‹ Mar 2021 results
UPGRADE MBGF
- Let date
- Thursday, March 4, 2021
- CCSJ
- 0055-07-062
- District
- Waco
- County
- McLennan
- Highway
- US 84
- Limits
- SH 317 to OAK CREEK DRIVE
- Classification
- Construction
- Project number
- F 2021(407)
- Working days
- 105
Bidders 10
| # | Contractor | Total bid | vs estimate | vs low |
| EE | Engineer's estimate | $2,057,976 | | |
| 1 |
TALBRAN ENTERPRISES LLC Low bidder |
$1,857,025 |
-9.8% |
|
| 2 |
ODUM SERVICES, LLC |
$1,985,973 |
-3.5% |
+6.9% |
| 3 |
ALTUS CONSTRUCTION LLC |
$1,989,668 |
-3.3% |
+7.1% |
| 4 |
SEFBO PIPELINE BRIDGE, INCORPORATED |
$2,002,168 |
-2.7% |
+7.8% |
| 5 |
3LW CIVIL LLC |
$2,046,617 |
-0.6% |
+10.2% |
| 6 |
NEW WORLD CONTRACTING, LLC |
$2,074,000 |
+0.8% |
+11.7% |
| 7 |
DBI SERVICES, LLC |
$2,197,788 |
+6.8% |
+18.3% |
| 8 |
ELITE CASTLE RESOURCES LLC |
$2,208,465 |
+7.3% |
+18.9% |
| 9 |
SJ&J CONSTRUCTION, LLC |
$2,220,944 |
+7.9% |
+19.6% |
| 10 |
BIG CREEK CONSTRUCTION, LTD. |
$2,673,946 |
+29.9% |
+44.0% |
Bid tab: unit prices 28 items
ExcelCSV
| Seq | Bid code | Description | Qty | Unit | Estimate |
#1 TALBRAN ENTERPR… | #2 ODUM SERVICES, … | #3 ALTUS CONSTRUCT… | #4 SEFBO PIPELINE … | #5 3LW CIVIL LLC | #6 NEW WORLD CONTR… | #7 DBI SERVICES, L… | #8 ELITE CASTLE RE… |
| 1 | 104-6010 |
REMOVING CONC (RIPRAP) | 676 | CY |
$120.00 |
$55.00 |
$15.00 |
$94.94 |
$46.23 |
$20.00 |
$67.50 |
$135.00 |
$50.00 |
| 2 | 134-6001 |
BACKFILL (TY A) | 309 | STA |
$195.00 |
$88.00 |
$125.00 |
$206.86 |
$197.15 |
$45.00 |
$60.00 |
$140.00 |
$250.00 |
| 3 | 162-6008 |
ROLL SODDING | 15,358 | SY |
$5.00 |
$5.50 |
$5.00 |
$3.49 |
$6.86 |
$0.5000 |
$3.85 |
$4.50 |
$5.00 |
| 4 | 168-6001 |
VEGETATIVE WATERING | 42 | MG |
$20.00 |
$1.00 |
$10.00 |
$31.75 |
$52.50 |
$3.50 |
$85.25 |
$100.00 |
$200.00 |
| 5 | 432-6041 |
RIPRAP (SPECIAL) | 77 | CY |
$425.00 |
$550.00 |
$500.00 |
$664.37 |
$500.00 |
$600.00 |
$463.00 |
$565.00 |
$500.00 |
| 6 | 432-6045 |
RIPRAP (MOW STRIP)(4 IN) | 1,452 | CY |
$320.00 |
$440.00 |
$500.00 |
$261.80 |
$394.40 |
$400.00 |
$415.00 |
$445.00 |
$450.00 |
| 7 | 500-6001 |
MOBILIZATION | 1 | LS |
$115,000.00 |
$16,500.00 |
$100,000.00 |
$196,830.35 |
$200,000.00 |
$100,000.00 |
$95,060.82 |
$75,000.00 |
$150,000.00 |
| 8 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 | MO |
$5,000.00 |
$1.00 |
$3,500.00 |
$12,698.73 |
$2,500.00 |
$38,261.00 |
$15,000.00 |
$13,500.00 |
$3,500.00 |
| 9 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 1,000 | LF |
$4.00 |
$1.00 |
$3.00 |
$2.61 |
$3.44 |
$0.3000 |
$3.65 |
$5.00 |
$5.00 |
| 10 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 1,000 | LF |
$1.00 |
$1.00 |
$1.00 |
$0.7600 |
$1.06 |
$0.3000 |
$1.45 |
$1.00 |
$1.00 |
| 11 | 540-6002 |
MTL W-BEAM GD FEN (STEEL POST) | 25,925 | LF |
$27.00 |
$22.00 |
$22.50 |
$22.71 |
$22.30 |
$25.00 |
$23.00 |
$27.80 |
$26.00 |
| 12 | 540-6006 |
MTL BEAM GD FEN TRANS (THRIE-BEAM) | 15 | EA |
$2,300.00 |
$1,540.00 |
$1,750.00 |
$2,162.59 |
$338.54 |
$2,000.00 |
$3,078.00 |
$2,000.00 |
$2,400.00 |
| 13 | 540-6014 |
SHORT RADIUS | 178.6 | LF |
$30.00 |
$25.00 |
$55.00 |
$129.08 |
$71.25 |
$35.00 |
$37.50 |
$55.00 |
$45.00 |
| 14 | 540-6016 |
DOWNSTREAM ANCHOR TERMINAL SECTION | 51 | EA |
$1,400.00 |
$1,430.00 |
$1,350.00 |
$1,499.07 |
$7.50 |
$1,200.00 |
$1,101.00 |
$1,225.00 |
$1,400.00 |
| 15 | 540-6039 |
MTL BM GD FEN TRANS (31"-28")(25') | 10 | EA |
$400.00 |
$1,210.00 |
$600.00 |
$625.72 |
$937.50 |
$400.00 |
$660.00 |
$1,000.00 |
$800.00 |
| 16 | 542-6001 |
REMOVE METAL BEAM GUARD FENCE | 23,737.5 | LF |
$3.00 |
$2.20 |
$1.00 |
$2.51 |
$2.11 |
$1.00 |
$2.45 |
$0.1000 |
$1.00 |
| 17 | 542-6003 |
REMOVE DOWNSTREAM ANCHOR TERMINAL | 49 | EA |
$180.00 |
$220.00 |
$100.00 |
$246.26 |
$127.55 |
$200.00 |
$175.00 |
$275.00 |
$200.00 |
| 18 | 542-6004 |
RM MTL BM GD FENCE TRANS (THRIE-BEAM) | 21 | EA |
$250.00 |
$330.00 |
$150.00 |
$266.01 |
$208.33 |
$200.00 |
$325.00 |
$250.00 |
$200.00 |
| 19 | 544-6001 |
GUARDRAIL END TREATMENT (INSTALL) | 69 | EA |
$2,800.00 |
$3,200.00 |
$2,450.00 |
$2,658.81 |
$2,687.50 |
$2,500.00 |
$2,780.00 |
$2,800.00 |
$3,500.00 |
| 20 | 544-6003 |
GUARDRAIL END TREATMENT (REMOVE) | 64 | EA |
$250.00 |
$220.00 |
$150.00 |
$305.36 |
$126.95 |
$200.00 |
$295.00 |
$125.00 |
$200.00 |
| 21 | 545-6005 |
CRASH CUSH ATTEN (REMOVE) | 1 | EA |
$700.00 |
$1,100.00 |
$1,000.00 |
$1,060.22 |
$625.00 |
$1,000.00 |
$913.00 |
$1,500.00 |
$2,500.00 |
| 22 | 560-6007 |
MAILBOX INSTALL-S (WC-POST) TY 3 | 3 | EA |
$400.00 |
$220.00 |
$250.00 |
$263.77 |
$562.50 |
$200.00 |
$204.00 |
$250.00 |
$500.00 |
| 23 | 658-6062 |
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI) | 16 | EA |
$50.00 |
$33.00 |
$35.00 |
$29.47 |
$34.38 |
$25.00 |
$77.60 |
$50.00 |
$20.00 |
| 24 | 658-6063 |
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BR) | 203 | EA |
$50.00 |
$33.00 |
$35.00 |
$52.46 |
$32.50 |
$25.00 |
$77.60 |
$50.00 |
$20.00 |
| 25 | 658-6065 |
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2(BR) | 146 | EA |
$50.00 |
$33.00 |
$35.00 |
$64.74 |
$32.50 |
$25.00 |
$77.60 |
$50.00 |
$20.00 |
| 26 | 6001-6001 |
PORTABLE CHANGEABLE MESSAGE SIGN | 20 | DAY |
$77.00 |
$330.00 |
$50.00 |
$63.47 |
$200.00 |
$50.00 |
$198.00 |
$100.00 |
$250.00 |
| 27 | 6001-6002 |
PORTABLE CHANGEABLE MESSAGE SIGN | 2 | EA |
$15,000.00 |
$1.00 |
$12,000.00 |
$6,349.37 |
$2,625.00 |
$9,800.00 |
$19,485.00 |
$5,500.00 |
$5,000.00 |
| 28 | 6185-6002 |
TMA (STATIONARY) | 240 | DAY |
$105.00 |
$1.00 |
$95.00 |
$177.78 |
$357.71 |
$50.00 |
$145.00 |
$150.00 |
$100.00 |
Showing the first 8 bidders. The Excel and CSV downloads include all 10.