LED FLASHING CHEVRONS ON CURVES
- Let date
- Wednesday, July 8, 2020
- CCSJ
- 0235-02-047
- District
- San Angelo
- County
- Edwards
- Highway
- SH 55
- Limits
- 9 MILES SOUTH OF US 377 to REAL COUNTY LINE
- Classification
- Construction
- Project number
- STP 2020(948)
- Working days
- 23
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $299,860 | ||
| 1 | L. UNITED BUILDING COMPANY Low bidder | $116,358 | -61.2% | |
| 2 | SYNERGY SIGNS & SERVICES LLC | $164,050 | -45.3% | +41.0% |
| 3 | BATTERSON, LLP | $240,250 | -19.9% | +106.5% |
| 4 | FLASHER EQUIPMENT COMPANY | $247,898 | -17.3% | +113.0% |
| 5 | STRIPE-A-ZONE, INC. | $289,760 | -3.4% | +149.0% |
| 6 | HJC FARMS, INC. | $295,100 | -1.6% | +153.6% |
| 7 | FNH CONSTRUCTION, LLC | $341,350 | +13.8% | +193.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 L. UNITED BUILD… | #2 SYNERGY SIGNS &… | #3 BATTERSON, LLP | #4 FLASHER EQUIPME… | #5 STRIPE-A-ZONE, … | #6 HJC FARMS, INC. | #7 FNH CONSTRUCTIO… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6001 | MOBILIZATION | 1 | LS | $23,000.00 | $25,000.00 | $15,000.00 | $50,000.00 | $18,000.00 | $28,500.00 | $50,000.00 | |
| 2 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 | MO | $6,000.00 | $1,000.00 | $2,000.00 | $3,500.00 | $2,500.00 | $10,000.00 | $3,000.00 | |
| 3 | 644-6001 | IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 28 | EA | $500.00 | $350.00 | $500.00 | $800.00 | $788.00 | $745.00 | $600.00 | |
| 4 | 644-6076 | REMOVE SM RD SN SUP&AM | 15 | EA | $100.00 | $50.00 | $150.00 | $110.00 | $78.00 | $240.00 | $100.00 | |
| 5 | 6185-6002 | TMA (STATIONARY) | 16 | DAY | $285.00 | $50.00 | $150.00 | $550.00 | $170.00 | $325.00 | $300.00 | |
| 6 | 6350-6001 | LEAD LED CHEVRON | 48 | EA | $4,000.00 | $1,150.00 | $1,800.00 | $2,800.00 | $3,748.00 | $3,450.00 | $4,000.00 | |
| 7 | 6350-6002 | LED CHEVRON | 8 | EA | $6,600.00 | $2,851.00 | $5,000.00 | $2,000.00 | $2,380.00 | $5,750.00 | $3,000.00 |