‹ Feb 2018 results
MISCELLANEOUS BRIDGE REPAIR
- Let date
- Thursday, February 1, 2018
- CCSJ
- 6312-37-001
- District
- Abilene
- County
- Scurry
- Highway
- US 84
- Limits
- VARIOUS LOCATIONS IN to THE ABILENE DISTRICT
- Classification
- Maintenance
- Project number
- BPM - 631237001
- Working days
- 62
Bidders 11
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $400,297 | | |
| 1 |
SCR CIVIL CONSTRUCTION, LLC Low bidder |
$343,510 |
-14.2% |
|
| 2 |
SCOTT TUCKER CONSTRUCTION COMPANY, LLC |
$456,662 |
+14.1% |
+32.9% |
| 3 |
WINDING ROAD CONSTRUCTION, INC. |
$498,554 |
+24.5% |
+45.1% |
| 4 |
RESTEK, INC. |
$558,625 |
+39.6% |
+62.6% |
| 5 |
PBX BRIDGE COMPANY |
$563,139 |
+40.7% |
+63.9% |
| 6 |
L.C. JORDAN & SON |
$609,575 |
+52.3% |
+77.5% |
| 7 |
SALINAS CONSTRUCTION TECHNOLOGIES, LTD. |
$611,475 |
+52.8% |
+78.0% |
| 8 |
CHAMPION INFRASTRUCTURE, LLC |
$659,110 |
+64.7% |
+91.9% |
| 9 |
O. TREVINO CONSTRUCTION, LLC |
$668,120 |
+66.9% |
+94.5% |
| 10 |
GILVIN-TERRILL, LTD. |
$693,200 |
+73.2% |
+101.8% |
| 11 |
FNH CONSTRUCTION, LLC |
$712,600 |
+78.0% |
+107.4% |
Bid tab: unit prices 6 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 SCR CIVIL CONST… | #2 SCOTT TUCKER CO… | #3 WINDING ROAD CO… | #4 RESTEK, INC. | #5 PBX BRIDGE COMP… | #6 L.C. JORDAN & S… | #7 SALINAS CONSTRU… | #8 CHAMPION INFRAS… |
| 1 | 429-6004 |
CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 291 | SF |
$125.00 |
$110.00 |
$127.72 |
$274.00 |
$75.00 |
$50.00 |
$125.00 |
$293.34 |
$210.00 |
| 2 | 438-6001 |
CLEANING AND SEALING EXISTING JOINTS | 1,080 | LF |
$18.00 |
$70.00 |
$48.28 |
$39.50 |
$60.00 |
$24.00 |
$40.00 |
$120.57 |
$50.00 |
| 3 | 500-6001 |
MOBILIZATION | 1 | LS |
$56,681.50 |
$34,200.00 |
$62,333.30 |
$40,000.00 |
$75,000.00 |
$54,619.00 |
$50,000.00 |
$108,617.38 |
$60,000.00 |
| 4 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 | MO |
$5,000.00 |
$8,550.00 |
$26,854.18 |
$13,000.00 |
$15,000.00 |
$20,000.00 |
$5,000.00 |
$14,574.00 |
$8,000.00 |
| 5 | 785-6006 |
BRIDGE JOINT REPAIR (HEADER) | 1,090 | LF |
$220.00 |
$150.00 |
$140.83 |
$224.00 |
$300.00 |
$345.00 |
$400.00 |
$168.31 |
$400.00 |
| 6 | 6001-6002 |
PORTABLE CHANGEABLE MESSAGE SIGN | 4 | EA |
$7,000.00 |
$1,000.00 |
$11,024.63 |
$10,000.00 |
$2,500.00 |
$3,000.00 |
$6,000.00 |
$11,381.52 |
$4,000.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 11.