PALM TREE TRIMMING AND REMOVAL
- Let date
- Tuesday, July 11, 2017
- CCSJ
- 6296-68-001
- District
- Pharr
- County
- Hidalgo
- Highway
- IH 2
- Limits
- DISTRICT WIDE to VARIOUS
- Classification
- Maintenance
- Project number
- RMC - 629668001
- Working days
- 160
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $148,200 | ||
| 1 | CROSS PLUS CONSTRUCTION, LLC Low bidder | $392,736 | +165.0% | |
| 2 | CHAMPION INFRASTRUCTURE, LLC | $1,130,200 | +662.6% | +187.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 CROSS PLUS CONS… | #2 CHAMPION INFRAS… |
|---|---|---|---|---|---|---|---|
| 1 | 500-6001 | MOBILIZATION | 1 | LS | $15,000.00 | $20,000.00 | $40,000.00 |
| 2 | 752-6007 | TREE REMOVAL (18" - 24" DIA) | 256 | EA | $125.00 | $456.00 | $1,200.00 |
| 3 | 752-6023 | TREE TRIMMING | 30 | EA | $40.00 | $200.00 | $1,100.00 |
| 4 | 7004-6004 | TREE TRIMMING | 2,500 | EA | $40.00 | $100.00 | $300.00 |