CONSTRUCT SIDEWALKS AND CURB RAMPS
- Let date
- Tuesday, December 5, 2017
- CCSJ
- 0910-16-143
- District
- Tyler
- County
- Smith
- Highway
- VA
- Limits
- ON SH110,FRM HAGAN,.7 MI S OF FM346 to 0.1 MI S OF LEAMINGTON SPA IN WHTHS
- Classification
- Construction
- Project number
- STP 2018(481)
- Working days
- 48
Bidders 14
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $133,671 | | |
| 1 |
ENCINO LANDSCAPE, INC. Low bidder |
$126,560 |
-5.3% |
|
| 2 |
HARTBEAT CONSTRUCTION |
$128,378 |
-4.0% |
+1.4% |
| 3 |
B & E CONSTRUCTION INC |
$139,332 |
+4.2% |
+10.1% |
| 4 |
CROSS PLUS CONSTRUCTION, LLC |
$144,808 |
+8.3% |
+14.4% |
| 5 |
J.R. POPE COMPANY, INC. |
$160,990 |
+20.4% |
+27.2% |
| 6 |
HIGHWAY 19 CONSTRUCTION LLC |
$166,500 |
+24.6% |
+31.6% |
| 7 |
SOUTH TEXAS ILLUMINATION, LLC |
$175,037 |
+30.9% |
+38.3% |
| 8 |
TI-ZACK CONCRETE, INC. |
$175,130 |
+31.0% |
+38.4% |
| 9 |
L. S. EQUIPMENT CO., INC. |
$179,500 |
+34.3% |
+41.8% |
| 10 |
STATELINE CONSTRUCTION, LLC |
$186,428 |
+39.5% |
+47.3% |
| 11 |
OPPORTUNITY EXCAVATION/CONCRETE, LLC |
$189,590 |
+41.8% |
+49.8% |
| 12 |
FNH CONSTRUCTION, LLC |
$210,658 |
+57.6% |
+66.4% |
| 13 |
LONGVIEW BRIDGE AND ROAD, LTD. |
$243,260 |
+82.0% |
+92.2% |
| 14 |
EAST TEXAS BRIDGE, INC. |
$274,510 |
+105.4% |
+116.9% |
Bid tab: unit prices 18 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 ENCINO LANDSCAP… | #2 HARTBEAT CONSTR… | #3 B & E CONSTRUCT… | #4 CROSS PLUS CONS… | #5 J.R. POPE COMPA… | #6 HIGHWAY 19 CONS… | #7 SOUTH TEXAS ILL… | #8 TI-ZACK CONCRET… |
| 1 | 104-6017 |
REMOVING CONC (DRIVEWAYS) | 114 | SY |
$14.00 |
$10.00 |
$27.00 |
$15.00 |
$34.00 |
$20.00 |
$25.00 |
$12.00 |
$25.00 |
| 2 | 132-6019 |
EMBANKMENT (VEHICLE)(ORD COMP)(TY B) | 24 | CY |
$40.00 |
$50.00 |
$30.00 |
$40.00 |
$45.00 |
$25.00 |
$100.00 |
$60.00 |
$45.00 |
| 3 | 162-6002 |
BLOCK SODDING | 120 | SY |
$6.00 |
$10.00 |
$10.00 |
$4.00 |
$5.00 |
$6.00 |
$5.00 |
$4.50 |
$5.00 |
| 4 | 450-6048 |
RAIL (HANDRAIL)(TY B) | 90 | LF |
$84.50 |
$100.00 |
$72.00 |
$65.00 |
$190.00 |
$75.00 |
$110.00 |
$75.00 |
$125.00 |
| 5 | 462-6006 |
CONC BOX CULV (5 FT X 2 FT) | 6 | LF |
$350.00 |
$500.00 |
$775.00 |
$200.00 |
$789.00 |
$400.00 |
$500.00 |
$300.00 |
$1,000.00 |
| 6 | 466-6178 |
WINGWALL (PW - 1) (HW=3 FT) | 4 | EA |
$3,000.00 |
$2,000.00 |
$850.00 |
$6,850.00 |
$4,500.00 |
$2,000.00 |
$5,000.00 |
$8,300.00 |
$6,000.00 |
| 7 | 500-6001 |
MOBILIZATION | 1 | LS |
$12,000.00 |
$14,000.00 |
$15,000.00 |
$12,666.50 |
$23,000.00 |
$20,000.00 |
$20,000.00 |
$14,500.00 |
$25,000.00 |
| 8 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 | MO |
$7,500.00 |
$2,500.00 |
$4,500.00 |
$4,000.00 |
$1,200.00 |
$1,750.00 |
$1,500.00 |
$1,800.00 |
$1,500.00 |
| 9 | 506-6029 |
EARTHWORK (EROSN & SEDMT CONT, IN VEH) | 20 | CY |
$30.00 |
$10.00 |
$30.00 |
$5.00 |
$23.00 |
$1.00 |
$100.00 |
$36.00 |
$25.00 |
| 10 | 506-6030 |
BACKHOE WORK (EROSION & SEDMT CONT) | 20 | HR |
$154.00 |
$1.00 |
$90.00 |
$45.00 |
$23.00 |
$75.00 |
$50.00 |
$21.50 |
$25.00 |
| 11 | 506-6041 |
BIODEG EROSN CONT LOGS (INSTL) (12") | 100 | LF |
$5.00 |
$10.00 |
$3.00 |
$2.50 |
$8.00 |
$15.00 |
$6.00 |
$4.20 |
$1.00 |
| 12 | 506-6043 |
BIODEG EROSN CONT LOGS (REMOVE) | 100 | LF |
$2.00 |
$1.00 |
$3.00 |
$0.5000 |
$1.00 |
$5.00 |
$2.00 |
$0.5000 |
$1.00 |
| 13 | 530-6017 |
DRIVEWAYS (CONC) (HES) | 114 | SY |
$95.00 |
$80.00 |
$72.00 |
$90.00 |
$54.00 |
$90.00 |
$100.00 |
$74.00 |
$105.00 |
| 14 | 531-6001 |
CONC SIDEWALKS (4") | 634 | SY |
$70.00 |
$70.00 |
$63.00 |
$45.00 |
$45.00 |
$65.00 |
$75.00 |
$49.50 |
$100.00 |
| 15 | 531-6010 |
CURB RAMPS (TY 7) | 3 | EA |
$2,000.00 |
$1,500.00 |
$3,600.00 |
$1,575.00 |
$2,300.00 |
$1,500.00 |
$1,100.00 |
$1,750.00 |
$1,500.00 |
| 16 | 531-6032 |
CONC SIDEWALKS (SPECIAL) (TYPE A) | 36 | SY |
$100.00 |
$200.00 |
$225.00 |
$600.00 |
$67.00 |
$1,125.00 |
$200.00 |
$1,350.00 |
$105.00 |
| 17 | 1002-6002 |
LANDSCAPE AMENITY (TY 1) | 1 | EA |
$4,000.00 |
$5,000.00 |
$8,500.00 |
$9,850.00 |
$12,000.00 |
$7,500.00 |
$15,000.00 |
$2,750.00 |
$10,000.00 |
| 18 | 1002-6003 |
LANDSCAPE AMENITY (TY 2) | 1 | EA |
$1,000.00 |
$10,000.00 |
$1,800.00 |
$800.00 |
$15,000.00 |
$7,500.00 |
$15,000.00 |
$12,000.00 |
$5,000.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 14.