TRAFFIC CONTROL
- Let date
- Thursday, September 7, 2017
- CCSJ
- 6320-55-001
- District
- San Antonio
- County
- Frio
- Highway
- IH 35
- Limits
- VARIOUS to VARIOUS
- Classification
- Maintenance
- Project number
- RMC - 632055001
- Working days
- 365
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,247,125 | ||
| 1 | AREA WIDE PROTECTIVE, INC. Low bidder | $1,096,294 | -12.1% | |
| 2 | ALTUS TRAFFIC MANAGEMENT LLC | $1,115,863 | -10.5% | +1.8% |
| 3 | K-BAR SERVICES, INC. | $1,133,850 | -9.1% | +3.4% |
| 4 | NIXON ENGINEERING | $1,199,375 | -3.8% | +9.4% |
| 5 | CHAMPION INFRASTRUCTURE, LLC | $1,374,258 | +10.2% | +25.4% |
| 6 | FLASHER EQUIPMENT COMPANY | $1,512,875 | +21.3% | +38.0% |
| 7 | TOTAL HIGHWAY MAINTENANCE, LLC | $1,607,200 | +28.9% | +46.6% |
| 8 | SHORT-LINE CORPORATION | $1,716,125 | +37.6% | +56.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 AREA WIDE PROTE… | #2 ALTUS TRAFFIC M… | #3 K-BAR SERVICES,… | #4 NIXON ENGINEERI… | #5 CHAMPION INFRAS… | #6 FLASHER EQUIPME… | #7 TOTAL HIGHWAY M… | #8 SHORT-LINE CORP… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6033 | MOBILIZATION (CALLOUT) | 250 | EA | $250.00 | $81.27 | $275.00 | $530.00 | $900.00 | $357.50 | $733.00 | $1,000.00 | $125.00 |
| 2 | 6001-6001 | PORTABLE CHANGEABLE MESSAGE SIGN | 50 | DAY | $75.00 | $15.71 | $50.00 | $50.00 | $200.00 | $33.00 | $167.00 | $85.00 | $75.00 |
| 3 | 6185-6001 | TMA (STATIONARY) | 400 | EA | $650.00 | $563.85 | $600.00 | $250.00 | $500.00 | $440.00 | $629.00 | $748.00 | $650.00 |
| 4 | 6185-6003 | TMA (MOBILE OPERATION) | 1,000 | HR | $100.00 | $80.55 | $65.00 | $65.00 | $125.00 | $71.50 | $117.00 | $80.00 | $200.00 |
| 5 | 7148-6001 | 1 LN CLOSURE 2 LN RD NO SHOULDERS | 1,700 | HR | $75.00 | $161.09 | $135.00 | $180.00 | $125.00 | $215.60 | $163.00 | $164.00 | $200.00 |
| 6 | 7148-6002 | 1 LN CLOSURE 2 LN RD PAVED SHOULDERS | 1,000 | HR | $100.00 | $161.16 | $140.00 | $180.00 | $100.00 | $217.80 | $163.00 | $164.00 | $200.00 |
| 7 | 7148-6003 | 1 LN CLOSURE 4 LN RD | 100 | HR | $140.00 | $109.26 | $147.50 | $120.00 | $200.00 | $170.50 | $173.00 | $192.00 | $175.00 |
| 8 | 7148-6004 | 2 LN CLOSURE 4 LN RD | 75 | HR | $150.00 | $139.17 | $147.50 | $100.00 | $100.00 | $280.50 | $211.00 | $242.00 | $150.00 |
| 9 | 7148-6005 | FREEWAY 1 LANE CLOSURE | 175 | HR | $175.00 | $146.67 | $150.00 | $200.00 | $100.00 | $170.50 | $183.00 | $213.00 | $275.00 |
| 10 | 7148-6006 | FREEWAY 2 LANE CLOSURE | 150 | HR | $200.00 | $157.03 | $210.00 | $150.00 | $100.00 | $280.50 | $277.00 | $322.00 | $350.00 |
| 11 | 7148-6007 | FREEWAY 3 LANE CLOSURE | 50 | HR | $225.00 | $202.02 | $250.00 | $150.00 | $100.00 | $385.00 | $333.00 | $383.00 | $500.00 |
| 12 | 7148-6008 | FREEWAY 4 LANE CLOSURE | 50 | HR | $225.00 | $244.91 | $275.00 | $150.00 | $100.00 | $423.50 | $461.00 | $464.00 | $550.00 |
| 13 | 7148-6009 | EXIT OR ENTRANCE RAMP CLOSURE | 200 | HR | $750.00 | $92.97 | $108.50 | $108.50 | $100.00 | $192.50 | $197.00 | $213.00 | $175.00 |
| 14 | 7148-6011 | COMPLETE FREEWAY CLOSURE | 100 | HR | $300.00 | $244.91 | $325.00 | $100.00 | $100.00 | $544.50 | $433.00 | $546.00 | $795.00 |
| 15 | 7148-6012 | ONE LANE FRONTAGE ROAD CLOSURE | 100 | HR | $100.00 | $69.71 | $109.00 | $109.00 | $150.00 | $176.00 | $123.00 | $164.00 | $225.00 |
| 16 | 7148-6016 | WORK AREA ON SHOULDER | 75 | HR | $100.00 | $78.97 | $110.00 | $110.00 | $125.00 | $126.50 | $117.00 | $164.00 | $250.00 |
| 17 | 7148-6018 | MOBILE OPERATIONS | 100 | HR | $275.00 | $161.10 | $185.00 | $120.00 | $175.00 | $220.00 | $223.00 | $201.00 | $200.00 |
| 18 | 7148-6019 | FURNISH ADDITIONAL FLAGGER | 700 | HR | $50.00 | $34.61 | $28.50 | $40.00 | $50.00 | $38.50 | $43.00 | $27.75 | $55.00 |
| 19 | 7148-6020 | PILOT VEHICLE AND OPERATOR | 3,000 | HR | $75.00 | $48.28 | $49.50 | $55.00 | $50.00 | $44.00 | $70.00 | $66.75 | $95.00 |