REPLACE BRIDGE AND APPROACHES
- Let date
- Wednesday, October 4, 2017
- CCSJ
- 0913-28-064
- District
- Yoakum
- County
- Fayette
- Highway
- CR
- Limits
- AT MIDDLE CREEK CR 160 to (HERZIK ROAD)
- Classification
- Construction
- Project number
- BR 2016(325)
- Working days
- 90
Bidders 10
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $380,956 | | |
| 1 |
HILL COUNTRY BRIDGE, INC. Low bidder |
$349,288 |
-8.3% |
|
| 2 |
ACME BRIDGE COMPANY, INC. |
$368,916 |
-3.2% |
+5.6% |
| 3 |
SB CONTRACTORS LLC |
$381,326 |
+0.1% |
+9.2% |
| 4 |
TREVWAY, INC. |
$385,062 |
+1.1% |
+10.2% |
| 5 |
RELMCO, INC. |
$385,861 |
+1.3% |
+10.5% |
| 6 |
3LW CIVIL LLC |
$388,286 |
+1.9% |
+11.2% |
| 7 |
A GREATER AUSTIN DEVELOPMENT COMPANY, LTD. |
$398,140 |
+4.5% |
+14.0% |
| 8 |
DEAN WORD COMPANY, LTD. |
$417,161 |
+9.5% |
+19.4% |
| 9 |
JOHN REED AND COMPANY, LLC |
$437,679 |
+14.9% |
+25.3% |
| 10 |
FUQUA CONSTRUCTION CO., INC. |
$470,308 |
+23.5% |
+34.6% |
Bid tab: unit prices 33 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 HILL COUNTRY BR… | #2 ACME BRIDGE COM… | #3 SB CONTRACTORS … | #4 TREVWAY, INC. | #5 RELMCO, INC. | #6 3LW CIVIL LLC | #7 A GREATER AUSTI… | #8 DEAN WORD COMPA… |
| 1 | 110-6001 |
EXCAVATION (ROADWAY) | 347 | CY |
$25.00 |
$24.41 |
$22.00 |
$20.00 |
$25.00 |
$9.75 |
$30.00 |
$25.00 |
$27.86 |
| 2 | 132-6005 |
EMBANKMENT (FINAL)(ORD COMP)(TY C) | 96 | CY |
$25.00 |
$20.94 |
$22.00 |
$20.00 |
$31.00 |
$25.93 |
$50.00 |
$50.00 |
$15.78 |
| 3 | 150-6002 |
BLADING | 10 | HR |
$150.00 |
$97.85 |
$180.00 |
$55.00 |
$100.00 |
$82.81 |
$200.00 |
$130.00 |
$83.10 |
| 4 | 164-6003 |
BROADCAST SEED (PERM) (RURAL) (CLAY) | 648 | SY |
$3.00 |
$1.80 |
$1.05 |
$2.50 |
$3.00 |
$1.30 |
$1.00 |
$1.10 |
$1.84 |
| 5 | 164-6009 |
BROADCAST SEED (TEMP) (WARM) | 162 | SY |
$3.00 |
$7.21 |
$1.05 |
$2.00 |
$3.00 |
$1.30 |
$1.00 |
$1.10 |
$7.35 |
| 6 | 164-6011 |
BROADCAST SEED (TEMP) (COOL) | 162 | SY |
$3.00 |
$7.21 |
$1.05 |
$2.00 |
$3.00 |
$1.30 |
$1.00 |
$1.10 |
$7.35 |
| 7 | 168-6001 |
VEGETATIVE WATERING | 3.6 | MG |
$150.00 |
$224.88 |
$97.40 |
$150.00 |
$100.00 |
$250.90 |
$85.00 |
$200.00 |
$129.65 |
| 8 | 247-6366 |
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 215 | CY |
$125.00 |
$127.63 |
$80.00 |
$105.00 |
$155.00 |
$104.97 |
$85.00 |
$140.00 |
$113.64 |
| 9 | 310-6009 |
PRIME COAT (MC-30) | 180 | GAL |
$10.00 |
$8.24 |
$16.60 |
$23.00 |
$18.00 |
$7.95 |
$14.50 |
$10.00 |
$10.36 |
| 10 | 316-6249 |
AGGR(TY-PE GR-4 SAC-B) | 14 | CY |
$500.00 |
$206.00 |
$415.00 |
$800.00 |
$505.00 |
$290.73 |
$306.00 |
$390.00 |
$605.78 |
| 11 | 316-6400 |
ASPH (AC-15P OR AC-10-2TR OR CRS-2P) | 610 | GAL |
$8.00 |
$6.18 |
$12.50 |
$19.00 |
$12.00 |
$4.62 |
$9.50 |
$9.00 |
$6.65 |
| 12 | 400-6005 |
CEM STABIL BKFL | 37 | CY |
$150.00 |
$141.69 |
$150.00 |
$165.00 |
$100.00 |
$206.86 |
$220.00 |
$150.00 |
$106.39 |
| 13 | 416-6003 |
DRILL SHAFT (30 IN) | 270 | LF |
$225.00 |
$186.92 |
$176.00 |
$210.00 |
$264.00 |
$275.00 |
$150.00 |
$145.00 |
$179.09 |
| 14 | 420-6013 |
CL C CONC (ABUT) | 27.2 | CY |
$900.00 |
$753.75 |
$950.00 |
$1,000.00 |
$500.00 |
$986.24 |
$1,200.00 |
$860.00 |
$1,412.30 |
| 15 | 422-6005 |
REINF CONC SLAB (BOX BEAM) | 1,570 | SF |
$20.00 |
$19.52 |
$20.00 |
$19.00 |
$22.00 |
$22.96 |
$17.00 |
$19.00 |
$23.26 |
| 16 | 422-6023 |
SHEAR KEY | 8 | CY |
$400.00 |
$554.47 |
$795.00 |
$200.00 |
$249.00 |
$324.35 |
$450.00 |
$480.00 |
$248.22 |
| 17 | 425-6001 |
PRESTR CONC BOX BEAM (4B20) | 238 | LF |
$200.00 |
$180.45 |
$236.00 |
$195.00 |
$201.00 |
$203.84 |
$181.00 |
$190.00 |
$169.66 |
| 18 | 425-6002 |
PRESTR CONC BOX BEAM (5B20) | 119 | LF |
$200.00 |
$180.45 |
$236.00 |
$195.00 |
$205.00 |
$226.77 |
$184.00 |
$190.00 |
$169.66 |
| 19 | 432-6002 |
RIPRAP (CONC)(5 IN) | 6 | CY |
$450.00 |
$721.23 |
$829.00 |
$700.00 |
$315.00 |
$592.80 |
$500.00 |
$950.00 |
$439.85 |
| 20 | 432-6026 |
RIPRAP (STONE COMMON)(DRY)(18 IN) | 87 | CY |
$150.00 |
$181.44 |
$215.00 |
$185.00 |
$155.00 |
$195.32 |
$170.00 |
$220.00 |
$185.34 |
| 21 | 450-6018 |
RAIL (TY T631) | 152 | LF |
$85.00 |
$70.86 |
$74.70 |
$81.00 |
$113.00 |
$63.76 |
$90.00 |
$65.00 |
$55.70 |
| 22 | 454-6004 |
ARMOR JOINT (SEALED) | 44 | LF |
$80.00 |
$70.12 |
$121.00 |
$85.00 |
$66.00 |
$99.42 |
$85.00 |
$150.00 |
$109.36 |
| 23 | 496-6009 |
REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 | EA |
$25,000.00 |
$31,537.44 |
$20,000.00 |
$15,000.00 |
$20,000.00 |
$15,000.00 |
$27,000.00 |
$22,400.00 |
$66,430.00 |
| 24 | 500-6001 |
MOBILIZATION | 1 | LS |
$35,000.00 |
$32,000.00 |
$31,000.00 |
$37,989.86 |
$38,000.00 |
$33,000.00 |
$45,000.00 |
$64,000.00 |
$41,610.29 |
| 25 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 | MO |
$2,500.00 |
$1,119.18 |
$2,000.00 |
$3,500.00 |
$800.00 |
$2,000.00 |
$6,000.00 |
$3,500.00 |
$1,874.54 |
| 26 | 506-6001 |
ROCK FILTER DAMS (INSTALL) (TY 1) | 25 | LF |
$50.00 |
$55.62 |
$47.20 |
$50.00 |
$25.00 |
$75.31 |
$45.00 |
$49.50 |
$56.70 |
| 27 | 506-6011 |
ROCK FILTER DAMS (REMOVE) | 25 | LF |
$10.00 |
$15.45 |
$16.00 |
$15.00 |
$1.00 |
$25.50 |
$15.00 |
$17.00 |
$15.75 |
| 28 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 560 | LF |
$5.00 |
$3.09 |
$2.25 |
$3.00 |
$3.00 |
$3.57 |
$3.50 |
$2.40 |
$3.15 |
| 29 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 560 | LF |
$2.00 |
$1.55 |
$0.2700 |
$0.2500 |
$1.00 |
$0.4200 |
$1.50 |
$0.2700 |
$1.58 |
| 30 | 540-6001 |
MTL W-BEAM GD FEN (TIM POST) | 100 | LF |
$25.00 |
$20.09 |
$25.80 |
$24.20 |
$31.58 |
$37.74 |
$25.00 |
$25.00 |
$29.64 |
| 31 | 544-6001 |
GUARDRAIL END TREATMENT (INSTALL) | 4 | EA |
$2,500.00 |
$2,266.00 |
$2,480.00 |
$2,477.35 |
$2,943.00 |
$4,211.49 |
$2,450.00 |
$2,800.00 |
$2,667.00 |
| 32 | 552-6001 |
WIRE FENCE (TY A) | 152 | LF |
$15.00 |
$15.45 |
$16.00 |
$15.00 |
$30.00 |
$18.54 |
$15.00 |
$22.50 |
$18.90 |
| 33 | 658-6062 |
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 8 | EA |
$25.00 |
$25.75 |
$21.60 |
$20.25 |
$25.00 |
$53.98 |
$25.00 |
$17.00 |
$26.25 |
Showing the first 8 bidders. The Excel and CSV downloads include all 10.