| Let date | CCSJ | County / District | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Nov 3, 2026 estimated | 0168-09-191 | RandallAmarillo | IH 27 | Bridge Maintenance IH 27 NB/WESTERN AVE BRG to . | $1,782,503 | Planned | COPPELL CONSTRUCTION CO., INC. $5,800,486 · +225.4% | |
| Nov 3, 2026 estimated | 0168-09-192 | RandallAmarillo | IH 27 | Bridge Maintenance IH 27 SB/WESTERN AVE BRG to . | $1,821,007 | Planned | ||
| Nov 3, 2026 estimated | 0168-09-193 | RandallAmarillo | IH 27 | Bridge Maintenance IH 27 NB/HILLSIDE RD BRG to . | $722,715 | Planned | ||
| Nov 3, 2026 estimated | 0168-09-194 | RandallAmarillo | IH 27 | Bridge Maintenance IH 27 SB/HILLSIDE RD BRG to . | $641,547 | Planned | ||
| Nov 3, 2026 estimated | 0168-09-200 | RandallAmarillo | IH 27 | Safety Improvement Projects Bridge Maintenance .7 M SOUTH OF WESTERN ST to .13 M NORTH OF WESTERN ST | $848,781 | Planned | ||
| Nov 3, 2026 estimated | 1626-01-013 | RandallAmarillo | FM 1714 | Seal Coat FM 168 to US 87 | $734,199 | Planned | ||
| Nov 3, 2026 estimated | 2614-01-031 | RandallAmarillo | FM 2590 | Seal Coat .3 MI NORTH OF SL 335 to .1 MI NORTH OF SL 335 (END CURB & GUTTER | $27,713 | Planned | ||
| Nov 3, 2026 estimated | 2635-03-030 | RandallAmarillo | FM 2590 | Seal Coat .2 MI SOUTH OF HILLSIDE ( AT PINERIDGE D to .3 MI NORTH OF SL 335 | $322,367 | Planned | ||
| Dec 1, 2026 | 2635-03-031 F 2027(215) | PotterRandallAmarillo | FM 2590 | Overlay Preventive Maintenance POTTER COUNTY LINE to SOUTH SL 335 (HOLLYWOOD RD) | $4,418,88192 items | Official | ||
| Apr 6, 2027 estimated | 2494-02-011 | RandallAmarillo | SL 335 | New Location Freeway Construct New Road WEST OF FM 2590 (SOUTH) to FM 2186 | $16,038,435 | Planned | ||
| Apr 6, 2027 estimated | 2635-05-004 | RandallAmarillo | SL 335 | New Location Freeway Construct New Road FM 2186 to NORTH OF FM 2186 | $32,125,308 | Planned | ||
| May 5, 2027 estimated | 0168-09-186 | RandallAmarillo | IH 27 | Rehabilitation of Existing Road Construct New Road Sundown Lane to SL 335 | $18,400,000 | Planned | ||
| May 5, 2027 estimated | 0904-11-071 | RandallAmarillo | CS 252414 | Bridge Widening or Rehabilitation Rehabilitate Bridge 34th Ave at BNSF to . | $4,000,000 | Planned | ||
| May 5, 2027 estimated | 2635-02-034 | RandallAmarillo | SL 335 | New Location Freeway Construct New Road IH 27 to BELL STREET | $29,050,000 | Planned | ||
| May 5, 2027 estimated | 2635-03-023 | RandallAmarillo | SL 335 | New Location Freeway Construct New Road EAST OF COULTER to IH 27 | $27,350,000 | Planned | ||
| May 5, 2027 estimated | 2635-03-028 | RandallAmarillo | SL 335 | Interchange (New or Reconstructed) Construct New Road IH 27 to Coulter | $162,800,000 | Planned | ||
| Oct 5, 2027 estimated | 0464-01-028 | RandallAmarillo | SH 217 | Overlay Preventive Maintenance FM 1541 to PALO DURO CANYON | $6,500,000 | Planned |
1–17 of 17
Advertised proposals and bid items: TxDOT Official and Unofficial Bid Items (data.texas.gov). Planned projects: TxDOT Projects Info service; their let dates are TxDOT estimates and often slip. Low bidders: TxDOT Bid Tabulations. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.