$4.66Avg low bid / LF
$4.44Avg of all bids
$5.78Avg engineer's estimate
13Jobs · 22,128 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2013 | 13 | 22,128 | $4.66 | $4.44 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Nov 6, 2013 | 6262-98-001 | LamarParis | 18,104 LF | $4.35 | STRIPING TECHNOLOGY, L.P. |
| Nov 6, 2013 | 0238-05-039 | ShermanAmarillo | 130 LF | $2.65 | J. LEE MILLIGAN, INC. |
| Nov 6, 2013 | 2075-02-045 | SmithTyler | 352 LF | $5.85 | LONGVIEW BRIDGE AND ROAD, LTD. |
| Oct 9, 2013 | 0405-02-024 | SterlingSan Angelo | 202 LF | $8.21 | PRICE CONSTRUCTION, LTD. |
| Oct 8, 2013 | 2293-01-024 | HaysAustin | 237 LF | $5.50 | DAN WILLIAMS COMPANY |
| Oct 8, 2013 | 0582-02-018 | LipscombAmarillo | 245 LF | $2.27 | RK HALL, LLC |
| Oct 8, 2013 | 3136-01-172 | TravisAustin | 120 LF | $7.40 | AUSTIN BRIDGE & ROAD, LP |
| Sep 11, 2013 | 0251-01-056 | HamiltonWaco | 340 LF | $7.00 | BIG CREEK CONSTRUCTION, LTD. |
| Sep 11, 2013 | 0458-01-022 | HendersonTyler | 400 LF | $5.50 | BIG CREEK CONSTRUCTION, LTD. |
| Sep 11, 2013 | 0700-04-045 | LlanoAustin | 42 LF | $4.96 | ALLEN KELLER COMPANY |
| Sep 11, 2013 | 6262-46-001 | McLennanWaco | 1,500 LF | $6.89 | KNIFE RIVER CORPORATION - SOUTH |
| Sep 10, 2013 | 0259-06-001 | JohnsonFort Worth | 360 LF | $5.43 | LONE STAR CIVIL CONSTRUCTION, INC. |
| Sep 10, 2013 | 2213-01-013 | JohnsonFort Worth | 96 LF | $6.05 | JAY MILLS CONTRACTING, INCORPORATED |