Bid code 7196-6076

TIE-IN (COMPLETE) (24") · per EA Sign up free

‹ All bid codes

$15,133.88Avg low bid / EA
$13,631.38Avg of all bids
$7,738.74Avg engineer's estimate
6Jobs · 22 EA

Average low bid by year

YearJobsQuantityAvg lowAvg all
202411$21,111.44$24,229.42
202315$15,800.00$13,253.02
202211$15,700.00$11,405.52
2021315$14,475.60$13,452.37

Recent low bids

ExcelCSV
Let dateCCSJCounty / DistrictQuantityUnit priceLow bidder
Aug 2, 20240521-06-155 BexarSan Antonio1 EA $21,111.44ZACHRY CONSTRUCTION CORPORATION
Aug 2, 20231477-01-043 BexarSan Antonio5 EA $15,800.00JORDAN FOSTER CONSTRUCTION, LLC
Sep 7, 20221741-02-036 BexarSan Antonio1 EA $15,700.00CAPITAL EXCAVATION COMPANY
Dec 2, 20210849-01-055 BexarSan Antonio3 EA $9,500.00HARPER BROTHERS CONSTRUCTION LLC
Jun 3, 20212452-02-128 BexarSan Antonio6 EA $19,570.00ZACHRY CONSTRUCTION CORPORATION
Mar 5, 20210521-06-138 BexarSan Antonio6 EA $11,869.00WILLIAMS BROTHERS CONSTRUCTION CO., INC.