BRIDGE PREVENTATIVE MAINTENANCE
- Let date
- Wednesday, July 11, 2018
- CCSJ
- 6319-77-001
- District
- Fort Worth
- County
- Tarrant
- Highway
- SH 180
- Limits
- VARIOUS LOCATIONS IN TARRANT, to PALO PINTO AND JACK COUNTIES
- Classification
- Maintenance
- Project number
- BPM - 631977001
- Working days
- 37
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $868,752 | ||
| 1 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC Low bidder | $798,330 | -8.1% | |
| 2 | SELECT STRIPING LLC | $866,299 | -0.3% | +8.5% |
| 3 | RESTEK, INC. | $963,555 | +10.9% | +20.7% |
| 4 | ALTUS CONSTRUCTION LLC | $971,994 | +11.9% | +21.8% |
| 5 | PIERCE R & B LLC | $985,000 | +13.4% | +23.4% |
| 6 | FNH CONSTRUCTION, LLC | $1,069,995 | +23.2% | +34.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 SCOTT TUCKER CO… | #2 SELECT STRIPING… | #3 RESTEK, INC. | #4 ALTUS CONSTRUCT… | #5 PIERCE R & B LLC | #6 FNH CONSTRUCTIO… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 100-6001 | PREPARING ROW | 1.193 | AC | $30,000.00 | $67,134.00 | $18,000.00 | $25,000.00 | $47,339.25 | $15,000.00 | $50,000.00 |
| 2 | 100-6009 | PREPARING ROW (TREE) (6" TO 24" DIA) | 5 | EA | $1,000.00 | $938.00 | $400.00 | $500.00 | $2,705.10 | $1,500.00 | $2,500.00 |
| 3 | 100-6011 | PREPARING ROW(TREE)(24" TO 36" DIA.) | 1 | EA | $1,500.00 | $1,268.00 | $2,000.00 | $1,500.00 | $4,057.65 | $5,999.00 | $5,000.00 |
| 4 | 110-6002 | EXCAVATION (CHANNEL) | 1,107 | CY | $20.00 | $69.00 | $30.00 | $75.00 | $27.94 | $34.00 | $30.00 |
| 5 | 401-6001 | FLOWABLE BACKFILL | 1,355 | CY | $200.00 | $156.00 | $250.00 | $200.00 | $217.68 | $250.00 | $250.00 |
| 6 | 432-6033 | RIPRAP (STONE PROTECTION)(18 IN) | 120 | CY | $150.00 | $197.00 | $120.00 | $210.00 | $164.27 | $299.00 | $185.00 |
| 7 | 432-6035 | RIPRAP (STONE PROTECTION)(24 IN) | 1,675 | CY | $150.00 | $122.00 | $115.00 | $195.00 | $155.44 | $174.00 | $185.00 |
| 8 | 432-6036 | RIPRAP (STONE PROTECTION)(30 IN) | 686 | CY | $250.00 | $117.00 | $120.00 | $180.00 | $173.15 | $185.00 | $210.00 |
| 9 | 500-6001 | MOBILIZATION | 1 | LS | $78,432.00 | $70,421.00 | $86,000.00 | $75,000.00 | $94,137.48 | $98,099.00 | $110,000.00 |
| 10 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 | MO | $2,000.00 | $8,597.00 | $26,240.00 | $6,000.00 | $12,172.95 | $5,000.00 | $8,500.00 |
| 11 | 6185-6002 | TMA (STATIONARY) | 37 | DAY | $220.00 | $542.00 | $400.00 | $200.00 | $1,149.67 | $267.00 | $250.00 |