‹ Nov 2016 results
REMOVE AND REPLACE MBGF
- Let date
- Friday, November 4, 2016
- CCSJ
- 6304-98-001
- District
- San Antonio
- County
- Bexar
- Highway
- IH 35
- Limits
- IH 410 to SPUR 422
- Classification
- Maintenance
- Project number
- RMC - 630498001
- Working days
- 34
Bidders 9
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $573,082 | | |
| 1 |
K-BAR SERVICES, INC. Low bidder |
$568,940 |
-0.7% |
|
| 2 |
Curran Contracting Company |
$586,012 |
+2.3% |
+3.0% |
| 3 |
ANGEL BROTHERS HOLDINGS CORP. |
$614,664 |
+7.3% |
+8.0% |
| 4 |
SHORT-LINE CORPORATION |
$615,155 |
+7.3% |
+8.1% |
| 5 |
ODUM SERVICES, L.P. |
$616,330 |
+7.5% |
+8.3% |
| 6 |
DEAN WORD COMPANY, LTD. |
$653,596 |
+14.0% |
+14.9% |
| 7 |
FNH CONSTRUCTION, LLC |
$771,850 |
+34.7% |
+35.7% |
| 8 |
ACME BRIDGE COMPANY, INC. |
$815,904 |
+42.4% |
+43.4% |
| 9 |
3LW MANAGEMENT, LLC |
$848,434 |
+48.0% |
+49.1% |
Bid tab: unit prices 21 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 K-BAR SERVICES,… | #2 Curran Contract… | #3 ANGEL BROTHERS … | #4 SHORT-LINE CORP… | #5 ODUM SERVICES, … | #6 DEAN WORD COMPA… | #7 FNH CONSTRUCTIO… | #8 ACME BRIDGE COM… |
| 1 | 104-6009 |
REMOVING CONC (RIPRAP) | 107 | SY |
$15.50 |
$50.00 |
$15.00 |
$40.00 |
$100.00 |
$25.00 |
$20.35 |
$25.00 |
$30.00 |
| 2 | 432-6001 |
RIPRAP (CONC)(4 IN) | 219 | CY |
$385.00 |
$475.00 |
$605.00 |
$565.00 |
$365.00 |
$550.00 |
$689.99 |
$550.00 |
$950.00 |
| 3 | 432-6045 |
RIPRAP (MOW STRIP)(4 IN) | 325 | CY |
$535.00 |
$475.00 |
$430.00 |
$565.00 |
$365.00 |
$550.00 |
$579.45 |
$650.00 |
$950.00 |
| 4 | 500-6001 |
MOBILIZATION | 1 | LS |
$40,970.00 |
$50,000.00 |
$49,000.00 |
$62,000.00 |
$100,000.00 |
$50,000.00 |
$70,225.60 |
$70,000.00 |
$65,000.00 |
| 5 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 | MO |
$10,000.00 |
$6,000.00 |
$13,000.00 |
$25,000.00 |
$25,000.00 |
$4,000.00 |
$10,357.71 |
$8,500.00 |
$11,350.00 |
| 6 | 506-6041 |
BIODEG EROSN CONT LOGS (INSTL) (12") | 3,790 | LF |
$4.85 |
$6.00 |
$4.00 |
$4.00 |
$7.00 |
$6.00 |
$3.62 |
$10.00 |
$6.00 |
| 7 | 506-6043 |
BIODEG EROSN CONT LOGS (REMOVE) | 3,790 | LF |
$2.50 |
$1.00 |
$1.05 |
$1.10 |
$2.00 |
$2.00 |
$1.05 |
$5.00 |
$2.00 |
| 8 | 540-6001 |
MTL W-BEAM GD FEN (TIM POST) | 6,375 | LF |
$22.00 |
$20.00 |
$19.00 |
$17.00 |
$22.00 |
$21.00 |
$22.44 |
$25.00 |
$18.70 |
| 9 | 540-6006 |
MTL BEAM GD FEN TRANS (THRIE-BEAM) | 2 | EA |
$1,475.00 |
$1,500.00 |
$2,700.00 |
$1,700.00 |
$2,000.00 |
$1,400.00 |
$1,802.65 |
$1,850.00 |
$1,340.00 |
| 10 | 540-6016 |
DOWNSTREAM ANCHOR TERMINAL SECTION | 15 | EA |
$1,025.00 |
$1,300.00 |
$1,090.00 |
$700.00 |
$1,200.00 |
$1,250.00 |
$724.50 |
$1,850.00 |
$777.00 |
| 11 | 540-6018 |
MTL BM GD FEN TRANS (NON - SYM) | 2 | EA |
$625.00 |
$1,000.00 |
$550.00 |
$450.00 |
$750.00 |
$800.00 |
$457.80 |
$1,850.00 |
$491.00 |
| 12 | 542-6001 |
REMOVE METAL BEAM GUARD FENCE | 5,650 | LF |
$2.50 |
$2.00 |
$2.95 |
$0.8000 |
$1.00 |
$3.00 |
$0.8400 |
$3.00 |
$0.9000 |
| 13 | 542-6002 |
REMOVE TERMINAL ANCHOR SECTION | 18 | EA |
$215.00 |
$100.00 |
$300.00 |
$90.00 |
$100.00 |
$120.00 |
$94.50 |
$500.00 |
$101.00 |
| 14 | 542-6004 |
RM MTL BM GD FENCE TRANS (THRIE-BEAM) | 2 | EA |
$158.00 |
$250.00 |
$300.00 |
$50.00 |
$500.00 |
$200.00 |
$47.25 |
$500.00 |
$50.70 |
| 15 | 544-6001 |
GUARDRAIL END TREATMENT (INSTALL) | 15 | EA |
$2,350.00 |
$2,800.00 |
$2,500.00 |
$1,800.00 |
$2,500.00 |
$2,050.00 |
$1,844.85 |
$2,850.00 |
$1,980.00 |
| 16 | 544-6003 |
GUARDRAIL END TREATMENT (REMOVE) | 11 | EA |
$235.00 |
$400.00 |
$350.00 |
$70.00 |
$500.00 |
$220.00 |
$68.25 |
$1,100.00 |
$73.20 |
| 17 | 658-6013 |
INSTL DEL ASSM (D-SW)SZ (BRF)CTB | 3 | EA |
$18.50 |
$20.00 |
$15.00 |
$20.00 |
$25.00 |
$25.00 |
$15.75 |
$100.00 |
$11.30 |
| 18 | 658-6026 |
INSTL DEL ASSM (D-SY)SZ (BRF)CTB | 3 | EA |
$18.80 |
$20.00 |
$15.00 |
$22.00 |
$25.00 |
$25.00 |
$15.75 |
$100.00 |
$11.30 |
| 19 | 658-6061 |
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2 | 40 | EA |
$45.00 |
$20.00 |
$20.00 |
$30.00 |
$15.00 |
$40.00 |
$21.00 |
$100.00 |
$13.50 |
| 20 | 658-6064 |
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2 | 37 | EA |
$38.50 |
$20.00 |
$20.00 |
$32.00 |
$15.00 |
$40.00 |
$21.00 |
$100.00 |
$13.50 |
| 21 | 6001-6001 |
PORTABLE CHANGEABLE MESSAGE SIGN | 60 | DAY |
$85.00 |
$50.00 |
$140.00 |
$200.00 |
$88.00 |
$220.00 |
$137.50 |
$150.00 |
$78.80 |
Showing the first 8 bidders. The Excel and CSV downloads include all 9.