| 1 | 100-6002 |
PREPARING ROW | 38.6 | STA |
$500.00 |
$500.00 |
$750.00 |
$400.00 |
$500.00 |
$463.00 |
$2,000.00 |
$3,850.00 |
$1,263.19 |
| 2 | 100-6004 |
PREPARING ROW(TREE)(12" TO 24" DIA) | 1 | EA |
$975.00 |
$1,000.00 |
$500.00 |
$1,000.00 |
$1,436.00 |
$1,140.00 |
$3,000.00 |
$500.00 |
$3,208.00 |
| 3 | 100-6011 |
PREPARING ROW(TREE)(24" TO 36" DIA.) | 1 | EA |
$2,500.00 |
$1,000.00 |
$500.00 |
$2,000.00 |
$3,200.00 |
$1,720.00 |
$10,000.00 |
$900.00 |
$2,616.00 |
| 4 | 104-6017 |
REMOVING CONC (DRIVEWAYS) | 1,984 | SY |
$12.50 |
$20.00 |
$25.00 |
$15.00 |
$30.00 |
$16.94 |
$20.00 |
$45.00 |
$61.43 |
| 5 | 104-6029 |
REMOVING CONC (CURB OR CURB & GUTTER) | 449 | LF |
$12.00 |
$20.00 |
$25.00 |
$10.00 |
$35.00 |
$22.15 |
$20.00 |
$22.00 |
$42.87 |
| 6 | 105-6020 |
REMOVING STAB BASE & ASPH PAV (12") | 110 | SY |
$9.50 |
$20.00 |
$18.50 |
$15.00 |
$15.00 |
$30.00 |
$30.00 |
$225.00 |
$54.97 |
| 7 | 105-6071 |
REMOVING STAB BASE & ASPH PAV (5" - 6") | 350 | SY |
$7.50 |
$20.00 |
$18.50 |
$20.00 |
$15.00 |
$14.20 |
$20.00 |
$35.00 |
$43.19 |
| 8 | 110-6001 |
EXCAVATION (ROADWAY) | 234 | CY |
$25.00 |
$50.00 |
$30.00 |
$20.00 |
$10.00 |
$30.00 |
$30.00 |
$43.00 |
$213.20 |
| 9 | 132-6006 |
EMBANKMENT (FINAL)(DENS CONT)(TY C) | 286 | CY |
$35.00 |
$50.00 |
$30.00 |
$30.00 |
$25.00 |
$46.00 |
$50.00 |
$52.00 |
$116.29 |
| 10 | 160-6003 |
FURNISHING AND PLACING TOPSOIL (4") | 3,610 | SY |
$1.25 |
$4.00 |
$3.50 |
$3.00 |
$1.50 |
$15.36 |
$10.00 |
$4.00 |
$12.00 |
| 11 | 162-6002 |
BLOCK SODDING | 3,610 | SY |
$4.50 |
$8.00 |
$6.50 |
$6.00 |
$5.00 |
$11.37 |
$10.00 |
$7.00 |
$9.98 |
| 12 | 164-6071 |
BROADCAST SEED (TEMP)(WARM OR COOL) | 3,610 | SY |
$1.00 |
$1.00 |
$0.1000 |
$1.00 |
$0.5000 |
$1.14 |
$2.00 |
$2.00 |
$3.00 |
| 13 | 168-6001 |
VEGETATIVE WATERING | 106.68 | MG |
$20.00 |
$50.00 |
$10.00 |
$25.00 |
$14.00 |
$49.50 |
$50.00 |
$100.00 |
$100.00 |
| 14 | 351-6008 |
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") | 134 | SY |
$75.00 |
$120.00 |
$155.00 |
$200.00 |
$140.00 |
$532.00 |
$150.00 |
$295.00 |
$300.00 |
| 15 | 460-6003 |
CMP (GAL STL 24 IN) | 6 | LF |
$95.00 |
$150.00 |
$175.00 |
$125.00 |
$125.00 |
$171.00 |
$150.00 |
$200.00 |
$500.00 |
| 16 | 464-6003 |
RC PIPE (CL III)(18 IN) | 81 | LF |
$75.00 |
$75.00 |
$65.57 |
$200.00 |
$115.00 |
$110.00 |
$150.00 |
$200.00 |
$300.00 |
| 17 | 464-6005 |
RC PIPE (CL III)(24 IN) | 63 | LF |
$115.00 |
$150.00 |
$81.89 |
$300.00 |
$135.00 |
$117.00 |
$250.00 |
$300.00 |
$300.00 |
| 18 | 465-6005 |
JCTBOX(COMPL)(PJB)(3FTX3FT) | 4 | EA |
$2,750.00 |
$4,000.00 |
$6,250.00 |
$4,000.00 |
$6,000.00 |
$7,880.00 |
$12,500.00 |
$9,500.00 |
$6,600.00 |
| 19 | 465-6126 |
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT) | 4 | EA |
$850.00 |
$6,000.00 |
$6,250.00 |
$4,500.00 |
$7,500.00 |
$7,880.00 |
$12,500.00 |
$5,300.00 |
$9,000.00 |
| 20 | 466-6097 |
HEADWALL (CH - PW - 0) (DIA= 24 IN) | 1 | EA |
$4,500.00 |
$10,000.00 |
$6,120.00 |
$3,000.00 |
$15,000.00 |
$19,600.00 |
$8,500.00 |
$9,020.00 |
$15,000.00 |
| 21 | 467-6363 |
SET (TY II) (18 IN) (RCP) (6: 1) (P) | 4 | EA |
$800.00 |
$1,200.00 |
$1,374.00 |
$1,000.00 |
$1,800.00 |
$2,065.00 |
$2,250.00 |
$1,800.00 |
$1,500.00 |
| 22 | 476-6013 |
JACK BOR OR TUN PIPE(24 IN)(RC)(CL III) | 63 | LF |
$1,250.00 |
$230.00 |
$405.00 |
$500.00 |
$1,550.00 |
$1,208.00 |
$2,000.00 |
$700.00 |
$1,500.00 |
| 23 | 479-6005 |
ADJUSTING MANHOLES (WATER VALVE BOX) | 2 | EA |
$650.00 |
$500.00 |
$350.00 |
$600.00 |
$600.00 |
$650.00 |
$1,500.00 |
$1,500.00 |
$500.00 |
| 24 | 496-6006 |
REMOV STR (HEADWALL) | 1 | EA |
$300.00 |
$1,000.00 |
$1,250.00 |
$1,000.00 |
$1,600.00 |
$1,045.00 |
$2,500.00 |
$1,200.00 |
$500.00 |
| 25 | 496-6016 |
REMOV STR (PIPE) | 2 | EA |
$1,500.00 |
$500.00 |
$700.00 |
$500.00 |
$650.00 |
$2,100.00 |
$1,500.00 |
$1,500.00 |
$500.00 |
| 26 | 500-6001 |
MOBILIZATION | 1 | LS |
$75,000.00 |
$50,000.00 |
$80,000.00 |
$70,000.00 |
$80,000.00 |
$103,600.00 |
$100,000.00 |
$100,000.00 |
$100,000.00 |
| 27 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 | MO |
$4,000.00 |
$4,000.00 |
$15,725.79 |
$3,000.00 |
$3,500.00 |
$7,300.00 |
$8,500.00 |
$6,500.00 |
$1,500.00 |
| 28 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 429 | LF |
$4.50 |
$4.00 |
$3.50 |
$4.00 |
$4.00 |
$7.99 |
$4.00 |
$1.00 |
$3.00 |
| 29 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 429 | LF |
$4.50 |
$1.00 |
$1.00 |
$1.00 |
$1.00 |
$2.25 |
$2.00 |
$1.00 |
$3.00 |
| 30 | 529-6007 |
CONC CURB & GUTTER (TY I) | 1,253 | LF |
$21.50 |
$40.00 |
$40.00 |
$35.00 |
$50.00 |
$46.42 |
$65.00 |
$32.00 |
$48.08 |
| 31 | 530-6004 |
DRIVEWAYS (CONC) | 1,811 | SY |
$70.00 |
$100.00 |
$92.50 |
$130.00 |
$110.00 |
$97.00 |
$95.00 |
$139.00 |
$175.00 |
| 32 | 530-6017 |
DRIVEWAYS (CONC) (HES) | 114 | SY |
$115.00 |
$120.00 |
$100.00 |
$200.00 |
$121.00 |
$256.00 |
$125.00 |
$199.00 |
$247.00 |
| 33 | 531-6003 |
CONC SIDEWALKS (6") | 1,558 | SY |
$70.00 |
$90.00 |
$105.00 |
$130.00 |
$95.00 |
$128.15 |
$75.00 |
$125.00 |
$149.00 |
| 34 | 531-6004 |
CURB RAMPS (TY 1) | 2 | EA |
$2,000.00 |
$3,000.00 |
$1,800.00 |
$2,500.00 |
$3,000.00 |
$1,012.00 |
$3,250.00 |
$2,700.00 |
$3,200.00 |
| 35 | 531-6006 |
CURB RAMPS (TY 3) | 2 | EA |
$2,000.00 |
$3,000.00 |
$1,920.00 |
$2,500.00 |
$4,200.00 |
$1,600.00 |
$3,250.00 |
$2,800.00 |
$3,208.00 |
| 36 | 531-6010 |
CURB RAMPS (TY 7) | 6 | EA |
$2,000.00 |
$3,000.00 |
$1,950.00 |
$2,500.00 |
$3,250.00 |
$1,570.00 |
$3,250.00 |
$2,900.00 |
$3,200.00 |
| 37 | 560-6001 |
MAILBOX INSTALL-S (TWG-POST) TY 1 | 1 | EA |
$350.00 |
$500.00 |
$324.50 |
$700.00 |
$765.00 |
$400.00 |
$1,000.00 |
$450.00 |
$900.00 |
| 38 | 560-6002 |
MAILBOX INSTALL-D (TWG-POST) TY 1 | 1 | EA |
$400.00 |
$500.00 |
$352.00 |
$725.00 |
$770.00 |
$460.00 |
$1,000.00 |
$450.00 |
$900.00 |
| 39 | 560-6003 |
MAILBOX INSTALL-M (TWG-POST) TY 1 | 1 | EA |
$850.00 |
$500.00 |
$546.70 |
$850.00 |
$1,115.00 |
$740.00 |
$1,000.00 |
$450.00 |
$900.00 |
| 40 | 644-6001 |
IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 12 | EA |
$650.00 |
$600.00 |
$709.50 |
$850.00 |
$880.00 |
$1,025.00 |
$1,500.00 |
$2,000.00 |
$1,600.00 |
| 41 | 644-6004 |
IN SM RD SN SUP&AM TY10BWG(1)SA(T) | 2 | EA |
$750.00 |
$600.00 |
$797.50 |
$1,000.00 |
$1,115.00 |
$1,365.00 |
$1,500.00 |
$795.00 |
$2,310.00 |
| 42 | 644-6027 |
IN SM RD SN SUP&AM TYS80(1)SA(P) | 1 | EA |
$750.00 |
$600.00 |
$805.75 |
$1,200.00 |
$1,226.00 |
$1,600.00 |
$1,500.00 |
$1,600.00 |
$213.00 |
| 43 | 644-6076 |
REMOVE SM RD SN SUP&AM | 12 | EA |
$95.00 |
$100.00 |
$126.50 |
$200.00 |
$169.00 |
$171.00 |
$500.00 |
$200.00 |
$200.00 |
| 44 | 668-6076 |
PREFAB PAV MRK TY C (W) (24") (SLD) | 263 | LF |
$15.00 |
$30.00 |
$14.80 |
$25.00 |
$36.00 |
$27.00 |
$20.00 |
$12.00 |
$7.00 |
| 45 | 678-6008 |
PAV SURF PREP FOR MRK (24") | 263 | LF |
$3.50 |
$6.00 |
$1.49 |
$2.00 |
$6.50 |
$2.25 |
$20.00 |
$17.00 |
$5.00 |
| 46 | 6001-6002 |
PORTABLE CHANGEABLE MESSAGE SIGN | 2 | EA |
$12,500.00 |
$1,000.00 |
$6,500.00 |
$7,500.00 |
$8,500.00 |
$7,600.00 |
$16,500.00 |
$2,000.00 |
$16,000.00 |
| 47 | 6185-6005 |
TMA (MOBILE OPERATION) | 50 | DAY |
$400.00 |
$300.00 |
$1.00 |
$300.00 |
$230.00 |
$900.00 |
$550.00 |
$1,000.00 |
$400.00 |