Bid tab 0924-00-183

Let Sep 5, 2025 · El Paso · El Paso Sign up free

‹ Sep 2025 results

IH 10 BMIP (FY 2026)

Let date
Friday, September 5, 2025
CCSJ
0924-00-183
District
El Paso
County
El Paso
Highway
Various
Limits
ON IH 10 (DISTRICTWIDE) to .
Classification
Bridge Widening or Rehabilitation · Construction
Project number
BR 2B25(034)
Working days
164
DBE goal
2%

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$6,376,066
1 INTERNATIONAL EAGLE ENTERPRISES, INC. Low bidder $4,508,216 -29.3%
2 DAN WILLIAMS COMPANY $5,505,586 -13.7% +22.1%
3 GIBSON & ASSOCIATES, INC. $6,161,335 -3.4% +36.7%
4 SPARTAN CONSTRUCTION OF TEXAS, INC. $6,339,711 -0.6% +40.6%
5 SOUTHERN ROAD & BRIDGE, LLC $9,429,909 +47.9% +109.2%

Bid tab: unit prices 51 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 INTERNATIONAL E…#2 DAN WILLIAMS CO…#3 GIBSON & ASSOCI…#4 SPARTAN CONSTRU…#5 SOUTHERN ROAD &…
1104-7006 REMOV CONC (RIPRAP)36SY $26.00 $200.00 $42.00 $27.50 $104.64 $25.00
2132-7001 EMBANK (FNL)(OC)(TY A)2CY $161.00 $500.00 $300.00 $750.00 $1,962.00 $95.00
3351-7001 FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")4SY $45.00 $1,000.00 $1,500.00 $1,250.00 $1,700.40 $25.00
4354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2")715SY $10.00 $2.00 $10.00 $15.38 $33.98 $25.00
5401-7001 FLOWABLE BACKFILL10CY $275.00 $350.00 $1,000.00 $467.50 $849.60 $1,950.00
6427-7005 EPOXY WATERPROOF FINISH (TY X)2,190SF $18.00 $5.00 $11.00 $13.20 $15.70 $22.00
7429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH))35SF $225.00 $160.00 $250.00 $308.00 $294.30 $485.00
8429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD)435SF $300.00 $170.00 $225.00 $380.00 $176.58 $600.00
9432-7001 RIPRAP (CONC)(4 IN)7CY $930.00 $1,200.00 $2,000.00 $973.50 $1,373.40 $650.00
10432-7013 RIPRAP (MOW STRIP)(4 IN)20CY $550.00 $850.00 $1,700.00 $907.50 $1,308.00 $500.00
11432-7031 RIPRAP (STONE COMMON)(DRY)(12 IN)15CY $145.00 $500.00 $300.00 $313.50 $654.00 $500.00
12434-7002 ELASTOMERIC BEARING (LAMINATED)72EA $3,000.00 $200.00 $550.00 $350.00 $915.60 $4,250.00
13438-7007 CLEANING AND SEALING EXIST JOINTS (CL7)180LF $36.00 $30.00 $30.00 $48.00 $52.32 $125.00
14439-7004 CONCRETE OVERLAY (3 IN)715SY $130.00 $125.00 $143.00 $178.00 $183.12 $225.00
15442-7017 MISC NON-BRIDGE (NBIS)336LB $25.00 $20.00 $15.00 $25.00 $23.54 $95.00
16483-7011 HYDRO-DEMOLITION (2 1/2 IN)715SY $132.00 $140.00 $240.00 $186.00 $156.96 $408.00
17483-7012 HYDRO-DEMOLITION (3 IN)1,590SY $140.00 $140.00 $249.00 $162.00 $189.66 $525.00
18495-7001 RAISING EXIST STRUCT1LS $100,000.00 $250,000.00 $150,000.00 $137,000.00 $326,400.00 $77,000.00
19500-7001 MOBILIZATION1LS $800,000.00 $400,000.00 $500,000.00 $736,000.00 $629,016.00 $600,000.00
20502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING10MO $12,000.00 $20,000.00 $30,000.00 $51,000.00 $19,620.00 $10,000.00
21503-7002 PORTABLE CHANGEABLE MESSAGE SIGN6EA $12,000.00 $14,000.00 $12,000.00 $25,000.00 $13,080.00 $22,000.00
22505-7001 TMA (STATIONARY)375DAY $300.00 $100.00 $175.00 $450.00 $523.20 $330.00
23505-7003 TMA (MOBILE OPERATION)8DAY $500.00 $300.00 $650.00 $1,050.00 $4,578.00 $300.00
24540-7002 MTL W-BEAM GD FEN (STEEL POST)125LF $46.00 $40.00 $35.00 $53.08 $71.94 $39.00
25542-7001 REMOVE METAL BEAM GUARD FENCE225LF $10.00 $2.00 $6.00 $11.00 $13.08 $6.00
26542-7003 REMOVE DOWNSTREAM ANCHOR TERMINAL2EA $300.00 $800.00 $350.00 $1,650.00 $1,962.00 $1,100.00
27544-7001 GUARDRAIL END TREATMENT (INSTALL)4EA $4,500.00 $3,000.00 $4,000.00 $5,340.50 $5,886.00 $3,988.00
28544-7003 GUARDRAIL END TREATMENT (REMOVE)2EA $325.00 $800.00 $350.00 $1,650.00 $1,308.00 $7,500.00
29644-7061 IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)4EA $2,330.00 $2,500.00 $2,000.00 $5,791.50 $3,270.00 $250.00
30658-7012 INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB12EA $22.00 $10.00 $55.00 $203.50 $91.56 $110.00
31658-7019 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)16EA $38.00 $10.00 $55.00 $203.50 $91.56 $110.00
32658-7031 INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB12EA $20.00 $5.00 $55.00 $203.50 $91.56 $110.00
33662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W130EA $2.30 $4.00 $2.25 $10.00 $6.54 $1.00
34662-7113 WK ZN PAV MRK SHT TERM (TAB)TY Y130EA $2.30 $4.00 $2.25 $10.00 $6.54 $1.00
35666-7172 RE PM TY II (W) 6" (BRK)486LF $0.2000 $1.60 $0.8000 $0.8800 $1.11 $1.00
36666-7175 RE PM TY II (W) 6" (SLD)1,940LF $0.4900 $0.7000 $0.3500 $0.3900 $0.5230 $2.00
37666-7213 RE PM TY II (Y) 6" (SLD)1,940LF $0.4900 $0.7000 $0.3500 $0.3900 $0.5230 $2.00
38666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL)1,940LF $2.25 $4.60 $2.30 $2.53 $3.14 $3.00
39666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL)1,940LF $2.25 $4.60 $2.30 $2.53 $3.14 $3.00
40666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL)486LF $1.84 $4.80 $2.40 $2.64 $3.27 $4.00
41668-7008 PREFAB PM TY B (W)(6")(BRK)834LF $13.00 $13.00 $6.50 $7.15 $8.63 $10.00
42668-7009 PREFAB PM TY B (W)(6")(SLD)1,112LF $10.00 $12.00 $6.00 $6.60 $8.11 $9.00
43668-7012 PREFAB PM TY B (W)(6")(BRK)CONTRAST834LF $25.00 $28.00 $14.00 $15.40 $18.31 $18.00
44668-7051 PREFAB PM TY B (Y)(6")(SLD)1,112LF $10.00 $13.00 $6.50 $7.15 $8.63 $10.00
45672-7006 REFL PAV MRKR TY II-C-R68EA $8.05 $18.00 $9.00 $9.90 $13.08 $12.00
46678-7002 PAV SURF PREP FOR MRK (6")7,424LF $0.4000 $0.6800 $0.3400 $0.3700 $0.5890 $1.00
47752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS)0.1AC $2,750.00 $2,000.00 $10,000.00 $20,000.00 $235,440.00 $25,000.00
48780-7002 CNC CRACK REPAIR (DISCRETE)(INJECT)3LF $78.00 $15.00 $300.00 $500.00 $1,308.00 $353.00
49785-7011 BRIDGE JOINT REPLACEMENT (SEJ)118LF $800.00 $500.00 $500.00 $500.00 $555.90 $858.00
50786-7002 CARBON FIBER REINF POLYMER STRENGTHNING2,310SF $155.00 $40.00 $35.00 $41.00 $58.86 $105.00
517001-7002 BENT CAP/ABUTMENT CAP CLEANING16EA $1,100.00 $1,000.00 $750.00 $1,400.00 $3,270.00 $1,500.00