MILLED EDGELINE RUMBLE STRIPS
- Let date
- Tuesday, March 6, 2018
- CCSJ
- 0703-02-059
- District
- Beaumont
- County
- Hardin
- Highway
- FM 92
- Limits
- TYLER C/L to FM 418
- Classification
- · Construction
- Project number
- STP 2018(655)HESG
- Working days
- 12
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $58,010 | ||
| 1 | STRIPE-A-ZONE, INC. Low bidder | $61,300 | +5.7% | |
| 2 | CRABTREE BARRICADE SYSTEMS, INC. | $65,862 | +13.5% | +7.4% |
| 3 | INTERSTATE BARRICADES & MARKINGS, INC. | $71,390 | +23.1% | +16.5% |
| 4 | THOMAS 11 DEVELOPMENT LLC | $81,673 | +40.8% | +33.2% |
| 5 | TRP CONSTRUCTION GROUP, LLC | $110,109 | +89.8% | +79.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 STRIPE-A-ZONE, … | #2 CRABTREE BARRIC… | #3 INTERSTATE BARR… | #4 THOMAS 11 DEVEL… | #5 TRP CONSTRUCTIO… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6001 | MOBILIZATION | 1 | LS | $5,000.00 | $5,000.00 | $10,000.00 | $6,000.00 | $12,700.00 | $10,000.00 |
| 2 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 | MO | $5,000.00 | $255.00 | $2,500.00 | $250.00 | $2,500.00 | $1,000.00 |
| 3 | 533-6001 | RUMBLE STRIPS (SHOULDER) | 105,276 | LF | $0.1400 | $0.1850 | $0.1300 | $0.2000 | $0.1000 | $0.2000 |
| 4 | 533-6002 | RUMBLE STRIPS (CENTERLINE) | 40,102 | LF | $0.1500 | $0.1900 | $0.1500 | $0.2400 | $0.1200 | $0.3500 |
| 5 | 666-6311 | RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL) | 27,309 | LF | $0.2900 | $0.3500 | $0.3700 | $0.2500 | $0.4400 | $0.6500 |
| 6 | 666-6314 | RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) | 28,893 | LF | $0.3000 | $0.3500 | $0.3500 | $0.2500 | $0.4400 | $0.5500 |
| 7 | 672-6009 | REFL PAV MRKR TY II-A-A | 1,056 | EA | $3.55 | $4.00 | $4.00 | $10.00 | $5.00 | $6.00 |
| 8 | 6185-6003 | TMA (MOBILE OPERATION) | 192 | HR | $10.00 | $25.00 | $35.00 | $50.00 | $97.00 | $120.00 |