LANDSCAPE DEVELOPMENT
- Let date
- Thursday, September 7, 2023
- CCSJ
- 0013-10-091
- District
- Fort Worth
- County
- Tarrant
- Highway
- BU 287P
- Limits
- WJ BOAZ RD to BAILEY BOSWELL RD
- Classification
- Construction
- Project number
- F 2023(972)
- Working days
- 96
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $360,609 | ||
| 1 | TIGHT LINE CONSTRUCTION, LLC Low bidder | $307,805 | -14.6% | |
| 2 | TEXAS ROAD CONSTRUCTION, LLC | $317,170 | -12.0% | +3.0% |
| 3 | CENTRAL NORTH CONSTRUCTION, LLC | $328,852 | -8.8% | +6.8% |
| 4 | C. GREEN SCAPING, L.P. | $335,333 | -7.0% | +8.9% |
| 5 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $389,371 | +8.0% | +26.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 TIGHT LINE CONS… | #2 TEXAS ROAD CONS… | #3 CENTRAL NORTH C… | #4 C. GREEN SCAPIN… | #5 SCOTT TUCKER CO… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 100-6002 | PREPARING ROW | 10 | STA | $5,000.00 | $1,000.00 | $1,000.00 | $3,000.00 | $3,170.00 | $1,574.00 |
| 2 | 105-6014 | REMOVING STAB BASE & ASPH PAV (7"-12") | 76 | SY | $11.00 | $100.00 | $100.00 | $50.00 | $80.00 | $107.00 |
| 3 | 164-6008 | BROADCAST SEED (PERM) (URBAN) (CLAY) | 0.25 | AC | $2,000.00 | $7,500.00 | $2,000.00 | $6,500.00 | $4,200.00 | $6,806.00 |
| 4 | 166-6001 | FERTILIZER | 0.25 | AC | $2,500.00 | $7,500.00 | $2,000.00 | $1,600.00 | $1,500.00 | $3,846.00 |
| 5 | 168-6001 | VEGETATIVE WATERING | 8.7 | MG | $100.00 | $1.00 | $0.1000 | $2.00 | $84.00 | $349.00 |
| 6 | 170-6001 | IRRIGATION SYSTEM | 1 | LS | $40,000.00 | $65,000.00 | $80,000.00 | $78,918.60 | $27,800.00 | $36,710.00 |
| 7 | 192-6003 | PLANT MATERIAL (3-GAL) | 1,631 | EA | $20.00 | $30.00 | $20.00 | $12.00 | $16.00 | $47.00 |
| 8 | 192-6015 | LANDSCAPE EDGE | 822 | LF | $25.00 | $15.00 | $20.00 | $13.00 | $11.00 | $11.00 |
| 9 | 192-6016 | PLANT BED PREPARATION | 968 | SY | $10.00 | $10.00 | $20.00 | $4.00 | $21.00 | $16.00 |
| 10 | 193-6001 | PLANT MAINTENANCE | 12 | MO | $3,300.00 | $1,250.00 | $700.00 | $1,900.00 | $2,900.00 | $1,482.00 |
| 11 | 193-6007 | IRRIGATION SYSTEM OPER AND MAINT | 12 | MO | $1,600.00 | $1,250.00 | $700.00 | $900.00 | $1,100.00 | $762.00 |
| 12 | 432-6001 | RIPRAP (CONC)(4 IN) | 23 | CY | $1,000.00 | $1,250.00 | $1,000.00 | $2,800.00 | $2,343.00 | $1,970.00 |
| 13 | 432-6041 | RIPRAP (SPECIAL) | 103 | CY | $475.00 | $400.00 | $500.00 | $450.00 | $594.00 | $821.00 |
| 14 | 500-6001 | MOBILIZATION | 1 | LS | $20,000.00 | $30,000.00 | $32,500.00 | $16,500.00 | $15,300.00 | $38,940.00 |
| 15 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 5 | MO | $7,500.00 | $1,500.00 | $3,000.00 | $3,250.00 | $4,080.00 | $2,845.00 |
| 16 | 506-6040 | BIODEG EROSN CONT LOGS (INSTL) (8") | 1,107 | LF | $5.00 | $7.00 | $6.00 | $1.00 | $6.60 | $5.00 |
| 17 | 506-6043 | BIODEG EROSN CONT LOGS (REMOVE) | 1,107 | LF | $2.50 | $1.00 | $1.00 | $0.5000 | $2.00 | $2.00 |
| 18 | 1004-6001 | TREE PROTECTION | 12 | EA | $700.00 | $350.00 | $300.00 | $100.00 | $320.00 | $349.00 |