Filtered by: Work type: Bridge Maintenance Clear all
| Let date | CCSJ | County / District | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jun 1, 2027 estimated | 0053-05-055 | GarzaLubbock | US 84 | Bridge Maintenance 05-086-0-0053-05-091 to On US 84 @ BNSF RR | $1,200,000 | Planned | ||
| Jun 1, 2027 estimated | 0053-05-056 | GarzaLubbock | US 84 | Bridge Maintenance 05-086-0-0053-05-092 to On US 84 @ BNSF RR | $1,200,000 | Planned | ||
| Jun 1, 2027 estimated | 0067-07-108 | LubbockLubbock | SS 326 | Bridge Maintenance NBI 05-152-0-0067-07-035 to On Spur 326 | $569,000 | Planned | ||
| Jun 1, 2027 estimated | 0092-14-112 | DallasDallas | IH 345 | Bridge Maintenance IH 30 to SP 366 | $4,500,000 | Planned | ||
| Jun 1, 2027 estimated | 0095-10-059 | DallasDallas | US 80 | Bridge Maintenance At IH 30 WB Connector Ramp to . | $2,120,703 | Planned | ||
| Jun 1, 2027 estimated | 0134-07-076 | WiseFort Worth | US 380 | Bridge Maintenance Begin Bridge Approach to End Bridge Approach | $573,313 | Planned | ||
| Jun 1, 2027 estimated | 0171-01-037 | JackFort Worth | SH 199 | Bridge Maintenance Begin Bridge to End Bridge | $504,128 | Planned | ||
| Jun 1, 2027 estimated | 0171-02-030 | WiseFort Worth | SH 199 | Bridge Maintenance Begin Bridge to End Bridge | $372,680 | Planned | ||
| Jun 1, 2027 estimated | 0249-05-033 | JackFort Worth | US 281 | Bridge Maintenance Begin Bridge to End Bridge | $1,079,507 | Planned | ||
| Jun 1, 2027 estimated | 0249-08-047 | Palo PintoFort Worth | US 281 | Bridge Maintenance Begin Bridge to End Bridge | $344,314 | Planned | ||
| Jun 1, 2027 estimated | 0259-03-066 | SomervellFort Worth | US 67 | Bridge Maintenance Begin Bridge to End Bridge | $836,664 | Planned | ||
| Jun 1, 2027 estimated | 0265-08-072 | FayetteYoakum | SH 71 | Bridge Maintenance @ Colorado River to STR # 0265-08-092 | $3,538,363 | Planned | ||
| Jun 1, 2027 estimated | 0353-01-029 | WiseFort Worth | SH 114 | Bridge Maintenance at US 81 to . | $1,814,131 | Planned | ||
| Jun 1, 2027 estimated | 0380-01-099 | LubbockLubbock | US 82 | Bridge Maintenance 19th W Connector to At US 82 | $2,000,000 | Planned | ||
| Jun 1, 2027 estimated | 0718-01-078 | DentonDallas | FM 156 | Bridge Maintenance North of Tributary to Elizabeth Creek to South of Elizabeth Creek | $457,789 | Planned | ||
| Jun 1, 2027 estimated | 1330-01-074 | TarrantFort Worth | FM 1187 | Bridge Maintenance Begin Bridge to End Bridge | $484,784 | Planned | ||
| Jun 1, 2027 estimated | 1330-01-075 | TarrantFort Worth | FM 1187 | Bridge Maintenance Begin Bridge Approach to End Bridge Approach | $301,234 | Planned | ||
| Jun 1, 2027 estimated | 1330-02-054 | TarrantFort Worth | FM 1187 | Bridge Maintenance Begin Bridge Approach to End Bridge Approach | $522,444 | Planned | ||
| Jun 1, 2027 estimated | 3123-01-016 | HoodFort Worth | FM 4 | Bridge Maintenance Begin Bridge to End Bridge | $463,069 | Planned |
1–19 of 19
Advertised proposals and bid items: TxDOT Official and Unofficial Bid Items (data.texas.gov). Planned projects: TxDOT Projects Info service; their let dates are TxDOT estimates and often slip. Low bidders: TxDOT Bid Tabulations. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.