| 1 | 100-6002 |
PREPARING ROW | 8.1 | STA |
$2,000.00 |
$3,000.00 |
$2,110.00 |
$3,500.00 |
$3,500.00 |
$2,000.00 |
$8,000.00 |
| 2 | 110-6001 |
EXCAVATION (ROADWAY) | 100 | CY |
$15.00 |
$10.00 |
$35.00 |
$42.00 |
$60.00 |
$30.00 |
$15.00 |
| 3 | 110-6002 |
EXCAVATION (CHANNEL) | 560 | CY |
$20.00 |
$10.00 |
$35.00 |
$42.00 |
$18.00 |
$30.00 |
$26.00 |
| 4 | 132-6005 |
EMBANKMENT (FINAL)(ORD COMP)(TY C) | 150 | CY |
$20.00 |
$35.00 |
$45.00 |
$42.00 |
$45.00 |
$35.00 |
$20.00 |
| 5 | 150-6002 |
BLADING | 40 | HR |
$100.00 |
$25.00 |
$75.00 |
$70.00 |
$115.00 |
$165.00 |
$95.00 |
| 6 | 164-6003 |
BROADCAST SEED (PERM) (RURAL) (CLAY) | 1,372 | SY |
$1.00 |
$0.5000 |
$3.00 |
$1.00 |
$1.70 |
$2.00 |
$1.00 |
| 7 | 164-6009 |
BROADCAST SEED (TEMP) (WARM) | 343 | SY |
$1.00 |
$1.00 |
$0.5000 |
$1.00 |
$1.65 |
$2.00 |
$1.00 |
| 8 | 164-6011 |
BROADCAST SEED (TEMP) (COOL) | 343 | SY |
$1.00 |
$1.00 |
$3.00 |
$1.00 |
$1.65 |
$2.00 |
$1.00 |
| 9 | 168-6001 |
VEGETATIVE WATERING | 15.4 | MG |
$60.00 |
$25.00 |
$25.00 |
$45.00 |
$70.00 |
$150.00 |
$60.00 |
| 10 | 247-6366 |
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 345 | CY |
$100.00 |
$130.00 |
$86.00 |
$140.00 |
$94.00 |
$150.00 |
$148.00 |
| 11 | 400-6005 |
CEM STABIL BKFL | 47 | CY |
$120.00 |
$100.00 |
$225.00 |
$270.00 |
$208.00 |
$200.00 |
$185.00 |
| 12 | 409-6001 |
PRESTR CONC PIL (16 IN SQ) | 1,253 | LF |
$110.00 |
$118.00 |
$110.00 |
$110.00 |
$102.00 |
$120.00 |
$110.00 |
| 13 | 420-6013 |
CL C CONC (ABUT) | 39.8 | CY |
$850.00 |
$700.00 |
$1,125.00 |
$1,200.00 |
$1,300.00 |
$1,100.00 |
$1,300.00 |
| 14 | 420-6029 |
CL C CONC (CAP) | 27 | CY |
$1,000.00 |
$677.00 |
$1,315.00 |
$1,700.00 |
$1,400.00 |
$325.00 |
$1,400.00 |
| 15 | 422-6007 |
REINF CONC SLAB (SLAB BEAM) | 4,030 | SF |
$17.00 |
$17.00 |
$19.25 |
$35.00 |
$22.40 |
$18.00 |
$28.00 |
| 16 | 425-6010 |
PRESTR CONC SLAB BEAM (5SB12) | 759.9 | LF |
$175.00 |
$181.00 |
$172.00 |
$160.00 |
$208.00 |
$199.00 |
$200.00 |
| 17 | 432-6002 |
RIPRAP (CONC)(5 IN) | 15 | CY |
$450.00 |
$300.00 |
$650.00 |
$700.00 |
$500.00 |
$650.00 |
$457.12 |
| 18 | 432-6031 |
RIPRAP (STONE PROTECTION)(12 IN) | 239 | CY |
$140.00 |
$140.00 |
$110.00 |
$170.00 |
$150.00 |
$180.00 |
$187.00 |
| 19 | 450-6006 |
RAIL (TY T223) | 358 | LF |
$100.00 |
$92.00 |
$110.00 |
$120.00 |
$117.00 |
$190.00 |
$116.00 |
| 20 | 454-6004 |
ARMOR JOINT (SEALED) | 90 | LF |
$75.00 |
$55.00 |
$95.00 |
$85.00 |
$95.00 |
$75.00 |
$75.00 |
| 21 | 496-6009 |
REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 | EA |
$25,000.00 |
$20,000.00 |
$18,000.00 |
$25,000.00 |
$15,000.00 |
$10,000.00 |
$22,000.00 |
| 22 | 500-6001 |
MOBILIZATION | 1 | LS |
$60,000.00 |
$75,000.00 |
$70,000.00 |
$85,929.50 |
$186,500.00 |
$150,000.00 |
$145,600.00 |
| 23 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 | MO |
$3,000.00 |
$800.00 |
$1,200.00 |
$600.00 |
$1,520.00 |
$8,000.00 |
$1,100.00 |
| 24 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 1,725 | LF |
$3.00 |
$2.00 |
$3.00 |
$2.50 |
$4.24 |
$3.00 |
$4.20 |
| 25 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 1,725 | LF |
$1.00 |
$1.00 |
$1.00 |
$1.00 |
$2.00 |
$1.00 |
$1.20 |
| 26 | 540-6001 |
MTL W-BEAM GD FEN (TIM POST) | 150 | LF |
$25.00 |
$31.00 |
$30.00 |
$32.00 |
$32.60 |
$22.00 |
$20.00 |
| 27 | 540-6006 |
MTL BEAM GD FEN TRANS (THRIE-BEAM) | 4 | EA |
$1,800.00 |
$1,507.00 |
$2,250.00 |
$2,200.00 |
$1,990.00 |
$2,000.00 |
$1,800.00 |
| 28 | 540-6007 |
MTL BEAM GD FEN TRANS (TL2) | 4 | EA |
$1,150.00 |
$973.00 |
$1,900.00 |
$1,000.00 |
$1,350.00 |
$1,400.00 |
$1,000.00 |
| 29 | 544-6001 |
GUARDRAIL END TREATMENT (INSTALL) | 8 | EA |
$2,800.00 |
$2,290.00 |
$2,750.00 |
$1,850.00 |
$2,988.00 |
$3,000.00 |
$2,800.00 |
| 30 | 644-6076 |
REMOVE SM RD SN SUP&AM | 5 | EA |
$75.00 |
$50.00 |
$200.00 |
$50.00 |
$100.00 |
$120.00 |
$75.00 |
| 31 | 658-6014 |
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI) | 16 | EA |
$15.00 |
$5.00 |
$45.00 |
$17.00 |
$22.00 |
$30.00 |
$15.00 |
| 32 | 658-6062 |
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 16 | EA |
$20.00 |
$11.00 |
$45.00 |
$21.00 |
$38.00 |
$30.00 |
$25.00 |