‹ Jan 2022 results
SAFETY LIGHTING
- Let date
- Friday, January 7, 2022
- CCSJ
- 0258-08-037
- District
- Waco
- County
- McLennan
- Highway
- SH 6
- Limits
- .5 MI N OF SP 412 to SP 412
- Classification
- Construction
- Project number
- STP 2022(264)HES
- Working days
- 60
Bidders 11
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $881,233 | | |
| 1 |
SOUTH TEXAS ILLUMINATION, LLC Low bidder |
$770,035 |
-12.6% |
|
| 2 |
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. |
$814,792 |
-7.5% |
+5.8% |
| 3 |
THIRD COAST SERVICES LLC |
$875,824 |
-0.6% |
+13.7% |
| 4 |
FLORIDA TRAFFIC CONTROL DEVICES, INC. |
$984,806 |
+11.8% |
+27.9% |
| 5 |
VACA UNDERGROUND UTILITIES INC |
$1,030,854 |
+17.0% |
+33.9% |
| 6 |
WG ENGINEERING & CONSTRUCTION, LLC |
$1,046,610 |
+18.8% |
+35.9% |
| 7 |
MICA CORPORATION |
$1,056,776 |
+19.9% |
+37.2% |
| 8 |
CROSS PLUS CONSTRUCTION, LLC |
$1,060,003 |
+20.3% |
+37.7% |
| 9 |
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. |
$1,077,000 |
+22.2% |
+39.9% |
| 10 |
F & W ELECTRICAL CONTRACTORS, INC. |
$1,080,316 |
+22.6% |
+40.3% |
| 11 |
ALLSTATE SIGNAL & CONSTRUCTION, LLC |
$1,214,523 |
+37.8% |
+57.7% |
Bid tab: unit prices 14 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 SOUTH TEXAS ILL… | #2 HIGHWAY INTELLI… | #3 THIRD COAST SER… | #4 FLORIDA TRAFFIC… | #5 VACA UNDERGROUN… | #6 WG ENGINEERING … | #7 MICA CORPORATION | #8 CROSS PLUS CONS… |
| 1 | 416-6029 |
DRILL SHAFT (RDWY ILL POLE) (30 IN) | 670 | LF |
$224.00 |
$164.84 |
$187.13 |
$173.00 |
$174.34 |
$160.00 |
$255.00 |
$200.65 |
$289.00 |
| 2 | 432-6009 |
RIPRAP (CONC) (CL B) (4") | 6 | CY |
$360.00 |
$422.33 |
$936.25 |
$798.00 |
$460.15 |
$300.00 |
$375.00 |
$1,952.00 |
$1,200.00 |
| 3 | 500-6001 |
MOBILIZATION | 1 | LS |
$43,000.00 |
$49,508.00 |
$54,293.49 |
$87,000.00 |
$65,138.31 |
$100,000.00 |
$48,850.00 |
$70,220.00 |
$65,000.00 |
| 4 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 | MO |
$5,150.00 |
$6,230.50 |
$2,749.75 |
$1,122.00 |
$666.62 |
$6,000.00 |
$3,985.00 |
$14,540.00 |
$4,500.00 |
| 5 | 610-6214 |
IN RD IL (TY SA) 40T-8 (250W EQ) LED | 63 | EA |
$3,200.00 |
$3,679.00 |
$3,358.25 |
$3,200.00 |
$4,319.48 |
$3,500.00 |
$3,215.00 |
$3,338.00 |
$4,700.00 |
| 6 | 610-6215 |
IN RD IL (TY SA) 40T-8-8 (250W EQ) LED | 2 | EA |
$4,100.00 |
$4,401.20 |
$4,168.20 |
$4,068.00 |
$5,536.00 |
$4,200.00 |
$3,868.00 |
$4,405.00 |
$5,500.00 |
| 7 | 618-6023 |
CONDT (PVC) (SCH 40) (2") | 17,392 | LF |
$8.70 |
$6.18 |
$7.58 |
$7.88 |
$12.11 |
$11.00 |
$13.00 |
$11.77 |
$7.25 |
| 8 | 618-6047 |
CONDT (PVC) (SCH 80) (2") (BORE) | 5,258 | LF |
$17.00 |
$9.36 |
$15.64 |
$18.51 |
$20.13 |
$25.00 |
$24.00 |
$23.40 |
$30.00 |
| 9 | 620-6007 |
ELEC CONDR (NO.8) BARE | 22,650 | LF |
$1.29 |
$1.18 |
$1.06 |
$1.25 |
$1.13 |
$1.80 |
$1.85 |
$1.42 |
$1.07 |
| 10 | 620-6008 |
ELEC CONDR (NO.8) INSULATED | 60,372 | LF |
$1.50 |
$1.18 |
$1.13 |
$1.60 |
$1.31 |
$1.90 |
$1.85 |
$1.51 |
$1.09 |
| 11 | 624-6002 |
GROUND BOX TY A (122311)W/APRON | 44 | EA |
$950.00 |
$845.30 |
$731.00 |
$870.77 |
$834.44 |
$1,000.00 |
$825.00 |
$1,383.00 |
$675.00 |
| 12 | 628-6002 |
REMOVE ELECTRICAL SERVICES | 1 | EA |
$760.00 |
$528.00 |
$1,050.00 |
$362.00 |
$250.02 |
$365.00 |
$550.00 |
$395.00 |
$100.00 |
| 13 | 628-6045 |
ELC SRV TY A 240/480 060(NS)SS(E)SP(O) | 6 | EA |
$6,600.00 |
$4,501.40 |
$6,973.10 |
$5,684.00 |
$6,245.37 |
$5,825.00 |
$5,685.00 |
$7,266.00 |
$5,900.00 |
| 14 | 6185-6002 |
TMA (STATIONARY) | 120 | DAY |
$108.00 |
$188.80 |
$143.75 |
$182.00 |
$155.44 |
$95.00 |
$180.00 |
$60.30 |
$250.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 11.