‹ May 2026 results
Rehab Historic Bridge Craft Rd
- Let date
- Wednesday, May 6, 2026
- CCSJ
- 0901-19-212
- District
- Paris
- County
- Grayson
- Highway
- CRAFT RD
- Limits
- Craft Rd to At Choctaw Creek Tributary
- Classification
- Bridge Replacement · Construction
- Project number
- BR 2023(646)
- Working days
- 99
- DBE goal
- 0%
Bidders 10
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $924,208 | | |
| 1 |
HODGES AND SON CONSTRUCTION COMPANY, INC. Low bidder |
$802,935 |
-13.1% |
|
| 2 |
C & W SOUTHERN LLC |
$858,061 |
-7.2% |
+6.9% |
| 3 |
THK CONSTRUCTION LLC |
$909,807 |
-1.6% |
+13.3% |
| 4 |
HIGHWAY 19 CONSTRUCTION LLC |
$931,366 |
+0.8% |
+16.0% |
| 5 |
TEXAS STEEL INDUSTRIAL PLACING, LLC |
$938,592 |
+1.6% |
+16.9% |
| 6 |
SKYLINE BRIDGE LLC |
$979,968 |
+6.0% |
+22.0% |
| 7 |
EAST TEXAS BRIDGE, INC. |
$1,197,747 |
+29.6% |
+49.2% |
| 8 |
GARRET SHIELDS INFRASTRUCTURE |
$1,280,604 |
+38.6% |
+59.5% |
| 9 |
RB CONTRACTING, LLC |
$1,350,348 |
+46.1% |
+68.2% |
| 10 |
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC |
$1,399,257 |
+51.4% |
+74.3% |
Bid tab: unit prices 36 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 HODGES AND SON … | #2 C & W SOUTHERN … | #3 THK CONSTRUCTIO… | #4 HIGHWAY 19 CONS… | #5 TEXAS STEEL IND… | #6 SKYLINE BRIDGE … | #7 EAST TEXAS BRID… | #8 GARRET SHIELDS … |
| 1 | 100-7002 |
PREPARING ROW | 4.2 | STA |
$2,500.00 |
$2,400.00 |
$1,200.00 |
$1,500.00 |
$2,500.00 |
$1,000.00 |
$1,100.00 |
$10,000.00 |
$1,000.00 |
| 2 | 110-7001 |
EXCAV (ROADWAY) | 196 | CY |
$20.00 |
$12.00 |
$10.00 |
$15.00 |
$25.00 |
$15.00 |
$16.00 |
$20.00 |
$30.00 |
| 3 | 110-7002 |
EXCAV (CHANNEL) | 1,446 | CY |
$25.00 |
$10.00 |
$8.00 |
$10.00 |
$20.00 |
$12.00 |
$14.00 |
$20.00 |
$30.00 |
| 4 | 132-7003 |
EMBANK (FNL)(OC)(TY B) | 74 | CY |
$20.00 |
$30.00 |
$10.00 |
$15.00 |
$50.00 |
$20.00 |
$45.00 |
$35.00 |
$40.00 |
| 5 | 164-7005 |
BROADCAST SEED (TEMP_WARM) | 437 | SY |
$1.00 |
$3.70 |
$0.0100 |
$2.10 |
$1.00 |
$1.15 |
$2.15 |
$2.20 |
$2.00 |
| 6 | 164-7006 |
BROADCAST SEED (TEMP_COOL) | 437 | SY |
$1.00 |
$3.70 |
$0.0100 |
$2.10 |
$1.00 |
$1.20 |
$2.15 |
$2.20 |
$2.00 |
| 7 | 164-7018 |
HYDRO MULCH SEED (PERM_RURAL_CLAY) | 874 | SY |
$2.00 |
$3.10 |
$3.50 |
$2.10 |
$5.00 |
$2.00 |
$2.15 |
$2.50 |
$2.00 |
| 8 | 168-7001 |
VEGETATIVE WATERING | 11 | TGL |
$30.00 |
$1.00 |
$55.00 |
$10.00 |
$10.00 |
$1.00 |
$1.00 |
$40.00 |
$20.00 |
| 9 | 251-7025 |
REWORK BS MTL (TY B)(6")(ORD COMP) | 759 | SY |
$6.00 |
$30.00 |
$35.00 |
$25.00 |
$5.00 |
$6.00 |
$10.00 |
$20.00 |
$20.00 |
| 10 | 305-7002 |
SALV, HAUL & STKPL RCL APH PV (0 TO 2") | 641 | SY |
$4.20 |
$12.00 |
$10.00 |
$10.00 |
$10.00 |
$8.00 |
$13.00 |
$15.00 |
$40.00 |
| 11 | 344-7009 |
SP MIXES SP-C PG64-22 | 126 | TON |
$190.00 |
$310.00 |
$324.00 |
$275.00 |
$308.50 |
$220.00 |
$330.00 |
$335.00 |
$200.00 |
| 12 | 400-7010 |
CEM STABIL BKFL | 31 | CY |
$200.00 |
$250.00 |
$300.00 |
$300.00 |
$350.00 |
$220.00 |
$250.00 |
$275.00 |
$250.00 |
| 13 | 416-7004 |
DRILL SHAFT (24 IN) | 615 | LF |
$200.00 |
$100.00 |
$115.00 |
$155.12 |
$180.00 |
$240.00 |
$195.00 |
$175.00 |
$300.00 |
| 14 | 420-7012 |
CL C CONC (ABUT) | 20.4 | CY |
$1,200.00 |
$1,200.00 |
$1,100.00 |
$950.00 |
$1,400.00 |
$1,100.00 |
$1,250.00 |
$1,500.00 |
$1,200.00 |
| 15 | 420-7022 |
CL C CONC (CAP) | 13.2 | CY |
$1,312.35 |
$1,500.00 |
$1,750.00 |
$1,400.00 |
$1,500.00 |
$1,500.00 |
$1,800.00 |
$1,500.00 |
$1,200.00 |
| 16 | 420-7038 |
CL C CONC (COLUMN) | 6.3 | CY |
$1,335.85 |
$1,600.00 |
$2,250.00 |
$1,500.00 |
$1,500.00 |
$1,500.00 |
$2,000.00 |
$1,500.00 |
$1,200.00 |
| 17 | 422-7007 |
REINF CONC SLAB (SLAB BEAM) | 3,120 | SF |
$22.70 |
$20.00 |
$25.00 |
$20.00 |
$19.00 |
$20.00 |
$22.00 |
$28.00 |
$30.00 |
| 18 | 425-7019 |
PRESTR CONC SLAB BEAM (5SB15) | 592.5 | LF |
$226.50 |
$290.00 |
$275.00 |
$311.33 |
$333.00 |
$223.25 |
$300.00 |
$315.00 |
$300.00 |
| 19 | 432-7043 |
RIPRAP (STONE PROTECTION)(18 IN) | 960 | CY |
$200.00 |
$175.00 |
$165.00 |
$150.00 |
$180.00 |
$145.00 |
$150.00 |
$205.00 |
$250.00 |
| 20 | 450-7021 |
RAIL (TY T631LS) | 264 | LF |
$75.00 |
$65.00 |
$55.00 |
$67.20 |
$59.97 |
$59.97 |
$69.00 |
$60.00 |
$250.00 |
| 21 | 454-7004 |
SEALED EXPANSION JOINT (4 IN) (SEJ - M) | 52 | LF |
$200.00 |
$210.00 |
$160.00 |
$200.00 |
$210.00 |
$200.00 |
$255.00 |
$275.00 |
$300.00 |
| 22 | 464-7009 |
RC PIPE (CL III)(36 IN) | 60 | LF |
$160.00 |
$90.00 |
$89.00 |
$115.35 |
$150.00 |
$165.00 |
$155.00 |
$175.00 |
$250.00 |
| 23 | 467-7365 |
SET (TY II) (36 IN) (RCP) (3: 1) (C) | 2 | EA |
$4,900.00 |
$3,000.00 |
$2,080.00 |
$2,563.00 |
$3,500.00 |
$3,500.00 |
$4,200.00 |
$3,500.00 |
$5,000.00 |
| 24 | 500-7001 |
MOBILIZATION | 1 | LS |
$43,566.60 |
$68,000.00 |
$70,000.00 |
$75,000.00 |
$100,000.00 |
$93,774.76 |
$75,000.00 |
$110,000.00 |
$150,000.00 |
| 25 | 502-7001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 | MO |
$7,500.00 |
$1,600.00 |
$900.00 |
$1,010.46 |
$2,000.00 |
$1,000.00 |
$1,745.50 |
$3,000.00 |
$5,000.00 |
| 26 | 506-7002 |
ROCK FILTER DAMS (INSTALL) (TY 2) | 52 | LF |
$35.00 |
$1.00 |
$10.00 |
$105.00 |
$55.00 |
$40.00 |
$45.00 |
$110.00 |
$20.00 |
| 27 | 506-7011 |
ROCK FILTER DAMS (REMOVE) | 52 | LF |
$10.00 |
$1.00 |
$1.00 |
$46.20 |
$10.00 |
$10.00 |
$10.00 |
$40.00 |
$10.00 |
| 28 | 506-7020 |
CONSTRUCTION EXITS (INSTALL) (TY 1) | 156 | SY |
$25.00 |
$1.00 |
$1.00 |
$47.25 |
$1.00 |
$40.00 |
$10.00 |
$45.00 |
$40.00 |
| 29 | 506-7024 |
CONSTRUCTION EXITS (REMOVE) | 156 | SY |
$6.00 |
$1.00 |
$1.00 |
$12.60 |
$1.00 |
$10.00 |
$1.00 |
$10.00 |
$10.00 |
| 30 | 506-7039 |
TEMP SEDMT CONT FENCE (INSTALL) | 578 | LF |
$2.50 |
$1.00 |
$3.00 |
$5.25 |
$4.00 |
$4.00 |
$4.00 |
$5.50 |
$5.00 |
| 31 | 506-7041 |
TEMP SEDMT CONT FENCE (REMOVE) | 578 | LF |
$1.00 |
$1.00 |
$1.00 |
$2.10 |
$1.00 |
$1.00 |
$1.50 |
$1.00 |
$1.00 |
| 32 | 540-7002 |
MTL W-BEAM GD FEN (STEEL POST) | 100 | LF |
$35.00 |
$32.00 |
$31.00 |
$32.03 |
$29.69 |
$28.00 |
$32.50 |
$34.50 |
$40.00 |
| 33 | 544-7001 |
GUARDRAIL END TREATMENT (INSTALL) | 4 | EA |
$3,100.00 |
$3,300.00 |
$3,200.00 |
$3,386.25 |
$3,355.00 |
$3,000.00 |
$3,415.00 |
$3,550.00 |
$3,500.00 |
| 34 | 658-7002 |
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GF2(BI) | 18 | EA |
$45.00 |
$20.00 |
$26.00 |
$21.00 |
$25.00 |
$25.00 |
$21.20 |
$30.00 |
$30.00 |
| 35 | 4005-7001 |
RELOCATE EXISTING TRUSS BRIDGE | 1 | LS |
$60,000.00 |
$35,000.00 |
$80,000.00 |
$97,000.00 |
$25,000.00 |
$140,500.00 |
$125,000.00 |
$150,000.00 |
$50,000.00 |
| 36 | 5011-7002 |
REMOVE LEAD-CONTAINING COATING (OTHER) | 1 | LS |
$30,000.00 |
$500.00 |
$14,000.00 |
$20,475.00 |
$15,000.00 |
$19,500.00 |
$21,000.00 |
$35,000.00 |
$30,000.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 10.