BRIDGE REPAIR
- Let date
- Wednesday, October 4, 2017
- CCSJ
- 0117-06-049
- District
- Lufkin
- County
- Houston
- Highway
- SH 21
- Limits
- AT TRINITY RIVER to , ETC
- Classification
- Construction
- Project number
- BR 2018(030)
- Working days
- 76
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,080,343 | ||
| 1 | HODGES AND SON CONSTRUCTION COMPANY, INC. Low bidder | $1,384,827 | +28.2% | |
| 2 | EARTH BUILDERS, L.P. | $1,963,671 | +81.8% | +41.8% |
| 3 | JAY-REESE CONTRACTORS, INC. | $2,241,822 | +107.5% | +61.9% |
| 4 | IOWA BRIDGE & CULVERT, LC | $2,693,502 | +149.3% | +94.5% |
| 5 | DCI CONTRACTING, INC. | $2,715,529 | +151.4% | +96.1% |
| 6 | PIERCE R & B LLC | $2,765,447 | +156.0% | +99.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 HODGES AND SON … | #2 EARTH BUILDERS,… | #3 JAY-REESE CONTR… | #4 IOWA BRIDGE & C… | #5 DCI CONTRACTING… | #6 PIERCE R & B LLC |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 164-6021 | CELL FBR MLCH SEED(PERM)(RURAL)(SANDY) | 6,551 | SY | $0.3500 | $1.00 | $1.00 | $0.5000 | $2.00 | $0.5800 | $0.5200 |
| 2 | 168-6001 | VEGETATIVE WATERING | 131 | MG | $20.00 | $1.00 | $20.00 | $60.00 | $300.00 | $61.96 | $60.00 |
| 3 | 403-6001 | TEMPORARY SPL SHORING | 3,300 | SF | $20.00 | $15.00 | $20.00 | $23.00 | $1.00 | $37.63 | $45.00 |
| 4 | 416-6006 | DRILL SHAFT (48 IN) | 366 | LF | $375.00 | $650.00 | $700.00 | $910.00 | $700.00 | $936.94 | $1,000.00 |
| 5 | 416-6007 | DRILL SHAFT (54 IN) | 254 | LF | $450.00 | $700.00 | $850.00 | $1,150.00 | $875.00 | $1,188.17 | $1,000.00 |
| 6 | 420-6033 | CL C CONC (CAP)(EXTEND) | 217.3 | CY | $1,800.00 | $1,200.00 | $2,000.00 | $2,400.00 | $2,000.00 | $1,794.20 | $1,900.00 |
| 7 | 420-6037 | CL C CONC (COLUMN) | 56 | CY | $2,000.00 | $1,400.00 | $2,000.00 | $2,100.00 | $2,500.00 | $2,978.79 | $2,400.00 |
| 8 | 496-6079 | REMOVE STR (PILING) | 2 | EA | $4,000.00 | $200.00 | $5,000.00 | $3,300.00 | $2,000.00 | $31,521.00 | $25,000.00 |
| 9 | 500-6001 | MOBILIZATION | 1 | LS | $100,000.00 | $105,000.00 | $200,000.00 | $213,000.00 | $269,000.00 | $258,020.00 | $250,000.00 |
| 10 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 | MO | $2,500.00 | $3,000.00 | $2,000.00 | $10,000.00 | $1,600.00 | $2,261.72 | $3,000.00 |
| 11 | 506-6034 | CONSTRUCTION PERIMETER FENCE | 1,880 | LF | $3.00 | $2.00 | $10.00 | $5.00 | $20.00 | $7.45 | $7.00 |
| 12 | 506-6038 | TEMP SEDMT CONT FENCE (INSTALL) | 375 | LF | $3.00 | $5.00 | $10.00 | $3.00 | $16.00 | $5.32 | $4.00 |
| 13 | 506-6039 | TEMP SEDMT CONT FENCE (REMOVE) | 375 | LF | $1.00 | $2.00 | $10.00 | $0.7500 | $6.00 | $1.33 | $2.00 |
| 14 | 552-6001 | WIRE FENCE (TY A) | 40 | LF | $20.00 | $50.00 | $100.00 | $15.00 | $40.00 | $39.90 | $50.00 |
| 15 | 552-6005 | GATE (TY 1) | 1 | EA | $800.00 | $1,000.00 | $3,500.00 | $1,500.00 | $1,500.00 | $3,325.00 | $2,000.00 |
| 16 | 4027-6001 | TEMP CONSTRUCTION ACCESS | 1 | LS | $100,000.00 | $365,000.00 | $600,000.00 | $560,000.00 | $1,200,000.00 | $984,200.00 | $1,020,000.00 |
| 17 | 7000-6002 | REML & DISPL DRIFTWOOD & DEBRIS | 1 | LS | $18,000.00 | $70,000.00 | $10,000.00 | $18,000.00 | $50,000.00 | $33,250.00 | $75,000.00 |