BRIDGE EROSION REPAIR
- Let date
- Wednesday, November 13, 2013
- CCSJ
- 6260-33-001
- District
- Dallas
- County
- Navarro
- Highway
- IH 45
- Limits
- IH45 FROM NAVARRO COUNTY LINE TO to ELLIS COUNTY LINE
- Classification
- Local Let
- Project number
- BPM - 626033001
- Working days
- 45
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $79,898 | ||
| 1 | EASTER CONSTRUCTION INC. Low bidder | $83,210 | +4.1% | |
| 2 | TEXAS TREE & LANDSCAPE, LTD. | $102,750 | +28.6% | +23.5% |
| 3 | L.C. JORDAN & SON | $103,230 | +29.2% | +24.1% |
| 4 | 3LW MANAGEMENT, LLC | $119,370 | +49.4% | +43.5% |
| 5 | BEAR CREEK CONSTRUCTION, LLC | $129,478 | +62.1% | +55.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 EASTER CONSTRUC… | #2 TEXAS TREE & LA… | #3 L.C. JORDAN & S… | #4 3LW MANAGEMENT,… | #5 BEAR CREEK CONS… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 100-2003 | PREPARING ROW(TREE)(5" TO 12" DIA) | 14 | EA | $418.92 | $250.00 | $200.00 | $250.00 | $950.00 | $293.00 |
| 2 | 104-2009 | REMOVING CONC (RIPRAP) | 38 | SY | $5.79 | $10.00 | $25.00 | $45.00 | $26.50 | $35.00 |
| 3 | 104-2044 | REMOVING CONC (FLUME) | 14 | SY | $11.12 | $20.00 | $25.00 | $80.00 | $72.00 | $69.50 |
| 4 | 132-2006 | EMBANKMENT (FINAL)(DENS CONT)(TY C) | 300 | CY | $14.13 | $45.00 | $30.00 | $25.00 | $25.00 | $30.50 |
| 5 | 400-2001 | STRUCT EXCAV | 250 | CY | $5.57 | $45.00 | $25.00 | $20.00 | $12.00 | $8.50 |
| 6 | 401-2001 | FLOWABLE BACKFILL | 22 | CY | $186.00 | $150.00 | $200.00 | $200.00 | $190.00 | $80.00 |
| 7 | 432-2002 | RIPRAP (CONC)(5 IN) | 175 | CY | $326.36 | $200.00 | $400.00 | $400.00 | $445.00 | $514.50 |
| 8 | 500-2001 | MOBILIZATION | 1 | LS | $6,820.00 | $16,000.00 | $9,000.00 | $10,000.00 | $11,500.00 | $20,000.00 |