RES | Pot Hole Repair along IH35
- Let date
- Friday, September 5, 2025
- CCSJ
- 0909-00-105
- District
- Waco
- County
- McLennan
- Highway
- Various
- Limits
- Various locations IH 35 @ Sun Valley Blv to Various locations IH 35 SL363
- Classification
- Restoration · Construction
- Project number
- F 2B25(168)
- Working days
- 135
- DBE goal
- 0%
Bidders 9
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $3,712,218 | | |
| 1 |
O. TREVINO CONSTRUCTION, LLC Low bidder |
$2,806,854 |
-24.4% |
|
| 2 |
SILVER CREEK CONSTRUCTION, INC. |
$2,839,861 |
-23.5% |
+1.2% |
| 3 |
WINDING ROAD CONSTRUCTION, INC. |
$2,988,803 |
-19.5% |
+6.5% |
| 4 |
EMERY SAPP & SON'S INC. |
$3,034,338 |
-18.3% |
+8.1% |
| 5 |
STRUCTURAL INTEGRITY GROUP LLC |
$3,049,692 |
-17.8% |
+8.7% |
| 6 |
ROY JORGENSEN ASSOCIATES, INC. |
$3,069,051 |
-17.3% |
+9.3% |
| 7 |
CROSS PLUS CONSTRUCTION, LLC |
$3,086,477 |
-16.9% |
+10.0% |
| 8 |
GARRET SHIELDS INFRASTRUCTURE |
$3,462,634 |
-6.7% |
+23.4% |
| 9 |
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC |
$5,471,161 |
+47.4% |
+94.9% |
Bid tab: unit prices 10 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 O. TREVINO CONS… | #2 SILVER CREEK CO… | #3 WINDING ROAD CO… | #4 EMERY SAPP & SO… | #5 STRUCTURAL INTE… | #6 ROY JORGENSEN A… | #7 CROSS PLUS CONS… | #8 GARRET SHIELDS … |
| 1 | 361-7008 |
FULL - DEPTH REPAIR CRCP (13") | 778 | CY |
$1,300.00 |
$1,120.00 |
$1,263.00 |
$1,200.00 |
$1,125.00 |
$1,310.00 |
$1,050.00 |
$700.00 |
$1,200.00 |
| 2 | 361-7009 |
FULL - DEPTH REPAIR CRCP (14") | 213 | CY |
$1,400.00 |
$1,150.00 |
$1,268.00 |
$1,800.00 |
$1,278.00 |
$1,339.00 |
$1,400.00 |
$1,200.00 |
$1,300.00 |
| 3 | 361-7010 |
FULL - DEPTH REPAIR CRCP (15") | 18 | CY |
$1,200.00 |
$3,500.00 |
$1,690.00 |
$2,500.00 |
$2,536.00 |
$1,359.00 |
$1,375.00 |
$1,200.00 |
$1,500.00 |
| 4 | 500-7001 |
MOBILIZATION | 1 | LS |
$140,500.00 |
$275,000.00 |
$280,000.00 |
$230,000.00 |
$179,500.00 |
$205,000.00 |
$300,000.00 |
$250,000.00 |
$250,000.00 |
| 5 | 502-7001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 | MO |
$25,000.00 |
$18,275.00 |
$8,500.00 |
$9,500.00 |
$4,520.00 |
$41,500.00 |
$12,500.00 |
$15,000.00 |
$5,000.00 |
| 6 | 503-7001 |
PORTABLE CHANGEABLE MESSAGE SIGN | 135 | DAY |
$90.00 |
$250.00 |
$110.00 |
$750.00 |
$102.00 |
$200.00 |
$25.00 |
$200.00 |
$100.00 |
| 7 | 505-7001 |
TMA (STATIONARY) | 270 | DAY |
$200.00 |
$200.00 |
$300.00 |
$350.00 |
$225.00 |
$125.00 |
$500.00 |
$910.00 |
$400.00 |
| 8 | 720-7003 |
SPALLING REPAIR (POLYMERIC) (SEMIRIGID) | 5,604 | GAL |
$132.00 |
$50.00 |
$58.00 |
$74.00 |
$131.50 |
$89.00 |
$75.00 |
$125.00 |
$100.00 |
| 9 | 721-7001 |
FIBER REINFORCED POLYMER PATCHING MATLS | 202,805 | LB |
$5.50 |
$3.92 |
$3.75 |
$3.27 |
$3.80 |
$2.75 |
$4.60 |
$4.16 |
$6.00 |
| 10 | 721-7002 |
BULKING AGGREGATE | 62,808 | LB |
$1.50 |
$0.4000 |
$0.3000 |
$0.6000 |
$0.6200 |
$0.4000 |
$0.4000 |
$1.00 |
$0.5000 |
Showing the first 8 bidders. The Excel and CSV downloads include all 9.