‹ May 2017 results
RIP RAP FOR SCOUR REPAIR
- Let date
- Tuesday, May 9, 2017
- CCSJ
- 6311-27-001
- District
- Bryan
- County
- Leon
- Highway
- SH 75
- Limits
- VARIOUS to VARIOUS
- Classification
- Local Let
- Project number
- BPM - 631127001
- Working days
- 20
Bidders 10
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $63,518 | | |
| 1 |
TEXCAVATION COMPANY LLC. Low bidder |
$56,555 |
-11.0% |
|
| 2 |
TCB CONSTRUCTION, INC |
$57,825 |
-9.0% |
+2.2% |
| 3 |
CHAMPION INFRASTRUCTURE, LLC |
$59,110 |
-6.9% |
+4.5% |
| 4 |
RAFTER JK CONSTRUCTION, LLC |
$59,751 |
-5.9% |
+5.7% |
| 5 |
BXB GROUP INCORPORATION |
$63,909 |
+0.6% |
+13.0% |
| 6 |
CROSS PLUS CONSTRUCTION, LLC |
$71,145 |
+12.0% |
+25.8% |
| 7 |
FNH CONSTRUCTION, LLC |
$80,125 |
+26.1% |
+41.7% |
| 8 |
TREVWAY, INC. |
$83,606 |
+31.6% |
+47.8% |
| 9 |
L.C. JORDAN & SON |
$88,680 |
+39.6% |
+56.8% |
| 10 |
3LW CIVIL LLC |
$210,675 |
+231.7% |
+272.5% |
Bid tab: unit prices 9 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 TEXCAVATION COM… | #2 TCB CONSTRUCTIO… | #3 CHAMPION INFRAS… | #4 RAFTER JK CONST… | #5 BXB GROUP INCOR… | #6 CROSS PLUS CONS… | #7 FNH CONSTRUCTIO… | #8 TREVWAY, INC. |
| 1 | 110-6002 |
EXCAVATION (CHANNEL) | 33 | CY |
$30.00 |
$30.00 |
$150.00 |
$95.00 |
$236.37 |
$148.00 |
$40.00 |
$100.00 |
$250.00 |
| 2 | 164-6001 |
BROADCAST SEED (PERM) (RURAL) (SANDY) | 125 | SY |
$0.5000 |
$2.00 |
$4.00 |
$2.00 |
$40.80 |
$3.00 |
$3.00 |
$5.00 |
$6.25 |
| 3 | 403-6006 |
TEMPORARY SPL SHORING (COFFERDAM) | 175 | SF |
$100.00 |
$25.00 |
$15.00 |
$35.00 |
$25.15 |
$40.00 |
$34.00 |
$60.00 |
$25.00 |
| 4 | 432-6024 |
RIPRAP (STONE COMMON)(DRY)(12 IN) | 110 | CY |
$160.00 |
$250.00 |
$165.00 |
$200.00 |
$125.52 |
$145.00 |
$350.00 |
$210.00 |
$400.00 |
| 5 | 432-6028 |
RIPRAP (STONE COMMON)(GROUT)(6 IN) | 40 | CY |
$300.00 |
$491.00 |
$245.00 |
$400.00 |
$288.46 |
$250.00 |
$350.00 |
$210.00 |
$400.00 |
| 6 | 500-6001 |
MOBILIZATION | 1 | LS |
$5,365.00 |
$1,000.00 |
$17,000.00 |
$5,000.00 |
$2,499.94 |
$10,500.00 |
$5,000.00 |
$8,000.00 |
$7,000.00 |
| 7 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 | MO |
$4,500.00 |
$500.00 |
$1,800.00 |
$2,800.00 |
$4,100.00 |
$6,500.00 |
$2,000.00 |
$12,500.00 |
$1,200.00 |
| 8 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 200 | LF |
$3.50 |
$6.00 |
$5.00 |
$4.00 |
$19.00 |
$8.00 |
$5.00 |
$4.00 |
$3.00 |
| 9 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 200 | LF |
$1.50 |
$3.00 |
$1.00 |
$1.00 |
$13.02 |
$3.00 |
$5.00 |
$2.00 |
$1.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 10.