32BidsFeb 3, 2017 to Nov 6, 2024
10Wins (low bidder)
31.3%Win rate
$12,739,809Total won
Competitor scorecard
Last 5 years in Texas33.3%Win rate6 of 18 bids
+9.0%Average bid vs estimate
-7.5%Winning bids vs estimate
+14.9%Over the low bid when they loseAverage field: 4.4 bidders
| Head to head | Times met | Beat them | Lost to them | Record |
|---|---|---|---|---|
| THE LEVY COMPANY, INC. | 15 | 9 | 6 | 60% |
| E-Z BEL CONSTRUCTION, LLC | 10 | 4 | 6 | 40% |
| TRAF-TEX, INC. | 8 | 6 | 2 | 75% |
| AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | 7 | 3 | 4 | 43% |
| FLORIDA TRAFFIC CONTROL DEVICES, INC. | 3 | 3 | 0 | 100% |
| VACA UNDERGROUND UTILITIES INC | 3 | 1 | 2 | 33% |
| ELECNOR BELCO ELECTRIC, INC. | 3 | 1 | 2 | 33% |
| MALDONADO-BURKETT, LLP | 3 | 3 | 0 | 100% |
| THIRD COAST SERVICES LLC | 2 | 1 | 1 | 50% |
| F & W ELECTRICAL CONTRACTORS, INC. | 2 | 2 | 0 | 100% |
| Let date | CCSJ | Project | Rank | Their bid | Low bid | vs low |
|---|---|---|---|---|---|---|
| Nov 6, 2024 | 0915-12-758 | VA: 0915-12-758: CoSA SFT TS BackplatesBexar · San Antonio | 4 of 8 | $1,437,500 | $1,111,075THE LEVY COMPANY, INC. | +29.4% |
| Jun 5, 2024 | 0038-07-084 | HAZARD ELIMINATION & SAFETYStarr · Pharr | 4 of 4 | $584,907 | $506,977AUSTIN TRAFFIC SIGNAL CONST… | +15.4% |
| Dec 6, 2023 | 0922-00-081 | INSTALL/UPGRADE ROADWAY LIGHTINGWebb · Laredo | 1 of 6 | $663,050 | $663,050 | Won |
| Dec 6, 2023 | 0291-10-119 | HAZARD ELIMINATION & SAFETYBexar · San Antonio | 1 of 5 | $452,898 | $452,898 | Won |
| Jun 28, 2023 | 0220-04-059 | HAZARD ELIMINATION & SAFETYCameron · Pharr | 2 of 4 | $935,415 | $930,687AUSTIN TRAFFIC SIGNAL CONST… | +0.5% |
| Jun 28, 2023 | 1803-02-049 | HAZARD ELIMINATION & SAFETYHidalgo · Pharr | 3 of 4 | $400,922 | $346,822THE LEVY COMPANY, INC. | +15.6% |
| Jun 28, 2023 | 0073-08-205 | HAZARD ELIMINATION & SAFETYBexar · San Antonio | 5 of 7 | $527,100 | $458,850ELECNOR BELCO ELECTRIC, INC. | +14.9% |
| Jun 28, 2023 | 0921-02-484 | HAZARD ELIMINATION & SAFETYHidalgo · Pharr | 3 of 4 | $357,305 | $307,598AUSTIN TRAFFIC SIGNAL CONST… | +16.2% |
| Jun 28, 2023 | 0921-02-500 | HAZARD ELIMINATION & SAFETYHidalgo · Pharr | 2 of 3 | $248,596 | $223,433THE LEVY COMPANY, INC. | +11.3% |
| Jun 28, 2023 | 6446-74-001 | LARGE SIGN REPLACEMENTHidalgo · Pharr | 1 of 4 | $1,211,753 | $1,211,753 | Won |
| Jun 27, 2023 | 0087-02-055 | HAZARD ELIMINATION & SAFETYJim Wells · Corpus Christi | 1 of 5 | $1,046,002 | $1,046,002 | Won |
| May 4, 2023 | 0038-07-083 | INSTALL TRAFFIC SIGNALStarr · Pharr | 2 of 2 | $345,450 | $301,665AUSTIN TRAFFIC SIGNAL CONST… | +14.5% |
| May 4, 2023 | 0915-12-770 | HAZARD ELIMINATION & SAFETYBexar · San Antonio | 4 of 5 | $529,261 | $491,128THE LEVY COMPANY, INC. | +7.8% |
| Aug 3, 2022 | 1586-01-089 | TRAFFIC SIGNAL IMPROVEMENTSHidalgo · Pharr | 1 of 5 | $1,313,573 | $1,313,573 | Won |
| Jun 30, 2022 | 0915-12-693 | HAZARD ELIMINATION & SAFETYBexar · San Antonio | 2 of 3 | $1,935,756 | $1,705,803E-Z BEL CONSTRUCTION, LLC | +13.5% |
| Jun 29, 2022 | 0915-12-624 | HAZARD ELIMINATION & SAFETYBexar · San Antonio | 1 of 3 | $2,074,272 | $2,074,272 | Won |
| Mar 4, 2022 | 0915-17-073 | HAZARD ELIMINATION & SAFETYComal · San Antonio | 2 of 4 | $725,479 | $629,837E-Z BEL CONSTRUCTION, LLC | +15.2% |
| Feb 3, 2022 | 0915-00-236 | TRAFFIC SIGNAL IMPROVEMENTSBexar · San Antonio | 3 of 4 | $1,769,460 | $1,421,995VACA UNDERGROUND UTILITIES … | +24.4% |
| Aug 4, 2021 | 0915-12-625 | HAZARD ELIMINATION & SAFETYBexar · San Antonio | 2 of 3 | $1,595,584 | $1,494,380E-Z BEL CONSTRUCTION, LLC | +6.8% |
| Aug 4, 2021 | 0100-02-068 | INSTALL FLASH BEACON/SFTY LIGHTING @ INTERSECTIONBexar · San Antonio | 3 of 3 | $428,191 | $411,503E-Z BEL CONSTRUCTION, LLC | +4.1% |
| Jul 1, 2021 | 0915-00-234 | TRAFFIC SIGNAL IMPROVEMENTSBexar · San Antonio | 4 of 5 | $1,669,376 | $1,384,854VACA UNDERGROUND UTILITIES … | +20.5% |
| Apr 8, 2021 | 0915-00-235 | TRAFFIC SIGNAL IMPROVEMENTSBexar · San Antonio | 1 of 4 | $1,609,699 | $1,609,699 | Won |
| Feb 4, 2021 | 0915-00-228 | DISTRICTWIDE NON-SITE SPECIFIC TRAF SIGNALS-FY2021Bexar · San Antonio | 2 of 3 | $1,672,295 | $1,625,676THE LEVY COMPANY, INC. | +2.9% |
| Aug 6, 2019 | 0025-09-079 | HAZARD ELIMINATION & SAFETYBexar · San Antonio | 4 of 6 | $686,098 | $627,875THE LEVY COMPANY, INC. | +9.3% |
| Apr 3, 2019 | 0915-00-221 | DISTRICTWIDE TRAFFIC CONTROL DEVICEBexar · San Antonio | 1 of 3 | $1,539,906 | $1,539,906 | Won |
| Apr 2, 2019 | 0915-00-192 | SIGNALS,SIGNS,PAV'T MRKSBexar · San Antonio | 3 of 4 | $1,207,680 | $817,876E-Z BEL CONSTRUCTION, LLC | +47.7% |
| Mar 5, 2019 | 0698-03-095 | SAFETY LIGHTINGHidalgo · Pharr | 3 of 4 | $1,852,733 | $1,620,585AUSTIN TRAFFIC SIGNAL CONST… | +14.3% |
| Apr 3, 2018 | 0915-00-205 | DISTRICTWIDE NON-SITE SPECIFIC TRAFFIC SIGNALSBexar · San Antonio | 1 of 2 | $1,479,469 | $1,479,469 | Won |
| Feb 2, 2018 | 0915-00-181 | DISTRICTWIDE TRAFFIC CONTROL DEVICEBexar · San Antonio | 3 of 3 | $1,501,830 | $1,424,652THE LEVY COMPANY, INC. | +5.4% |
| Feb 2, 2018 | 0039-12-058 | INSTALL INTERSECT. FLASHING BEACONS, SAFETY LIGHTSCameron · Pharr | 3 of 4 | $1,210,031 | $1,094,325AUSTIN TRAFFIC SIGNAL CONST… | +10.6% |
| Apr 4, 2017 | 0915-00-204 | DISTRICTWIDE TRAFFIC CONTROL DEVICEBexar · San Antonio | 1 of 3 | $1,349,187 | $1,349,187 | Won |
| Feb 3, 2017 | 0038-07-068 | INSTALL INT. FLASHING BEACONStarr · Pharr | 2 of 3 | $1,402,143 | $1,030,637AUSTIN TRAFFIC SIGNAL CONST… | +36.0% |
Active prime contracts 3
| CCSJ | Where | Work | Contract | Complete | Report |
|---|---|---|---|---|---|
| 6446-74-001Let Jun 28, 2023 | HidalgoPharr · IH0002 | MAINTENANCE | $1,260,753 | 77% | |
| 0542-01-099Let Jun 2, 2023 | WebbLaredo · BU 59Z | TRAFFIC SIGNAL | $1,849,230 | 100% | |
| 0915-12-624Let Jun 29, 2022 | BexarSan Antonio · CS | HAZARD ELIMINATION & SAFETY | $2,256,832 | 61% |
Subcontracts on active jobs 28
| CCSJ | Prime contractor | Where | Work | Share | Value (est.) |
|---|---|---|---|---|---|
| 1426-01-058Let Apr 8, 2026 | IOC COMPANY LLC | CameronPharr | OVERLAY | 1.09% | $92,040 |
| 0038-07-080Let Jan 7, 2026 | IOC COMPANY LLC | StarrPharr | OVERLAY | 2.56% | $65,521 |
| 0863-01-075Let Dec 2, 2025 | IOC COMPANY LLC | HidalgoPharr | OVERLAY | 0.64% | $75,056 |
| 3632-01-001Let Sep 5, 2025 | POSILLICO CIVIL, INC. | StarrPharr | NEWLOCATION NON-FREEWAY | 0.88% | $550,202 |
| 3586-02-007Let Jul 2, 2025 | CK NEWBERRY, LLC | WebbLaredo | REHABILITATION OF EXISTING ROAD | 0.43% | $113,390 |
| 0255-07-152Let May 1, 2025 | FOREMOST PAVING, INC. | HidalgoPharr | OVERLAY | 1.23% | $80,034 |
| 0258-10-050Let May 1, 2025 | TI-ZACK CONCRETE, LLC | MclennanWaco | MISCELLANEOUS CONSTRUCTION | 3.4% | $95,357 |
| 0613-01-070Let Apr 4, 2025 | CK NEWBERRY, LLC | BexarSan Antonio | HAZARD ELIMINATION & SAFETY | 3.91% | $346,522 |
| 0025-09-081Let Feb 6, 2025 | TEXAS MATERIALS GROUP, INC. | BexarSan Antonio | REHABILITATION OF EXISTING ROAD | 1.11% | $240,646 |
| 0017-05-096Let Nov 6, 2024 | RELMCO, INC. | MedinaSan Antonio | BRIDGE REPLACEMENT | 1.84% | $235,955 |
| 0921-06-359Let Oct 2, 2024 | IOC COMPANY LLC | CameronPharr | MISCELLANEOUS CONSTRUCTION | 5.27% | $375,460 |
| 2452-04-017Let Aug 2, 2024 | STERLING DELAWARE HOLDING COMPANY | BexarSan Antonio | WIDEN FREEWAY | 3.17% | $529,924 |
| 0327-04-039Let Aug 2, 2024 | FOREMOST PAVING, INC. | KenedyPharr | NEW LOCATION FREEWAY | 0.44% | $415,566 |
| 0327-04-037Let Aug 1, 2024 | FOREMOST PAVING, INC. | KenedyPharr | NEW LOCATION FREEWAY | 0.78% | $268,236 |
| 0916-29-019Let Aug 1, 2024 | MAKO CONTRACTING, LLC | Live OakCorpus Christi | MISCELLANEOUS CONSTRUCTION | 11.54% | $115,213 |
| 0037-08-042Let Jul 9, 2024 | HUNTER INDUSTRIES, LTD. | DimmitLaredo | REHABILITATION OF EXISTING ROAD | 0.97% | $444,648 |
| 0907-00-229Let Jun 6, 2024 | RELMCO, INC. | Tom GreenSan Angelo | MISCELLANEOUS CONSTRUCTION | 11.89% | $370,433 |
| 3483-02-002Let May 2, 2024 | WEBBER, LLC | WebbLaredo | NEWLOCATION NON-FREEWAY | 1.53% | $1,887,175 |
| 0074-02-082Let May 2, 2024 | HUNTER INDUSTRIES, LTD. | Live OakCorpus Christi | OVERLAY | 1.89% | $262,191 |
| 1064-01-043Let Mar 6, 2024 | TEXAS CORDIA CONSTRUCTION, LLC | HidalgoPharr | WIDEN NON-FREEWAY | 6.4% | $787,424 |
| 7124-01-006Let Mar 5, 2024 | RELMCO, INC. | PresidioEl Paso | MAINTENANCE | 7.11% | $2,036,506 |
| 0161-03-025Let Mar 5, 2024 | DELGADO'S CONTRACTORS, LLC | Val VerdeLaredo | MISCELLANEOUS CONSTRUCTION | 0% | $0 |
| 1803-02-035Let Jan 5, 2024 | ASAGO, LLC | HidalgoPharr | WIDEN NON-FREEWAY | 2.76% | $238,607 |
| 0327-05-041Let Dec 5, 2023 | POSILLICO CIVIL, INC. | KenedyPharr | UPGRADE TO STANDARDS FREEWAY | 0.98% | $1,914,611 |
| 1477-01-043Let Aug 2, 2023 | JORDAN FOSTER CONSTRUCTION, LLC | BexarSan Antonio | WIDEN NON-FREEWAY | 2.22% | $1,581,121 |
| 0037-05-062Let Jun 27, 2023 | RELMCO, INC. | DimmitLaredo | TRAFFIC PROTECTION DEVICES | 15.29% | $471,707 |
| 0291-06-053Let May 4, 2023 | STERLING DELAWARE HOLDING COMPANY | BanderaSan Antonio | WIDEN FREEWAY | 1.38% | $234,728 |
| 2520-01-016Let Mar 8, 2023 | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. | MedinaSan Antonio | BRIDGE REPLACEMENT | 0.75% | $48,813 |