$5.66Avg low bid / LF
$5.52Avg of all bids
$3.19Avg engineer's estimate
10Jobs · 6,205 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 3 | 1,372 | $8.84 | $6.86 |
| 2023 | 3 | 300 | $4.04 | $6.36 |
| 2021 | 2 | 2,533 | $6.14 | $5.91 |
| 2020 | 1 | 1,000 | $3.20 | $3.82 |
| 2018 | 1 | 1,000 | $3.00 | $3.17 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 5, 2024 | 0067-06-062 | HaleLubbock | 1,172 LF | $9.24 | TI-ZACK CONCRETE, LLC |
| Feb 2, 2024 | 6456-91-001 | HendersonTyler | 100 LF | $10.00 | TRP CONSTRUCTION GROUP, LLC |
| Feb 1, 2024 | 6456-93-001 | WoodTyler | 100 LF | $3.00 | STRIPING TECHNOLOGY, L.P. |
| Nov 2, 2023 | 6456-41-001 | GreggTyler | 100 LF | $3.21 | REYNOLDS & KAY, LTD. |
| Nov 1, 2023 | 6455-27-001 | El PasoEl Paso | 100 LF | $5.70 | SYNERGY PROJECT CONTRACTORS, INC. |
| Nov 1, 2023 | 6456-39-001 | SmithTyler | 100 LF | $3.21 | REYNOLDS & KAY, LTD. |
| Jun 4, 2021 | 0905-00-110 | LubbockLubbock | 1,633 LF | $6.50 | TI-ZACK CONCRETE, INC. |
| Jun 3, 2021 | 0540-08-008 | BrazosBryan | 900 LF | $5.49 | KNIFE RIVER CORPORATION - SOUTH |
| Nov 4, 2020 | 6367-56-001 | BowieAtlanta | 1,000 LF | $3.20 | STRIPING TECHNOLOGY, L.P. |
| Jul 10, 2018 | 6332-57-001 | BowieAtlanta | 1,000 LF | $3.00 | STRIPING TECHNOLOGY, L.P. |