$1,124.36Avg low bid / EA
$2,005.08Avg of all bids
$1,162.33Avg engineer's estimate
7Jobs · 195 EA
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 27 | $1,700.00 | $4,103.33 |
| 2022 | 2 | 11 | $1,618.18 | $1,946.36 |
| 2021 | 2 | 101 | $769.80 | $1,707.21 |
| 2020 | 1 | 41 | $800.00 | $1,983.33 |
| 2019 | 1 | 15 | $3,000.00 | $1,802.83 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Mar 5, 2024 | 0905-00-130 | LubbockLubbock | 27 EA | $1,700.00 | L&L COMPANY |
| Mar 3, 2022 | 0905-00-102 | LubbockLubbock | 10 EA | $1,100.00 | L&L COMPANY |
| Feb 4, 2022 | 0130-05-085 | LubbockLubbock | 1 EA | $6,800.00 | SACYR CONSTRUCTION USA LLC |
| Oct 7, 2021 | 6390-58-001 | LubbockLubbock | 10 EA | $950.00 | TEXAS PANHANDLE CONSTRUCTION, INC. |
| Feb 5, 2021 | 0905-00-103 | LubbockLubbock | 91 EA | $750.00 | L&L COMPANY |
| Feb 6, 2020 | 0905-00-094 | LubbockLubbock | 41 EA | $800.00 | VIZCAINO, L.P. |
| Sep 5, 2019 | 6348-21-001 | Floyd | 15 EA | $3,000.00 | BARRICADES UNLIMITED |