MILLING ASPHALT PAVEMENT TO IMPROVE RIDE/DRAINAGE
- Let date
- Friday, February 2, 2018
- CCSJ
- 6298-24-001
- District
- Brownwood
- County
- Mills
- Highway
- SH 16
- Limits
- VARIOUS LOCATIONS DISTRICT-WIDE to ***
- Classification
- Maintenance
- Project number
- RMC - 629824001
- Working days
- 45
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $519,664 | ||
| 1 | DUSTROL, INC. Low bidder | $385,345 | -25.8% | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $487,101 | -6.3% | +26.4% |
| 3 | TEX OP CONSTRUCTION, LP | $626,531 | +20.6% | +62.6% |
| 4 | A. L. HELMCAMP, INC. | $846,318 | +62.9% | +119.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 DUSTROL, INC. | #2 BIG CREEK CONST… | #3 TEX OP CONSTRUC… | #4 A. L. HELMCAMP,… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 354-6002 | PLAN & TEXT ASPH CONC PAV(0" TO 2") | 301,267.11 | SY | $1.55 | $1.14 | $1.50 | $1.84 | |
| 2 | 500-6001 | MOBILIZATION | 1 | LS | $42,000.00 | $7,500.00 | $23,000.00 | $48,000.00 | |
| 3 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 | MO | $5,000.00 | $15,000.00 | $5,000.00 | $11,000.00 | |
| 4 | 662-6109 | WK ZN PAV MRK SHT TERM (TAB)TY W | 200 | EA | $0.5000 | $2.00 | $1.00 | $1.00 | |
| 5 | 662-6111 | WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 2,000 | EA | $0.3000 | $2.00 | $1.00 | $1.00 |