00 | $150.00 | $195.00 |
| 8 | 7148-6006 | FREEWAY 2 LANE CLOSURE | 20 | HR | $145.00 | $75.00 | $200.00 | $225.00 |
| 9 | 7148-6009 | EXIT OR ENTRANCE RAMP CLOSURE | 100 | HR | $125.00 | $50.00 | $100.00 | $165.00 |
| 10 | 7148-6016 | WORK AREA ON SHOULDER | 20 | HR | $116.00 | $50.00 | $200.00 | $165.00 |
| 11 | 7148-6019 | FURNISH ADDITIONAL FLAGGER | 2,250 | HR | $60.00 | $65.00 | $40.00 | $66.50 |
| 12 | 7148-6020 | PILOT VEHICLE AND OPERATOR | 500 | HR | $60.00 | $75.00 | $80.00 | $86.50 |